Zoning, building permits and septic rules in New Carlisle, Ohio

New Carlisle, Ohio, in Clark County, requires an approved city zoning permit before any structure is built, moved or altered1. Most new construction also needs a building permit from the Clark County Building Department2. Septic permits come from the Clark County Combined Health District3.

At a glance

Zoning
City zoning permit required before building, moving or altering a structure1
Building permit
Most new construction needs a Clark County building permit in addition to the city zoning permit24
Zoning permit fee
$135 for a new 1- or 2-family home5
Zoning review time
Typically 5 to 10 working days; up to 30 days6
Septic
Permit through the Clark County Combined Health District37

Who to call

Zoning

City of New Carlisle Planning Department

Zoning permits for new construction, additions and structural alterations inside New Carlisle city limits

937.845.9492

[email protected]

331 South Church Street, New Carlisle, Ohio 45344

Building permits

Clark County Building Department (Community & Economic Development)

Building permits for most new construction in New Carlisle and unincorporated Clark County

(937) 521-2160

3130 East Main Street, Springfield, OH 45503

Septic permits

Clark County Combined Health District, Environmental Health

Household sewage treatment system (septic) permits, site reviews, inspections and private-water-system isolation distances for Clark County

(937) 717-2451

[email protected]

529 East Home Road, Springfield, OH 45503

Contact details are copied from each office’s official page and were checked against it on October 14, 2026.

Off-grid gear

Going off-grid in New Carlisle means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Does New Carlisle, Ohio have zoning, and what does it mean for building?

Yes. The City of New Carlisle runs its own zoning, and no building or structure may be erected, moved, added to or structurally altered without an approved zoning permit1. The city's Planning Department issues that permit and has up to 30 days to approve or disapprove an application1.

The city's published form also asks for a site plan and tells applicants to check plat covenants and easements first6. Setbacks, minimum lot sizes and dwelling-size rules depend on the zoning district, and we could not confirm the figures for New Carlisle's districts; ask the Planning Department for the district your parcel sits in before you buy.

We also could not confirm rules for RVs, tiny homes or manufactured homes inside city limits. The Clark County zoning code's RV and tiny-home provisions cover only the county-zoned townships, not the city8.

Do you need a building permit in New Carlisle, and who issues it?

Two separate permits are involved. The city issues the zoning permit; the Clark County Building Department issues the building permit, and most new construction may require one2. The county's own guidance lists the City of New Carlisle among the places where building permits are required4.

The city's zoning permit for new 1- and 2-family residential construction costs $135, residential additions cost $50 plus $1 per 100 square feet, and multiple-family construction costs $80 per unit5. Clark County building fees are separate; its residential application fee is $429.

The county takes applications through its online permit portal, and permits are not issued until required submittals are received and fees paid10. For a new house, state rules also require plan approval from the building department having jurisdiction before construction starts11.

How do septic permits work in New Carlisle?

Septic permits in Clark County come from the Clark County Combined Health District, not from the city or the county building department3. The district requires a permit to install or alter a household sewage treatment system and a separate permit to operate one7. Ohio requires a site review, including a soil evaluation, before the board of health accepts a permit application12.

The county's residential plan checklist asks for site approval for structures not on public sewer10. Whether a given New Carlisle lot connects to city sewer or needs its own system is something we could not confirm; ask the city and the health district's Environmental Health office. Wells are permitted by the same health district13.

Countywide, the soil rating context: about 14% of Clark County soils are rated not limited for a conventional drain field, so many lots need a site evaluation14.

Building a home in New Carlisle: the steps, in order

  1. Call the City of New Carlisle Planning Department to confirm your zoning district and what it allows1.
  2. Confirm sewer or septic: ask the city about sewer, or apply for site approval through the Clark County Combined Health District7.
  3. Apply for the city zoning permit with a site plan; review typically takes 5 to 10 working days6.
  4. Apply for the Clark County building permit through the county's online permit portal10.
  5. Start work within 6 months of the city's approval, or the zoning permit expires6.
  6. Schedule inspections and bring approved plans to each one15.

What stays with Clark County, and what to check before you buy in New Carlisle?

Building permits, septic permits and well permits for New Carlisle addresses go through Clark County offices, not city hall23. For land outside city limits, the county's own answers are on the Clark County page; inside the city, only the city's zoning rules apply.

County-level figures: the effective property tax rate is 1.2% and the median property tax bill is $1,943 per year1617. The nearest city of 100,000 or more is about 24 miles from the county center18.

Ask the Planning Department about plat covenants, easements and the zoning district before you sign6.

Watch-outs

  • A city zoning permit and a county building permit are separate approvals, and the county's building fees are not part of the city's $135 zoning fee5.
  • The city's zoning permit expires if work does not begin within 6 months of approval6.
  • We could not confirm New Carlisle's setbacks, minimum lot sizes, RV or tiny-home rules, or sewer-connection requirements; the City Planning Department is the office to ask1.

Sources

  1. Application for Zoning Permit (new additions / new construction) (New Carlisle), quoted and re-checked
  2. Application for Zoning Permit (new additions / new construction) (New Carlisle), quoted and re-checked
  3. Sewage & Septic Systems – Clark County Health Department, quoted and re-checked
  4. Does My Project Require a Permit, quoted and re-checked
  5. Application for Zoning Permit (new additions / new construction) (New Carlisle), quoted and re-checked
  6. Application for Zoning Permit (new additions / new construction) (New Carlisle), quoted and re-checked
  7. Sewage & Septic Systems, quoted and re-checked
  8. Planning & Zoning, quoted and re-checked
  9. Residential Building Fee Schedule, quoted and re-checked
  10. Forms & Applications, quoted and re-checked
  11. Section 3791.04 | Submission of plan - approvals - prohibition - fine (2026 county census)
  12. Rule 3701-29-09 | Site review and permits for STS installation and operation (Ohio statewide rule), quoted and re-checked
  13. Private Water Systems: Wells, quoted and re-checked
  14. Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
  15. Forms & Applications, quoted and re-checked
  16. Effective property tax rate: Bolthole Index county data
  17. Median property tax bill: Bolthole Index county data
  18. Straight-line distance from the county center to the nearest city of 100,000+ people: Bolthole Index county data

Written October 14, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for New Carlisle

New Carlisle’s own rules

  • Local zoningPresent

    Land inside New Carlisle city limits

    • Zoning permit required before erecting, moving or altering structures
    • City has up to 30 days to approve or disapprove in conformity with the zoning code
    “no building or structure shall be erected, moved, added to or structurally altered without first obtaining an approved zoning permit.”
  • Permit feesPublished

    City of New Carlisle zoning permit fees (Clark County building permit fees are separate)

    • Form updated 11/25

    new residential construction (1 & 2 family): 135 USD · residential additions: 50 USD (plus $1 per 100 sq ft) · multiple family construction: per 80 USD per unit

    “new residential construction (1&2 family) - $135 residential additions - $50 + $1 per 100 sqft. multiple family construction - $80 per unit”
  • Permit processPublished (with conditions)

    City zoning permit process in New Carlisle city

    • Review typically 5 to 10 working days; city has up to 30 days
    • Work must begin within six months or permit expires; must be completed within 1.5 years
    • Site plan required
    • Clark County building permits may also be needed
    “all zoning permits shall be conditional upon the commencement of work within six (6) months of city approval.”

Rules another office applies inside New Carlisle

New Carlisle does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Building permitRequired

    New construction inside New Carlisle city; Clark County building department permits in addition to the city zoning permit

    • Source says most new construction 'may require' a county building permit; city zoning permit is separate

    Clark County building department phone: 937-521-2160

    “most new construction may require a building permit from clark county building department as well. 937-521-2160”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask New Carlisle or Clark County directly.

  • Owner-builder exemption — Owner-builder exemption inside New Carlisle city
  • Building code adopted — Building code adoption inside New Carlisle city
  • Inspections — Building inspection inside New Carlisle city
  • Certificate of occupancy — Certificate of occupancy inside New Carlisle city
  • Zoning districts — Zoning district list inside New Carlisle city
20 more unanswered
  • Minimum dwelling size
  • Minimum lot size
  • Setbacks
  • Lot coverage
  • Building height
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Off-grid sanitation
  • Well permit
  • Mandatory utility hookup
  • Agricultural exemption
  • Subdividing land
  • Driveway access
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that New Carlisle publishes no rule on the point, not that none exists. Clark County’s page lists the county offices to call.

← All of Clark County: county rules, score and offices