Potter Township, Centre County, Pennsylvania zones its own land through a township zoning ordinance with agricultural and rural residential districts1. Building permits follow the state Uniform Construction Code and come from one of the code agencies the township lists23. Septic permits come from a local sewage agency under the state sewage facilities program; we could not confirm which one covers Potter Township4.
At a glance
- Zoning
- Yes, township zoning ordinance with mapped districts15
- Building permit
- Required under the state Uniform Construction Code; township lists its code agencies26
- Who issues building permits
- Your choice of the code agencies the township lists3
- Septic
- Local sewage agency under state program; township contact unconfirmed4
- Minimum lot, rural residential
- 1 acre, less with public water or sewer7
- Minimum lot, agricultural
- 20 acres, with a 2-acre house-lot exception8
- Owner-builder
- No statewide contractor license for most work9
Who to call
Planning & zoning
Township office for Potter Township; first call for zoning questions and the zoning map
124 Short Road, Spring Mills, PA 16875
Building permits
Penns Valley Code Enforcement Agency (one of three code agencies Potter Township lists)
Uniform Construction Code building permits and inspections; the township also lists Bureau Veritas and Keystone Inspection Agency
225 East Main Street P.O. Box 357 Millheim, PA 16854
Contact details are copied from each office’s official page and were checked against it on October 14, 2026.
Off-grid gear
Going off-grid in Potter Township means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Does Potter Township, PA have zoning, and what does it mean for lot size and setbacks?
Potter Township has its own zoning ordinance, divided into districts that include Agricultural (A) and Rural Residential (RR)15. Centre County itself has no countywide zoning ordinance, so the township, not the county, decides what you can build10.
In the Agricultural district the base lot is 20 acres, but a parcel may be cut down for a single-family dwelling to 2 acres or, under the second option, 1-acre lots with conditions, and no further subdivision is then allowed8. A perc test and soil log are required before a zoning permit there8. In Rural Residential, non-agricultural uses need 1 acre unless public water or sewer is available7.
Setbacks measured from the road center line are 65 feet in both districts1112. Agricultural side yards are 35 feet and rear yards 50 feet11; Rural Residential side and rear yards are 25 feet12. Building coverage is capped at 25% in both1314.
Do you need a building permit in Potter Township, and who issues it?
Yes. Potter Township has adopted the state Uniform Construction Code as its building code2, and the state requires a permit before any covered work starts6. Centre County does not issue these permits for you; the township lists its code agencies instead3.
The township offers three options for building code administration and lets applicants choose which agency to work with3. The Penns Valley Code Enforcement Agency in Millheim is one of them, alongside Bureau Veritas and Keystone Inspection Agency3. Each agency has its own fee schedule, so ask the agency you pick what a permit costs3.
A certificate of occupancy must be issued before a building can be used15. Inside the township's floodplain overlay, both the floodplain ordinance and the underlying zoning district must be met16.
How do septic permits work in Potter Township?
Pennsylvania requires a permit from the local agency before an on-lot sewage system is installed or a building served by one is occupied4. Local agencies are municipalities, groups of municipalities or county health departments, so the agency differs from place to place17.
We could not confirm which agency issues septic permits for Potter Township. Zoning in the Agricultural district requires a perc test and soil log before the zoning permit, and the lot must meet Act 537 and the township's sewage ordinance8. Call the Potter Township Office to find out who runs the program18.
Soil matters here: about 16% of Centre County soils rate as not limited for a conventional drain field, so many lots need a site evaluation or an engineered system19. The state's 10-acre exemption for an owner's or immediate family's residence has strict owner-of-record and siting conditions, so confirm it with the local agency before relying on it4.
Can you live in an RV or tiny home on your land in Potter Township?
We could not confirm the township's rule on living in an RV or tiny home on private land. The township's zoning ordinance governs where dwellings and temporary uses are allowed, so ask the Potter Township Office before parking or placing either one18.
State rules about RV stays cover state park campgrounds, not your own parcel, and do not answer this question20. For manufactured housing, the state building code still applies to additions, resale and relocation, but it does not settle local zoning or septic approval21.
Building a home in Potter Township: the steps, in order
- Confirm the district on the township zoning map and check lot size and setbacks with the Potter Township Office185.
- In the Agricultural district, get the perc test and soil log done before the zoning permit8.
- Find who issues septic permits for the township and apply with them4.
- If the driveway meets a state highway, apply for a PennDOT Highway Occupancy Permit22.
- Choose one of the township's code agencies and apply for the building permit3.
- Build to the permit and schedule inspections; foundations, systems, framing and a final inspection are covered23.
- Get the certificate of occupancy before moving in24.
Pennsylvania has no statewide licensing for most construction contractors, though municipalities may add their own9.
What to check before you buy land in Potter Township
Which district the parcel sits in decides almost everything: Agricultural land is set up for large lots, and Rural Residential allows smaller ones87. Ask the Potter Township Office whether the parcel touches the floodplain overlay1618.
If you plan to split the land, the county's subdivision ordinance applies only where a municipality has not adopted its own, so ask the township which applies25. Private wells are not covered by a state construction standard, and the township code has a chapter on wells that we could not review26.
County-level figures: wooded land covers about 81% of Centre County27, and the effective property tax rate is about 1.1%28.
Watch-outs
- We could not confirm who issues septic permits for Potter Township or whether the township runs an on-lot sewage management program; call the Potter Township Office before you sign a purchase contract18.
- Each of the township's code agencies sets its own permit fees, so get quotes from the agency you choose3.
- Rules for RVs, tiny homes and accessory dwellings were not confirmed for the township; ask the Potter Township Office18.
- A driveway onto a state highway needs a PennDOT Highway Occupancy Permit, separate from the building permit22.
Sources
- Chapter 220 Zoning, Article II Zoning Districts - Township of Potter, PA (Potter Township), quoted and re-checked
- Chapter 83 Construction Codes, Uniform - Township of Potter, PA (Potter Township), quoted and re-checked
- Penns Valley Code Enforcement Agency (one of three code agencies Potter Township lists) (pottertownship.org)
- 25 Pa. Code § 72.22. Permit issuance (Pennsylvania statewide rule), quoted and re-checked
- Chapter 220 Zoning, Article II Zoning Districts - Township of Potter, PA (Potter Township), quoted and re-checked
- Apply for a Uniform Construction Code Building Permit, quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Contractor Licensing (Pennsylvania statewide rule), quoted and re-checked
- Centre County Housing, quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Chapter 220 Zoning, district regulations - Township of Potter, PA (Potter Township), quoted and re-checked
- Apply for a Uniform Construction Code Building Permit, quoted and re-checked
- Chapter 220 Zoning, Article II Zoning Districts - Township of Potter, PA (Potter Township), quoted and re-checked
- Act 537 Sewage Facilities (Pennsylvania statewide rule), quoted and re-checked
- Potter Township Office (pottertownship.org)
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- RV and Tent Campsites (Pennsylvania statewide rule), quoted and re-checked
- Pennsylvania Uniform Construction Code, Chapter 403 (Pennsylvania statewide rule), quoted and re-checked
- Apply for a PennDOT Highway Occupancy Permit (Pennsylvania statewide rule), quoted and re-checked
- Part XIV, Uniform Construction Code, Chapter 403 Administration (Pennsylvania statewide rule), quoted and re-checked
- Part XIV, Uniform Construction Code, Chapter 403 Administration (Pennsylvania statewide rule), quoted and re-checked
- Subdivision & Land Development, quoted and re-checked
- Apply for a Water Well Drillers License and Rig Permit (Pennsylvania statewide rule), quoted and re-checked
- Wooded share of land: Bolthole Index county data
- Effective property tax rate: Bolthole Index county data