Upper Makefield Township in Bucks County, Pennsylvania requires a township building permit and a zoning use and occupancy permit for construction1. Zoning comes from the regional Newtown Area Joint Municipal Zoning Ordinance (JMZO)2. Septic permits and well approvals involve the Bucks County Department of Health, not the township alone34.
At a glance
- Building permit
- Required; applied for through the township, with a zoning use and occupancy permit1
- Zoning
- Regional Newtown Area Joint Municipal Zoning Ordinance (JMZO)2
- Building code
- 2018 International Building Code and 2018 International Plumbing Code; 2017 NEC5
- Septic
- Bucks County Department of Health36
- Wells
- Permits from both the township and the Bucks County health department4
- Owner-builder
- Notarized homeowner exemption on the zoning application7
Who to call
Building permits
Upper Makefield Township offices (building, planning and zoning)
Building permit and zoning applications for land inside Upper Makefield Township
1076 Eagle Road, Newtown, PA 18940
Septic permits
Bucks County Department of Health
On-lot sewage (septic) permits and well permits for Bucks County
1282 Almshouse Road, Doylestown, PA 18901
Contact details are copied from each office’s official page and were checked against it on October 14, 2026.
Off-grid gear
Going off-grid in Upper Makefield Township means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Upper Makefield Township, PA?
Yes. Upper Makefield Township requires a building permit application together with a zoning use and occupancy permit application (with impervious calculations) for accessory buildings and similar construction1. The township's instructions say their permit list is not inclusive, so ask before assuming a small project is exempt1.
Permit applications are reviewed against the 2018 International Building Code, the 2018 International Plumbing Code and the 2017 National Electrical Code58. Pennsylvania's statewide Uniform Construction Code is the backbone of these rules9. Disturbing more than 1,000 sq ft of ground also brings a grading permit1.
Who issues building permits in Upper Makefield Township, and how do you reach them?
The township itself handles building permit and zoning applications; Bucks County does not run a building department for township land10. Contact the Upper Makefield Township offices at 1076 Eagle Road, Newtown, PA 18940, phone 215-968-3340, email [email protected]8.
The township's own instructions put about 3 weeks of processing time on a complete application11. Electrical work needs plan review and inspections by a third-party electrical agency12. A building-code certificate of occupancy was not separately confirmed; the township's application is a zoning use and occupancy permit13.
Does Upper Makefield Township have zoning?
Yes. Upper Makefield Township applies zoning through the Newtown Area Joint Municipal Zoning Ordinance (JMZO), a regional ordinance shared with other townships rather than a township-only document28. Bucks County itself does not run zoning for the township; each municipality sets its own14.
We could not confirm the JMZO's district rules for minimum lot size, setbacks, RVs, tiny homes, accessory dwellings or manufactured homes. Pennsylvania's rules about state park campgrounds do not answer whether you can live in an RV on your own lot. Ask Upper Makefield Township planning and zoning, and read the JMZO district for your parcel before you buy8.
How do septic permits work in Upper Makefield Township?
Septic systems inside Upper Makefield Township go through the Bucks County Department of Health; the township sends applicants to the county's requirements3. The county requires a permit before installing, altering, repairing or occupying a structure that needs an on-lot sewage system15. A site evaluation is requested in writing, and additional soil testing may be required16.
Before anyone occupies the structure, the system must receive written Approval to Cover and a final inspection by the Department's Sewage Enforcement Officer17. Adding a bedroom requires approval of the existing septic system from the health department18. On-lot systems are not allowed where an approved public sewer is accessible19. Contact:20.
What other approvals does Upper Makefield Township require?
Water well permits are required from both the township and the Bucks County health department4. Wells must sit at least 100 feet from any septic system, and township ordinance 216 governs well construction, depth and water testing4. Additions must be at least 10 feet from the well and septic system18.
Grading disturbance over 1,000 sq ft needs approval from the Bucks County Conservation District11. Subdivision and land development are regulated by the township's code, and plans also go to the Bucks County Planning Commission2122. A driveway onto a PennDOT-jurisdiction road needs a highway occupancy permit23.
Can you build your own home in Upper Makefield Township?
Homeowners doing their own work sign page three of the zoning application as a notarized homeowner exemption and supply a copy of homeowner liability insurance in place of contractor registration7. That exemption covers contractor registration; it does not skip the building permit or inspections1.
Steps, in order:
- Ask Upper Makefield Township planning and zoning which JMZO district your parcel is in8.
- Start septic and well approvals with the Bucks County Department of Health3.
- File the building permit and zoning use and occupancy applications with a plot plan1.
- Complete required inspections, including electrical12.
What stays with Bucks County, and what should you check before you buy?
Septic and well permits sit with the Bucks County Department of Health, and subdivision plans get county planning review322. For land outside the township, see the Bucks County page.
Before you buy, confirm the JMZO district and any floodplain limits with the township, and have the health department evaluate the site. Bucks County's typical home value is $533,660 and the median property tax bill is $5,833 a year2425.
Watch-outs
- We could not confirm Upper Makefield Township's rules for RVs, tiny homes, minimum lot size or setbacks; ask the township planning and zoning office, which administers the JMZO2.
- The township's published permit instructions are dated May 2019 and list older code editions than its code page, so confirm current code editions and fees with the township before budgeting5.
- Septic and well approvals come from the Bucks County Department of Health, not the township, so start there early3.
Sources
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township: Township Code (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township: Township Code (Upper Makefield Township), quoted and re-checked
- Bucks County Department of Health On-Lot Sewage Rules and Regulations, quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township offices (building, planning and zoning) (uppermakefield.org)
- Uniform Construction Code (UCC) (Pennsylvania statewide rule), quoted and re-checked
- PA Department of Labor & Industry - Uniform Construction Code (2026 county census)
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Overview | Bucks County Planning Commission, quoted and re-checked
- Bucks County Department of Health On-Lot Sewage Rules and Regulations, quoted and re-checked
- Bucks County Department of Health On-Lot Sewage Rules and Regulations, quoted and re-checked
- Rules and Regulations Governing Individual and Community On-Lot Sewage Disposal Systems, quoted and re-checked
- Upper Makefield Township General Instructions for Permit Applications (rev. May 2019) (Upper Makefield Township), quoted and re-checked
- Bucks County Department of Health Rules and Regulations Governing Individual and Community On-Lot Sewage Disposal Systems, quoted and re-checked
- Bucks County Department of Health (buckscounty.gov)
- Township of Upper Makefield, PA code of ordinances (eCode360) table of contents (Upper Makefield Township), quoted and re-checked
- Bucks County Planning Commission Overview, quoted and re-checked
- Pennsylvania Construction Code Act, quoted and re-checked
- Typical home value (Zillow): Bolthole Index county data
- Median property tax bill: Bolthole Index county data
Written October 14, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.