The Town of Bedford, New Hampshire requires a building permit for construction, alteration, relocation or any excavation, issued by the town's building code official1. Bedford adopts and enforces its own zoning in Chapter 275 of the town code2. Septic and well permits come from the town building/health department, and septic designs also need state approval34.
At a glance
- Building permit
- Required from the town building code official, including for excavation1
- Zoning
- Town zoning ordinance (Chapter 275), enforced by the zoning administrator2
- Certificate of occupancy
- Required before a new or altered building is used5
- Septic
- Town permit first, then state NHDES approval63
- Wells
- Town permit required before work starts4
- Permit fees
- Listed in the town building department handbook, not in the code7
- Zoning details (RV, tiny home, lot size, setbacks)
- Set by Bedford district tables; ask the town zoning administrator8
Who to call
Building permits
Town of Bedford Building Code Compliance
Building permits, inspections and certificates of occupancy inside Bedford town limits
55 Constitution Drive
Septic permits
New Hampshire Department of Environmental Services, Subsurface Systems Bureau
State approval of septic designs, for Bedford as for every New Hampshire town
29 Hazen Drive, Concord, NH 03302-0095
Contact details are copied from each office’s official page and were checked against it on October 24, 2026.
Off-grid gear
Going off-grid in Town of Bedford means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Bedford, New Hampshire?
Yes. Bedford's town code says no building or structure may be constructed, reconstructed, altered or relocated, and no excavation may start, without a building permit from the town's building code official1. Applications are made on standard forms available at the town offices9.
Before a permit issues, the applicant must show certified verification of all requisite local, state and federal approvals, and wetlands must be flagged by a New Hampshire certified wetlands scientist before construction1. Footings and foundations must be certified by a New Hampshire licensed land surveyor unless the building code official waives it1.
New Hampshire's state building code applies to all construction, and Bedford enforces it through its local process1011. We could not confirm which code editions the town lists or its owner-builder rules; ask the building office.
Who issues building permits in Bedford, and how do you reach them?
The Town of Bedford's Building Code Compliance office at 55 Constitution Drive handles building permits, inspections and certificates of occupancy; call 603-472-383812. The town publishes an inspection policy and a request process on its website12.
Before anyone may use a new or altered building, the building code official must issue a certificate of occupancy, and a plat plan certified by a New Hampshire licensed land surveyor is required unless waived for good cause5. Fee amounts are not in the code; the town building department handbook, available at the town offices, lists them7.
Does Bedford, NH have zoning?
Yes. Bedford administers its own Chapter 275 Zoning ordinance, enforced by the town zoning administrator2. New Hampshire law leaves zoning to municipal government, and counties zone only where they hold unincorporated towns or unorganized places, so Hillsborough County does not set Bedford's rules13.
We could not confirm Bedford's district map, minimum lot sizes, setbacks, minimum home size, or its rules on RVs, tiny homes, manufactured homes and accessory dwellings. These sit in the town's zoning use and dimensional tables, so ask the Bedford zoning administrator before you buy or plan a build. New Hampshire sets no single statewide lot size or setback; both depend on the local district8.
How do septic permits work in Bedford, NH?
Septic work inside Bedford needs two approvals. The town requires a permit from the building/health department before any work on a sewage disposal system begins6. New septic designs must also be reviewed and approved by the Bedford health department before state approval3.
The state approval comes from the New Hampshire Department of Environmental Services, which issues an approval for construction and an approval for operation, and you need both before using the system14. Final inspection is required before the system is covered or placed in operation15.
In Hillsborough County, USDA rates about 7% of soils as not limited for a conventional drain field, so expect a site evaluation and possibly an engineered system16. A homeowner building a new domicile may install their own system without an installer's permit if they file a 2-year domicile affidavit, though state plan approval is still required17.
Do you need a well permit in Bedford?
Yes. Bedford requires a permit from the building/health department before any work begins on a private well4. The application must include a scaled diagram of the existing or proposed septic system on that lot and adjacent lots, and a new well must pass bacteria and VOC testing at a New Hampshire certified lab before it goes into service4.
Can you live in an RV or tiny home in Bedford?
We could not confirm Bedford's rules on long-term RV living, camping on private land or tiny homes. Those answers sit in the town's zoning use table, so ask the Bedford zoning administrator. New Hampshire's statewide campground rule covers RVs at licensed campgrounds, for temporary occupancy only, and does not answer whether you can live in an RV on your own lot18.
Building a home in Bedford: the steps, in order
- Ask the zoning administrator which district your lot is in and what it allows.
- Have wetlands flagged by a New Hampshire certified wetlands scientist1.
- Get the town septic permit and state NHDES approval for the design614.
- Get the town well permit4.
- Apply for the building permit on the town's standard forms9.
- Request inspections through Building Code Compliance at 603-472-383812.
- Obtain the certificate of occupancy before moving in5.
What stays with Hillsborough County, and what to check before you buy
Hillsborough County does not issue building permits or set zoning inside Bedford; the town does13. For land outside the town, see the Hillsborough County page.
Before buying, confirm the zoning district, ask whether public sewer is available (we could not confirm Bedford's sewer connection rules), and check floodplain and driveway rules with the town. Statewide, a building within 100 feet of a public sewer must connect to it19. Hillsborough County's effective property tax rate is 1.8%20.
Watch-outs
- We could not confirm Bedford's zoning tables, so lot size, setbacks, RV, tiny home and accessory dwelling rules need a call to the town zoning administrator at the Bedford Town Offices2.
- Bedford's 2026 zoning amendments and its building code editions were not reviewed; ask Building Code Compliance for the current versions2.
- Septic inspection steps and permit fees are in the town building department handbook, which we could not locate; request it at the town offices7.
Sources
- Town of Bedford NH Code, Chapter 275 Zoning, Article XI Administration and Enforcement (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 275 Zoning, Article XI Administration and Enforcement (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 208 Septic Systems and Wells (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 208 Septic Systems and Wells (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 275 Zoning, Article XI Administration and Enforcement (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 208 Septic Systems and Wells (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford NH Code, Chapter 208 Septic Systems and Wells (eCode360) (Town of Bedford), quoted and re-checked
- gc.nh.gov (New Hampshire statewide rule), quoted and re-checked
- Town of Bedford NH Code, Chapter 275 Zoning, Article XI Administration and Enforcement (eCode360) (Town of Bedford), quoted and re-checked
- Chapter 155-A New Hampshire Building Code, quoted and re-checked
- Town of Bedford NH Code, Chapter 275 Zoning, Article XI Administration and Enforcement (eCode360) (Town of Bedford), quoted and re-checked
- Town of Bedford Building Code Compliance (bedfordnh.org)
- gc.nh.gov, quoted and re-checked
- New Hampshire Department of Environmental Services, Subsurface Systems Bureau (des.nh.gov)
- RSA 485-A:29 Submission and Approval of Plans and Specifications (New Hampshire statewide rule), quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- RSA 485-A:36 System Installer Permit, quoted and re-checked
- Chapter 216-I Recreational Campgrounds and Camping Parks (New Hampshire statewide rule), quoted and re-checked
- RSA 147:8 Toilets; Drains (New Hampshire statewide rule), quoted and re-checked
- Effective property tax rate: Bolthole Index county data
Written October 24, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.