Rhome, Texas, in Wise County, requires city building permits for building or remodeling and administers its own zoning.12 The city issues the building permits and uses a third-party inspector.3 The authority for septic permits inside Rhome city limits could not be confirmed, so ask Rhome Permitting and Wise County Environmental Services before planning an onsite system.45
At a glance
- Building permit
- Required for building or remodeling inside Rhome1
- Zoning
- Rhome zoning controls land and building uses inside city limits2
- Septic
- Authority inside city limits is unconfirmed; ask the city and Wise County Environmental Services45
- RV living
- No city occupancy rule confirmed; ask Rhome Permitting about the parcel and proposed use24
- Tiny home
- No separate city rule confirmed; zoning and building review still apply21
- Owner-builder
- License and bond exemption available for personal work, but the customary job permit remains required6
Who to call
Building permits
City of Rhome Building Inspections & Permitting
Rhome building permits and coordination of third-party building, electrical and plumbing inspections
261 School Road, Rhome, TX 76078
Septic permits
Wise County Environmental Services
Wise County contact for septic inspection information; confirm whether the office has jurisdiction at the Rhome address
2901 S FM 51 Building 100 Decatur, TX 76234
Contact details are copied from each office’s official page and were checked against it on October 9, 2026.
Off-grid gear
Going off-grid in Rhome means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Rhome, Texas?
Yes. Rhome directs anyone building or remodeling inside city limits to begin with its Permitting Department, and the city issues the building permit.1 Rhome also lists adopted building, energy, fire, mechanical, plumbing and residential codes from 2021, along with the 2020 electrical code.7
Accessory buildings have a more specific published rule: every residential accessory building requires a permit and plan review, with the permit fee due when the application is submitted.8 The city uses a third-party inspector for building, electrical and plumbing inspection services, but permit authority remains with Rhome.3 Ask Permitting to classify the exact project before starting work, particularly if the project is not ordinary new construction or remodeling.4
Who issues building permits in Rhome, and how do you reach the office?
City of Rhome Building Inspections & Permitting issues building permits and coordinates the city's third-party inspections.4 Call 817-636-2462 or visit 261 School Road in Rhome.4 When work is ready for inspection, the city directs applicants to email [email protected] or use the Ross DFW scheduling page.4
For a building or remodeling project, the city's published process starts at Permitting.9 Development submissions follow a separate path: preliminary plats, final plats and Development Review Committee requests go to [email protected], and a plat application is not complete until the corresponding fee is paid.10 Rhome says its development and building-related fee schedule is in Chapter 15 of the city code, so confirm the current amount with the city before filing.11
Does Rhome have zoning, and what does it mean for RVs and tiny homes?
Rhome has municipal zoning inside city limits, and its Planning and Zoning work regulates land use, building use and the location of residential and commercial development.2 The city publishes a zoning code and an official zoning map, but the online code warns that the official hard copy governs if the two differ.12
We could not confirm a current city rule that specifically answers residential RV occupancy, temporary camping, tiny-home occupancy, manufactured-home occupancy or accessory dwelling units. Ask Rhome Permitting to identify the parcel's zoning district and classify the proposed structure and use before buying or placing a unit.4 We also could not confirm citywide minimum dwelling size, primary-house setbacks, lot coverage or building height; those questions require the applicable district text rather than a general rule. Rhome zoning and building-permit review still apply to a proposed tiny home used as a residence.21
How do septic permits work inside Rhome?
The responsible authority for an onsite sewage facility inside incorporated Rhome could not be confirmed from the available official material. Wise County says septic permits are required and directs applicants to Public Works, but the city-limit applicability of that statement is not explicit.13 Contact Rhome Permitting and Wise County Environmental Services before ordering a septic design or relying on an existing system.45
Texas generally requires a permit and approved plan to construct, alter, repair, extend or operate an onsite sewage facility, subject to stated exemptions and any stricter local program.14 Do not assume the state 10-acre exemption settles a Rhome project: it applies only when every state condition is satisfied, including a qualifying single-family tract, site evaluation and a 100-foot property-line setback for every part of the system.14 Wise County soil data indicate that 24% of mapped soils avoid a severe limitation rating for a conventional drain field, so parcel-level evaluation belongs early in due diligence.15
Can an owner-builder construct a home in Rhome?
Rhome provides a limited owner-builder exemption for a person who personally erects, constructs or repairs a structure that person owns. The exemption removes the contractor license and bond requirement, but the owner must still obtain the customary permit for the particular job.6 It is not a blanket waiver of the city's building, zoning or inspection process.13
Texas also provides conditional state licensing exemptions for an owner doing electrical, plumbing or air-conditioning work on the owner's own qualifying residence or homestead, but those exemptions do not cover every trade and do not erase local permits or inspections.16 Before choosing subcontractors or self-performing work, describe the scope to Rhome Permitting and ask which contractor registrations, trade permits, plan documents and inspections apply.4
Building a home in Rhome: what are the steps?
- Ask Rhome Permitting to confirm that the parcel is inside city limits, identify its zoning district and verify the proposed residential use and site dimensions.24
- Confirm water and sewer availability with the city; new connections incur both tap and impact fees, and the utility rules distinguish ordinary taps from extension projects.17
- If an onsite sewage facility is proposed, confirm jurisdiction and the required design, permit and inspection sequence with Rhome and Wise County Environmental Services.45
- Submit the building-permit application and required plans through the city's Permitting Department.9
- Pay the applicable city fee and do not treat an owner-builder exemption as a permit exemption.116
- Schedule building, electrical and plumbing inspections through the city's third-party inspection service.34
What should you check before buying land in Rhome?
Start with the official zoning map and have Rhome identify the district, allowed use and dimensional standards for the exact parcel.12 If land will be divided, involve Community Development early because Rhome regulates preliminary plats, final plats and site-plan review, and applications are not complete until the corresponding fee is paid.1810
Confirm water and sewer service before assuming an off-grid plan will work. Rhome's published utility rules say new connections carry tap and impact fees, while longer connections may become private extension projects.17 For a driveway connecting to a Texas state highway, TxDOT requires its access-driveway application and a fully executed permit before right-of-way construction begins.19 Finally, investigate drainage, flood hazards and septic feasibility for the parcel; the city-specific floodplain process and the septic authority inside Rhome could not be confirmed, so ask Rhome Permitting and Wise County Environmental Services before fixing the building site.45
Watch-outs
- Do not apply Wise County's no-general-building-permit rule to a parcel inside Rhome; the city issues building permits and directs building or remodeling applicants to Permitting.1
- An owner-builder in Rhome may be exempt from the contractor license and bond, but not from the customary permit for the job.6
- Residential RV use, tiny-home occupancy, primary-house dimensions, private-well rules and the city-specific floodplain process could not be confirmed; ask Rhome Permitting before committing to a site plan.4
- The septic authority inside incorporated Rhome could not be confirmed; contact Rhome Permitting and Wise County Environmental Services before relying on county or state procedures.45
Sources
- Building Requirements (Rhome), quoted and re-checked
- Community Development (Rhome), quoted and re-checked
- Building Requirements (Rhome), quoted and re-checked
- City of Rhome Building Inspections & Permitting (cityofrhome.com)
- Wise County Environmental Services (co.wise.tx.us)
- Registration | City of Rhome, TX (Rhome), quoted and re-checked
- Building Requirements | City of Rhome (Rhome), quoted and re-checked
- Residential Accessory Building | City of Rhome (Rhome), quoted and re-checked
- Building Requirements (Rhome), quoted and re-checked
- Building Requirements (Rhome), quoted and re-checked
- Community Development (Rhome), quoted and re-checked
- City of Rhome Municipal Code (Rhome), quoted and re-checked
- Frequently Asked Questions - Who issues Building Permits in Wise County?, quoted and re-checked
- Getting a Permit for an OSSF - Such as a Septic System (Texas statewide rule), quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Exemptions to Electrician Licensing (Texas statewide rule), quoted and re-checked
- Utility Billing (Rhome), quoted and re-checked
- Community Development (Rhome), quoted and re-checked
- Section 4: Driveway Permits, Design, and Materials (Texas statewide rule), quoted and re-checked
Written October 9, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.