Unincorporated Blount County, Tennessee requires a written building permit before most construction, structural alterations, building moves or changes in use; listed exceptions include interior finishes in certain homes, agricultural uses and accessory farm buildings1. Blount County Development Services enforces the 2018 ICC commercial and residential regulations through plan review and inspections2. Septic permit and completion packages go directly to Blount County Environmental Health34.
At a glance
- Building permit
- Required for most construction; listed agricultural and interior-finish exceptions apply1
- Building code
- Development Services enforces the 2018 ICC edition2
- Zoning
- County zoning applies outside municipal limits56
- Septic permits
- Apply directly to Blount County Environmental Health34
- Owner-builder
- One permit every two years for an owner-used home not for sale, lease or rent7
- Rural District 2 lot size
- Five acres per unit unless another provision expressly requires otherwise8
- Manufactured homes
- One or two dwellings are permitted on one Rural District 2 lot9
- RV or tiny-home living
- Not confirmed countywide; ask the Building Commissioner for the parcel's district rule10
Who to call
Building permits
Blount County Development Services (Office of the Building Commissioner)
Building permits, plan review, inspections, occupancy certificates and zoning enforcement for unincorporated Blount County
303 McGhee Street, Maryville, TN 37801
Planning & zoning
Blount County Planning Department
Staff support to the Planning Commission and general land-use planning for the county
1221 McArthur Road, Maryville, TN 37804
Septic permits
Blount County Department of Environmental Health
Subsurface sewage disposal (septic) permits and private water supply bacteriological testing
1221 McArthur Road, Maryville, TN 37804
Zoning
Zoning Regulations of Blount County, Tennessee
The county's adopted zoning ordinance text, administered by the Building Commissioner
Contact details are copied from each office’s official page and were checked against it on September 29, 2026.
Do you need a building permit in Blount County, Tennessee?
Blount County requires a written permit before most building erection, structural alteration, building moves or changes in the use of a building or land1. Maintenance and interior finishes in one- or two-family homes, agricultural uses, accessory farm buildings and home gardening are listed exceptions1. Development Services applies the 2018 ICC commercial and residential regulations through plan review and inspections2. After all required inspections are complete and fees are paid, the contractor named on the permit receives a Certificate of Occupancy or Certificate of Completion11. A Tennessee owner may obtain one permit every two years to build a residence for personal use, provided the home is not for sale, lease or rent; hiring a contractor changes the licensing obligations7.
Who is the Blount County building department, and how do you reach it?
Blount County Development Services, through the Office of the Building Commissioner, issues building permits and enforces zoning10. The office is at 303 McGhee Street, Maryville, TN 37801; call 865-681-9301 or email [email protected]10. For zoning administration and building inspections, start there. The Blount County Planning Department supports the Planning Commission and provides general planning services12. Planning is at 1221 McArthur Road, Maryville, TN 37804 and uses 865-681-930112. Properties inside a municipality need a separate check with that city because the county zoning resolution applies outside municipal limits6.
Does Blount County have zoning?
Blount County zoning applies throughout the county outside municipal limits6. The exact district matters. In R-2 Rural District 2, one or two single-family or manufactured-home dwellings may occupy one lot9. R-2 development generally requires five acres per unit unless another provision expressly requires otherwise, and structures generally may not rise more than 35 feet above the highest adjacent natural grade unless another article allows it813. Vacation cabin rentals and tourist accommodations are special exceptions in R-2 rather than automatically permitted uses14. Tennessee's agricultural zoning protection is conditional: the structure must be on land devoted to agriculture and incidental to that enterprise, with exclusions for certain locations including the one-hundred-year floodplain15. Ask the Building Commissioner to identify the parcel's district before treating any R-2 standard as applicable108.
How do septic permits work in Blount County?
Blount County Environmental Health operates under Tennessee groundwater-protection rules and receives septic permit and Certificate of Completion packages directly because Blount is a contract county163. A septic construction permit is required for a new system or repair, and the county provides the local application417. Final inspection is required; when statutory conditions are met, a third-party water-resources engineer may perform it instead of the department or county and must submit the report within five business days18. Only about 20% of county soils are rated without severe limitations for a conventional drain field, so establish system feasibility before relying on a homesite19. If a qualifying bonded utility has sewer along the abutting public way, Tennessee law may allow that utility to require the building to connect20.
Can you live in an RV or tiny home on land in Blount County?
We could not confirm a countywide rule allowing or prohibiting full-time occupancy of an RV or tiny home on an individual Blount County parcel. The ordinance language held by the county addresses commercial RV parks, where mobile homes and permanent residences are prohibited except for a resident manager's structure, but that does not answer occupancy on a private residential or agricultural lot6. Manufactured homes have a clearer answer in one district: R-2 allows one or two single-family or manufactured-home dwellings on one lot9. That district-specific permission should not be read as countywide approval. Before placing any RV, tiny home or manufactured home, ask the Building Commissioner to confirm the parcel's zoning district, allowed occupancy and permit path10.
Building a home in Blount County: the steps, in order
- Ask the Building Commissioner to identify the parcel's zoning district and applicable dimensional standards10.
- Confirm septic feasibility and submit the construction-permit package directly to Blount County Environmental Health34.
- Decide whether a licensed contractor or Tennessee's owner-builder path applies; the owner-builder allowance is limited to one permit every two years for a personal residence not intended for sale, lease or rent7.
- Submit plans and obtain the written county building permit before starting covered work1.
- If access connects to a state-highway right-of-way, obtain the required TDOT entrance permit21.
- Complete building and septic inspections, pay outstanding fees and obtain the applicable occupancy or completion certificate before occupancy1118.
What should you check before buying land in Blount County?
Start with zoning: confirm whether the tract is outside municipal limits, then get its district from the Building Commissioner610. Do not apply R-2's five-acre-per-unit or 35-foot standards to a parcel until its district is verified813. Establish septic feasibility early because only about 20% of county soils are rated without severe limitations for a conventional drain field19. Confirm whether sewer connection is available or may be required, since the statewide authority applies only under specific utility and frontage conditions20. For road access, a state-highway driveway requires a TDOT entrance permit, while we could not confirm a countywide driveway-approval rule for other roads21. Also ask Environmental Health about private-well requirements because we could not confirm a county well-permit rule16.
Watch-outs
- R-2 Rural District 2 standards are not countywide defaults; verify the parcel's zoning district before relying on its five-acre lot rule, manufactured-home permission, height limit or vacation-rental process891314.
- A building permit does not finish the process: covered work must pass required inspections, all fees must be paid and the applicable occupancy or completion certificate must be issued11.
- Blount County receives septic permit and completion packages directly, and a final septic inspection is part of the process318.
Sources
- Development Services, quoted and re-checked
- Development Services, quoted and re-checked
- Environmental Health, quoted and re-checked
- Forms & Applications, quoted and re-checked
- Zoning Regulations of Blount County, Tennessee (2026 county census)
- Zoning Regulations of Blount County, Tennessee (blounttn.gov)
- Can I build my own home without a license? (Tennessee statewide rule), quoted and re-checked
- Blount County Zoning Regulations, quoted and re-checked
- Blount County Zoning Regulations, quoted and re-checked
- Blount County Development Services (Office of the Building Commissioner) (blounttn.gov)
- Permitting Process Reference Manual, quoted and re-checked
- Blount County Planning Department (blounttn.gov)
- Blount County Zoning Regulations, quoted and re-checked
- Blount County Zoning Regulations, quoted and re-checked
- Exemption from County Zoning Regulation for Buildings on Land Used for Agriculture, Opinion No. 22-07 (Tennessee statewide rule), quoted and re-checked
- Blount County Department of Environmental Health (blounttn.gov)
- Septic System Construction Permit (Tennessee statewide rule), quoted and re-checked
- Third-Party Permits & Final Inspections for Subsurface Sewage Disposal Systems, quoted and re-checked
- Share of soils without severe limits for a conventional septic drain field (USDA SSURGO): Bolthole Index county data
- Utility Customers Frequently Asked Questions (Tennessee statewide rule), quoted and re-checked
- Highway Entrance Permits (Tennessee statewide rule), quoted and re-checked
Written September 29, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.