For Mount Pleasant Township in Bates County, Missouri, we could not confirm a residential building-permit requirement, building department or township zoning ordinance. Missouri leaves building-code adoption to local governments under a conditional statutory framework.1 Bates County Health Center handles onsite sewage permitting inside the township.2

At a glance

Building permit
Requirement and issuing office not confirmed; ask the township and Bates County before work1
Zoning
No official township zoning ordinance or no-zoning statement was confirmed3
Septic permit
Required for specified new systems, major modifications and repairs through Bates County Health Center4
RV living
Long-term occupancy and temporary-camping rules not confirmed; ask the township before relying on an RV as a dwelling5
Tiny home
Siting, minimum size and occupancy rules not confirmed; septic rules still apply4
Owner-installed septic
Allowed subject to county requirements; inspection is required before covering the system6
Private well
Contractor-performed well work requires state permits; a landowner's own installation has a limited exception78

Who to call

Septic permits

Bates County Health Center - Environmental Health

Onsite sewage permits and inspections in Bates County through the Environmental Public Health Specialist

660-679-6108

P.O. Box 178, 501 N. Orange, Butler, MO 64730

Floodplain permits

Bates County Surveyor's Office

County surveying, county road engineering and floodplain management

(660) 386-7776 Opt 6

103 West Dakota St Rm 6, Butler, MO 64730

Contact details are copied from each office’s official page and were checked against it on October 9, 2026.

Off-grid gear

Going off-grid in Mount Pleasant Township means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Mount Pleasant Township, Missouri?

We could not confirm a Mount Pleasant Township residential building-permit rule, adopted building code, inspection authority or certificate-of-occupancy requirement. Do not treat that gap as a permit exemption. Missouri authorizes local building-code adoption under a conditional framework rather than imposing one uniformly adopted statewide building code.1

Before ordering materials or beginning site work, ask the Mount Pleasant Township clerk and Bates County Commission to identify the office with jurisdiction over the parcel and to provide the controlling ordinance in writing. Ask separately about a building permit, electrical or other trade approvals, inspections and permission to occupy the completed home. Missouri's county building authority is limited and conditional, so the state statute alone does not answer what this township requires.9

Who issues building permits in Mount Pleasant Township?

No official page we could confirm identifies a Mount Pleasant Township building department, building inspector or residential building-permit application. Start with the township clerk, then ask the Bates County Commission whether any county-administered approval applies to the parcel. Get the answer in writing before construction begins.

Keep the approval lanes separate. Bates County Health Center handles onsite sewage permitting through its Environmental Public Health Specialist.10 The Bates County Surveyor's Office handles county floodplain management and county road engineering.11 Those offices do not become a general building department merely because their approvals may affect a home site. Ask the identified building authority for its application, plan list, fee schedule, inspection sequence and occupancy rule; none of those township-specific items was confirmed.

Does Mount Pleasant Township have zoning?

We could not confirm an official Mount Pleasant Township zoning ordinance, zoning map or statement that the township has no zoning. Missouri law allows qualifying counties to adopt zoning for unincorporated land after voter approval, but that authority does not prove that Bates County or Mount Pleasant Township adopted a zoning program.3

Before buying, ask the township clerk and Bates County Commission for a written parcel-specific answer on allowed uses, setbacks, minimum lot size, building height, lot coverage, dwelling size, accessory dwellings and manufactured homes. The absence of a zoning page is not evidence that a parcel is unrestricted. Agricultural exemptions are also narrow: Missouri protects qualifying farm structures from certain county rules, but the cited exemptions do not erase septic, floodplain or every other land-use requirement.1213

How do septic permits work inside Mount Pleasant Township?

Bates County Health Center is the onsite-wastewater authority inside Mount Pleasant Township.2 County rules require a permit for covered new systems, major modifications and repairs; a completed application needs a site drawing plus a certified percolation test or soil-morphology evaluation, and construction begins only after the Environmental Public Health Specialist issues the green construction permit.4

The county rules provide a limited exception for some single-family residences on tracts over 3 acres, but the system must still meet county standards and a second system has separate conditions.4 The system must remain uncovered until the Environmental Public Health Specialist inspects and approves it.6 Countywide soil data show no mapped share without severe limitations for a conventional septic drain field, so resolve the soil evaluation before fixing the house site.14

Can you live in an RV or tiny home in Mount Pleasant Township?

We could not confirm a Mount Pleasant Township rule allowing or prohibiting long-term RV occupancy, temporary camping, tiny-home occupancy, manufactured homes or accessory dwellings. Ask the township clerk and Bates County Commission for the rule applying to the parcel before buying or placing a unit. Do not use Missouri's campground rules as an answer to private residential RV occupancy; the confirmed state claim only says developments such as campgrounds using onsite wastewater need DNR approval.5

A small or movable dwelling does not avoid wastewater rules. Covered onsite systems still require Bates County approval, and the county process may require a soil evaluation, construction permit and inspection before covering.46 Ask separately about legal occupancy, utility connections, setbacks, minimum dwelling size and any certificate needed before moving in, because those township-specific answers were not confirmed.

Building a home in Mount Pleasant Township: what are the steps?

  1. Ask the Mount Pleasant Township clerk and Bates County Commission to identify the building and zoning authority and provide every parcel-specific rule in writing.
  2. Check the flood map before choosing the house site; development in a mapped Special Flood Hazard Area requires a floodplain development permit before work proceeds.15
  3. Confirm the road owner. A driveway built or modified within MoDOT right-of-way requires a MoDOT permit; township-road access requirements remain unconfirmed.16
  4. Contact Bates County Health Center, complete the required site evaluation and obtain the green septic construction permit before starting covered work.4
  5. Confirm the well installer and permit path; contractor-performed well work requires state permits, while a landowner's own installation has a limited exception.78
  6. Obtain every confirmed approval and keep the septic system uncovered until county inspection.6

What should you check before buying land in Mount Pleasant Township?

Get written answers on zoning, building permits, setbacks, minimum lot size, legal dwelling types, RV occupancy and township-road access before closing; those township-specific rules could not be confirmed. For wastewater planning, Bates County's soil data show no mapped share without severe limitations for a conventional septic drain field.14 Budget for a certified soil or percolation evaluation before fixing the house site.4

Check the FEMA flood map and consult the Bates County Flood Plain Manager before placing a house, manufactured home, fill or other development in a mapped hazard area.15 Verify whether the access point meets a township road or MoDOT right-of-way, because MoDOT access work has its own permit.16 Bates County's effective property-tax rate is about 0.6%, and its median annual property-tax bill is about $962.1718

Watch-outs

  • Do not assume that the absence of a published Mount Pleasant Township zoning or building page means the parcel is unrestricted; ask the township and Bates County for the controlling rules.3
  • Bates County's septic permit exception for some larger single-family tracts does not waive county installation standards.4
  • Bates County's mapped soils show no share without severe limitations for a conventional septic drain field, so complete the soil evaluation early.14
  • A driveway in MoDOT right-of-way requires a state permit, while a township-road driveway requirement could not be confirmed.16

Sources

  1. RSMo Section 64.170 (Missouri statewide rule), quoted and re-checked
  2. OWTS Construction Permit Process (Mount Pleasant Township), quoted and re-checked
  3. RSMo § 64.850 — County commission may prescribe zoning regulations (Missouri statewide rule), quoted and re-checked
  4. BATES COUNTY ON-SITE SEWAGE RULES AND REGULATIONS, quoted and re-checked
  5. OWTS Construction Permit Process (Missouri statewide rule), quoted and re-checked
  6. Bates County On-Site Sewage Rules and Regulations, quoted and re-checked
  7. Water Wells - PUB2945, quoted and re-checked
  8. Water Wells - PUB2945, quoted and re-checked
  9. RSMo Section 64.170 — County commissions control construction; issue building permits (Missouri statewide rule), quoted and re-checked
  10. Environmental Health – Bates County Health Center (Mount Pleasant Township), quoted and re-checked
  11. Bates County Surveyor's Office (batescounty.net)
  12. RSMo Section 64.003 — Farm buildings and farm structures (Missouri statewide rule), quoted and re-checked
  13. RSMo Section 64.890 — Building and land use restrictions; exemptions (Missouri statewide rule), quoted and re-checked
  14. Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
  15. Bates County Surveyor’s Office – Bates County Courthouse, quoted and re-checked
  16. Permits – Missouri Department of Transportation, quoted and re-checked
  17. Effective property tax rate: Bolthole Index county data
  18. Median property tax bill: Bolthole Index county data

Written October 9, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Mount Pleasant Township

Mount Pleasant Township’s own rules

  • Who permits septicCounty (with conditions)

    Onsite wastewater permitting inside Mount Pleasant township is handled by the Bates County Health Center, the county ordinance authority.

    • The Missouri DHSS page identifies Bates County Health Center as the Bates County authority type Ordinance.
    • Incorporated areas may be treated differently; this claim concerns land inside Mount Pleasant township.
    “Agency: Bates County Health Center Authority Type: Ordinance Address: 501 N. Orange PO Box 178 Butler, MO 64730 County: Bates Phone: (660) 679-6108 Website: www.batescountyhealthcenter.org Alert: Contact the agency above for onsite wastewater permitting instructions. This county has their own Onsite Wastewater Ordinance and may have additional requirements beyond the state minimum construction standards.”
  • Septic permitRequired

    Onsite wastewater systems inside Mount Pleasant township administered through the Bates County Health Center ordinance authority.

    • A construction permit is required before installing or repairing most onsite wastewater systems.
    • Missouri DHSS states that some single-family residential lots may be exempt.
    • For residential property under three acres, DHSS states a construction permit is required, but the under-three-acre exemption rule does not apply in some counties; the county authority must be checked.
    • Non-residential onsite systems require a permit regardless of property size.
    • The Bates County ordinance may impose additional requirements beyond state minimum standards.
    • Effective August 28, 2026, Missouri DHSS states that application fees for onsite sewage disposal construction, modifications, and repairs are temporarily suspended pending new standards.

    residential property threshold: < 3 acres (DHSS states the rule does not apply in some counties; check the county authority)

    “A construction permit is required before installing or repairing most onsite wastewater treatment systems (OWTS). Some single family residential lots may be exempt from permitting.”
    One more reviewed finding on this topic
    • Required — Installing or repairing most onsite wastewater treatment systems inside Mount Pleasant township.
      “A construction permit is required before installing or repairing most onsite wastewater treatment systems (OWTS). Some single family residential lots may be exempt from permitting. The first step of the permitting process is to determine the agency that has permitting authority where the work is being done.”
  • Subdividing landRegulated (with conditions)

    Subdivision or development of property inside Mount Pleasant township.

    • DNR residential development regulations apply.
    • The Missouri onsite sewage law also applies.
    • The source does not identify the specific subdivision-plat procedure or thresholds for Bates County.
    “Anyone subdividing or developing property must comply with DNR residential development regulations as well as the onsite sewage law.”

Rules another office applies inside Mount Pleasant Township

Mount Pleasant Township does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Well permitRequired

    Water-well construction or repair serving property inside Mount Pleasant township.

    • Missouri DNR states that a non-restricted water-well installation permit is required to construct or repair a water well.
    • Landowners may install their own well or pump without a permit under the cited law and rules.
    • A separate pump-installation permit is required for installing or replacing a pump and for certain plumbing/electrical work from the well to the structure.
    “A non-restricted water well installation permit is required to construct or repair a water well in Missouri. A non-restricted pump installation permit is required to install or replace a pump in a water well. A non-restricted pump installation permit is also needed to install or repair the plumbing and electrical lines from the well to the point of entry in the structure. Landowners may install their own well or pump without a permit pursuant to the above mentioned law and rules.”
    One more reviewed finding on this topic
    • Limited — Water-well construction, repair, and pump installation inside Mount Pleasant township.
      “A non-restricted water well installation permit is required to construct or repair a water well in Missouri. A non-restricted pump installation permit is required to install or replace a pump in a water well. A non-restricted pump installation permit is also needed to install or repair the plumbing and electrical lines from the well to the point of entry in the structure.”
  • Building in a floodplainRequired

    Development in a mapped floodplain inside Mount Pleasant township; Bates County lists Bill Lethcho as the county floodplain administrator.

    • Some type of permit must be issued for all development in the floodplain.
    • Development in a regulatory floodway also requires an engineering No-Rise Certificate before the floodplain development permit may be issued.
    • The Bates County floodplain administrator is listed as Bill Lethcho.
    “Regardless, some type of permit MUST be issued for ALL development in the floodplain.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Mount Pleasant Township or Bates County directly.

  • Building permit — New residential construction inside Mount Pleasant township.
  • Owner-builder exemption — Owner-builders constructing inside Mount Pleasant township.
  • Building code adopted — Building-code adoption for land inside Mount Pleasant township.
  • Inspections — Building inspections inside Mount Pleasant township.
  • Certificate of occupancy — Certificates of occupancy for buildings inside Mount Pleasant township.
20 more unanswered
  • Local zoning
  • Zoning districts
  • Minimum dwelling size
  • Minimum lot size
  • Setbacks
  • Lot coverage
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Septic inspection
  • Off-grid sanitation
  • Mandatory utility hookup
  • Agricultural exemption
  • Driveway access
  • Short-term rentals
  • Permit fees
  • Permit process

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Mount Pleasant Township publishes no rule on the point, not that none exists. Bates County’s page lists the county offices to call.