New one- and two-family homes in the Village of Union Center, Wisconsin need a Uniform Dwelling Code building permit, and the village is the delegated permitting and inspection authority.1 Private septic work falls to Juneau County where the county wastewater ordinance applies, while local zoning details should be confirmed with the Village Clerk before buying or designing.23
At a glance
- Building permit
- Required for new one- and two-family dwellings1
- Building inspections
- Required; Union Center has delegated local inspection authority4
- Zoning
- Confirm parcel rules and allowed uses with the Village Clerk3
- Private septic
- County sanitary permit required where the county ordinance applies and public sewer does not serve the property5
- Owner-builder
- Available to a qualifying owner-occupant, but required permits still apply6
- Private well
- Advance DNR notification is generally required before construction7
- RV or tiny-home living
- Not confirmed; ask the Village Clerk before relying on the use3
Who to call
Building permits
Local contact for Union Center UDC building permits and inspections
Septic permits
Juneau County Sanitation & Zoning Department
Sanitary permits and plan review, private sewage information, shoreland building permits, floodplain zoning and land-use permits
650 Prairie Street Mauston, WI 53948
Contact details are copied from each office’s official page and were checked against it on October 9, 2026.
Off-grid gear
Going off-grid in Village of Union Center means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Union Center, Wisconsin?
Yes. A UDC building permit is required for a new one- or two-family dwelling in the Village of Union Center, including a stick-built, modular or manufactured-home installation.1 Wisconsin's Uniform Dwelling Code governs these homes, and Union Center is listed as a delegated municipality for UDC permitting and inspection.8
Required inspections cover the footings, foundation and reinforcement, rough work, insulation and final stage; the applicant contacts the inspector identified on the UDC permit when each stage is ready.9 Commercial work follows a separate delegation: Union Center has authority over qualifying small-project plan review and primary inspection responsibility for buildings, subject to the limits and retained state jurisdiction in the delegation.1011
An owner who lives or will live in the dwelling can apply for the building permit without a Dwelling Contractor Certification, but the same UDC permit and inspections still apply.6
Who issues building permits in Union Center?
The Village of Union Center is the local starting point for a UDC building permit because Wisconsin DSPS lists the village as delegated.1 The DSPS directory gives the Village Clerk contact as 608-462-8810 and [email protected].3 Ask the clerk who will review the current application and perform inspections for the specific project.3
A new-home application package includes the building-permit application, contractor license numbers and expiration dates, legible plans, a site and erosion-control plan, floor plan, elevations, energy documentation, truss plans, water calculations, wall-bracing information and the building-permit fee.12 Union Center's official site also posts building-permit information and an application, but the current fee amount could not be confirmed; request the current schedule from the Village Clerk.3
Does Union Center have zoning for RVs, tiny homes and setbacks?
Union Center's zoning rules for ordinary parcels, including allowed RV living, tiny-home occupancy, minimum dwelling size, lot size and setbacks, could not be confirmed from a readable village code. Before buying, give the Village Clerk the parcel address and proposed use and ask for the controlling zoning district, map, dimensional table and any zoning approval required.3
A tiny home used as a new one- or two-family dwelling does not escape the building-code layer: the UDC permit rule covers new stick-built, modular and manufactured-home installations.13 A mapped floodplain adds another layer because floodplain ordinances regulate development, including building, filling, grading, paving, excavation and storage.14 Juneau County Sanitation & Zoning lists floodplain zoning and land-use permits among its services, so ask that office to screen the parcel as well.15 In Juneau County floodplain-zoning areas, a land use permit is required before any development, repair, modification or addition, or change in use of a building, including sewer and water facilities.16
How do septic permits work inside Union Center?
Where a Union Center property is not served by public sewer and the Juneau County wastewater ordinance applies, every private sewage system needs a separate complete application signed by a licensed plumber and a county sanitary permit.5 A building that will use a private sewage system must have its sanitary permit before a local building permit is issued.17
Juneau County Sanitation & Zoning handles sanitary permits and plan review and can be reached at 608-847-9391.15 County inspection is required for a private onsite wastewater treatment system installed, modified or reconnected under the ordinance, and the system must remain open for inspection under the stated procedure.18 Union Center also has village water and sewer service, but a mandatory connection rule could not be confirmed; ask the Village Clerk whether the parcel must connect before planning a private system.3
Juneau County's delegated plan-review authority covers at-grade and mound systems with design wastewater flows up to 1,000 gallons per day that use approved treatment and dispersal methods.19 Individual site designs and other systems outside those categories go to the state Department of Safety and Professional Services for plan review, and the state's delegation list says plans may be submitted to either the county or the state.20 After installation, Wisconsin requires every private septic system to be visually inspected at least once every 3 years.21
Can you live in an RV or tiny home in Union Center?
Long-term RV occupancy and temporary camping on private land in the Village of Union Center could not be confirmed, so do not treat a vacant parcel or an existing driveway as approval to live in an RV. Ask the Village Clerk for a written answer tied to the parcel and proposed duration before purchase or setup.3
For a tiny home intended as a dwelling, the construction route matters. A new stick-built, modular or manufactured installation used as a one- or two-family dwelling requires a UDC building permit.13 If the building has plumbing and is not connected to public sewer, Wisconsin requires suitable wastewater treatment, recycling, dispersal or holding rather than unrestricted off-grid disposal.22 Where the county wastewater ordinance applies, the county sanitary-permit requirement must also be resolved.5
Building a home in Union Center: what are the steps?
- Confirm the parcel rules. Give the Village Clerk the address, site plan and intended dwelling type; ask for the applicable zoning, setbacks, access rules and current building-permit fee.3
- Resolve sewer or septic first. If the home will use a private sewage system and the county ordinance applies, have a licensed plumber submit the sanitary-permit application before the local building permit is issued.517
- Prepare the UDC package. Submit the building-permit application, contractor credentials, legible plans and required supporting calculations to the delegated local authority.12
- Arrange inspections. Notify the inspector shown on the UDC permit as each required construction stage becomes ready.9
- Close out safely. Occupy the dwelling only after a final inspection finds no major health or safety violation.23
What should you check before buying land in Union Center?
Start with service availability: the village provides water and sewer utilities, but the exact connection obligation for a particular parcel should be confirmed with the Village Clerk.3 If a private well is proposed, Wisconsin generally requires a DNR Well Construction Notification Number before construction and a well construction report afterward.7
Ask Juneau County Sanitation & Zoning to check floodplain constraints and whether county sanitary-permit jurisdiction applies.15 Countywide soil data show only about 0.5% of Juneau County soils avoid a “very limited” rating for a conventional septic drain field, so a soil and site evaluation deserves an early place in due diligence.24 If access will connect to a state highway, WisDOT requires a connection permit.25 Finally, confirm the village's zoning district, setbacks, RV or tiny-home use, and any land-division approval in writing before closing.3
Watch-outs
- Union Center's ordinary zoning districts, dimensional standards and zoning map could not be confirmed online; ask the Village Clerk for the rules tied to the parcel.3
- A sanitary permit must come before a local building permit when the building will use a private sewage system.17
- Floodplain development can require a separate land-use review even when a UDC building permit is required.14
- Juneau County soils overwhelmingly rate very limited for conventional septic drain fields, so investigate wastewater feasibility before fixing the house location.24
Sources
- UDC (Uniform Dwelling Code / One- and Two-Family Dwellings) (Village of Union Center), quoted and re-checked
- Chapter 15 Private Sewage System Ordinance (Village of Union Center), quoted and re-checked
- Village of Union Center Clerk (dsps.wi.gov)
- UDC (Uniform Dwelling Code / One- and Two-Family Dwellings) (Village of Union Center), quoted and re-checked
- Chapter 15 Private Sewage System Ordinance (Village of Union Center), quoted and re-checked
- Instructions for Submitting a UDC Permit Application (Village of Union Center), quoted and re-checked
- Well and heat exchange notification (Wisconsin statewide rule), quoted and re-checked
- UDC (Uniform Dwelling Code / One- and Two- Family Dwellings) (Village of Union Center), quoted and re-checked
- UDC (Uniform Dwelling Code / One- and Two- Family Dwellings) (Village of Union Center), quoted and re-checked
- Village of Union Center Jurisdiction Request for Plan Review of Small Commercial Buildings and Inspections of All Size Buildings (Village of Union Center), quoted and re-checked
- Village of Union Center Jurisdiction Request for Plan Review of Small Commercial Buildings and Inspections of All Size Buildings (Village of Union Center), quoted and re-checked
- UDC (Uniform Dwelling Code / One- and Two-Family Dwellings) (Village of Union Center), quoted and re-checked
- UDC (Uniform Dwelling Code / One- and Two- Family Dwellings) (Village of Union Center), quoted and re-checked
- Regulations and ordinances (Village of Union Center), quoted and re-checked
- Juneau County Sanitation & Zoning Department (co.juneau.wi.gov)
- Juneau County Floodplain Zoning Ordinance, quoted and re-checked
- Requirement for Plan Review Prior to Issuing Local Permits (Village of Union Center), quoted and re-checked
- Chapter 15 Private Sewage System Ordinance (Village of Union Center), quoted and re-checked
- Delegated Agents for Private On-Site Wastewater Treatment System (POWTS) Plan Review, quoted and re-checked
- Juneau County POWTS Plan Review Delegation Letter, quoted and re-checked
- Wisconsin Maintenance Program (Wisconsin statewide rule), quoted and re-checked
- Wisconsin Administrative Code, SPS 382 (Wisconsin statewide rule), quoted and re-checked
- Wisconsin’s Uniform Dwelling Code (Wisconsin statewide rule), quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- State highway connection permits (driveways & more) (Wisconsin statewide rule), quoted and re-checked
Written October 9, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.