Unincorporated Madison County, Illinois requires a building permit before covered construction begins, and the county reviews plans and inspects work at selected milestones12. County zoning also regulates land use in designated districts3. The county reviews and approves private sewage systems, but we could not confirm the complete permit and inspection process4.
At a glance
- Building permit
- Required before covered construction begins in unincorporated Madison County1
- Zoning
- County zoning applies in unincorporated Madison County3
- Septic approval
- County review and approval apply; ask Planning & Development for the current permit and inspection steps4
- Water well permit
- Required; the county ordinance lists a $100 non-refundable water-well permit fee5
- RV or tiny-home living
- A general private-land occupancy rule could not be confirmed; ask Zoning Administration for the parcel's district rule6
- Owner-builder exemption
- Could not be confirmed; ask Building & Zoning before relying on one7
- Minimum lot size
- County rules include minimum lot specifications, but the parcel's numeric minimum must be confirmed8
- Conventional septic soils
- Only 9.2% of county soils are rated without severe limitations9
Who to call
Building permits
Madison County Building & Zoning Department — Building Permits & Inspections
Building permit applications, plan review and construction inspections in unincorporated Madison County
157 N. Main Street, Suite 254, Edwardsville, IL 62025
Zoning
Madison County Zoning Administration
Zoning administration, map amendments, special-use permits and variances
157 N. Main Street, Suite 254, Edwardsville, IL 62025
Septic permits
Madison County Planning & Development — Private Sewage Permits & Inspections
Private sewage permits, installation inspections and installer licensing
157 N. Main Street, Suite 254, Edwardsville, IL 62025
Contact details are copied from each office’s official page and were checked against it on September 29, 2026.
Do you need a building permit in Madison County, Illinois?
Yes. Covered construction in unincorporated Madison County requires a building permit before work starts1. The contractor submits project plans, waits for county review and permit issuance, and then may begin construction10. Inspectors check work at selected milestones for code compliance2. Madison County has adopted and administers building codes for unincorporated areas, including the listed international, electrical, Illinois plumbing and private-sewage codes11. Ask Building & Zoning which project types require permits and what the current application documents and fees are, because the available county material does not provide the complete packet, fee schedule or all exceptions10.
Who is the Madison County building department, and how do you reach it?
Madison County Building & Zoning handles building-permit applications, plan review and construction inspections in unincorporated Madison County12. The office is at 157 N. Main Street, Suite 254, Edwardsville, IL 62025, and its main number is (618) 296-620012. Email the building-permit office at [email protected]12. Submit plans before work begins and do not start until the county has reviewed them and issued the permit10. Once construction starts, coordinate inspections at the selected milestones2. We could not confirm an owner-builder exception, so ask Building & Zoning whether an owner may apply or perform work without the contractor described in the county process7.
Does Madison County have zoning?
Yes. Madison County zoning regulates land use and development in unincorporated areas through designated districts with permitted and special uses3. Confirm the parcel's district with Zoning Administration before deciding that a house, manufactured home, accessory use or other project is allowed6. County zoning and subdivision rules include minimum lot specifications, but the available county fact does not state the numeric limits8. We also could not confirm a general minimum dwelling size, maximum building height, lot-coverage limit or countywide setback. Ask Zoning Administration for the parcel's dimensional schedule and whether a variance or special-use permit is needed. Incorporated municipalities may apply different rules, so first confirm whether the land is inside municipal limits3.
How do septic permits work in Madison County?
Madison County Building & Zoning reviews and approves private sewage systems and enforces the private sewage code4. The county's current fact identifies Planning & Development as the authority, but we could not confirm the complete permit application or required inspection sequence; ask the private-sewage office for the current steps before committing to a building site13. Illinois requires approval of plans by the applicable authority before a new private sewage system is built14. Only 9.2% of Madison County soils are rated without severe limitations for a conventional drain field, so make soil suitability an early contingency in a land purchase9. Do not assume acreage alone makes a parcel buildable; septic approval and zoning are separate reviews43.
Can you live in an RV or tiny home on land in Madison County?
We could not confirm a general Madison County rule allowing long-term RV occupancy, temporary camping or tiny-home occupancy on private land. Unincorporated land is divided into zoning districts with permitted and special uses, so ask Zoning Administration whether the parcel's district allows the proposed structure and residential use6. Illinois campground rules apply to qualifying campgrounds and do not establish a general right to occupy an RV on a private parcel15. A tiny home also does not bypass building review: covered construction in unincorporated Madison County requires a permit, adopted building codes apply, and private sewage systems require county approval1114. Get written zoning and sewage answers before placing or buying the unit.
Building a home in Madison County: the steps, in order
- Confirm that the parcel is unincorporated, then ask Zoning Administration for its district, allowed use and dimensional requirements36.
- If the parcel will be divided, ask about preliminary-plat, improvement-plan and final-plat review before relying on a proposed lot line16.
- Submit the private-sewage proposal to Planning & Development for review and approval; ask which permit and inspections apply4.
- Obtain the required water-well permit before construction or deepening, and arrange the required pre-work notice517.
- Submit project plans and the building-permit application, then wait for review and issuance before starting10.
- Coordinate the required building inspections at selected milestones2.
- Ask Building & Zoning what final occupancy approval applies because we could not confirm a county certificate-of-occupancy requirement.
What should you check before buying land in Madison County?
Start with jurisdiction and zoning because county rules apply to unincorporated land, while incorporated municipalities may administer their own ordinances3. If a seller proposes a split, confirm subdivision review and the applicable minimum lot specifications before treating it as a buildable parcel168. Check sewage feasibility early because only 9.2% of county soils are rated without severe limits for a conventional drain field, and private systems need county review and approval94. Water-well construction or deepening requires a permit, with a $100 non-refundable county fee, and the Health Department must receive at least 48 hours' notice before covered work begins517. County driveway access and floodplain-development procedures could not be confirmed, so identify the road authority and ask Planning & Development about floodplain review before closing.
Watch-outs
- Madison County's owner-builder exception, if any, could not be confirmed; ask Building & Zoning before assuming the owner may replace the contractor named in the permit process7.
- Madison County reviews and approves private sewage systems, but the complete permit and inspection sequence could not be confirmed; ask Planning & Development before choosing a house site4.
- A driveway onto an Illinois state-maintained roadway requires IDOT approval before right-of-way work begins18.
Sources
- Building Permits & Inspections, quoted and re-checked
- Building Permits & Inspections, quoted and re-checked
- Zoning Administration, quoted and re-checked
- Private Sewage - Permits, Inspections & Complaints, quoted and re-checked
- Madison County water well ordinance, quoted and re-checked
- Zoning Administration, quoted and re-checked
- (2026 county census)
- Zoning Administration, quoted and re-checked
- Share of soils without severe limits for a conventional septic drain field (USDA SSURGO): Bolthole Index county data
- Building Permits & Inspections, quoted and re-checked
- Building Permits & Inspections, quoted and re-checked
- Madison County Building & Zoning Department — Building Permits & Inspections (madisoncountyil.gov)
- Building and Zoning Code Enforcement, quoted and re-checked
- 77 Ill. Adm. Code 905.190 Installation Approval (Illinois statewide rule), quoted and re-checked
- Youth Camps and Campgrounds (Illinois statewide rule), quoted and re-checked
- Subdivision Platting, quoted and re-checked
- Madison County water well ordinance, quoted and re-checked
- Highway Permits (Illinois statewide rule), quoted and re-checked
Written September 29, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.