Building permits are required inside Gloversville, New York: the city adopted the state Uniform Code for building construction1. Gloversville also has its own zoning ordinance, so zoning questions go to the city, not Fulton County2. We could not confirm who permits septic systems inside city limits, so ask the city Building Inspector before you buy3.

At a glance

Building permit
Required; the city adopted the state Uniform Code1
Who issues it
City of Gloversville Building Inspector, not Fulton County3
Zoning
Yes, the city has its own zoning ordinance2
Certificate of occupancy
Required for new, altered or moved buildings4
Permit review time
Up to 60 days for a decision5
Owner-builder
Owners of one- or two-family homes may do own plumbing after 90 days of residence6
Flood zones
Development permit required in special flood hazard areas7

Who to call

Building permits

City of Gloversville Building Inspector

Building permits, plan review and code enforcement inside Gloversville city limits; permits are picked up at the Gloversville Fire Department

(518) 773-4560

Contact details are copied from each office’s official page and were checked against it on October 24, 2026.

Off-grid gear

Going off-grid in Gloversville means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Gloversville, NY?

Yes. Inside Gloversville city limits, the City of Gloversville has adopted the New York State Uniform Fire Prevention and Building Code, including its future amendments, for the regulation of building construction1. State rules back that up: a building permit must be required for any work that has to conform to the Uniform Code, though a local authority may exempt listed categories such as small detached sheds8.

Gloversville also requires a certificate of occupancy before a new, altered, moved or repurposed building is used, except for farm-type land use such as tilling the soil4. The city's published building-permit fee starts at $15 for work costing $1,000 or less, adds $5 per additional $1,000 up to $15,000, and then $2 per additional $1,0009. Confirm the current schedule with the Building Inspector before you budget.

Who issues building permits in Gloversville, and how do you reach them?

The City of Gloversville Building Inspector handles building permits inside the city; Fulton County has no building department for city addresses3. The city's guide tells applicants to meet with the Building Inspector first, then submit plans and specifications3. The city code allows up to 60 days for review before a decision is required5, and a site plan review may also be needed depending on the location3.

Permit paperwork is picked up at the Gloversville Fire Department, which the city lists as open every day3. The application must be on the code enforcement official's form and include the site, occupancy, cost, owner and work description, with plans that can be waived for minor alterations5. Call the Building Inspector at the number listed above for forms and appointments.

Does Gloversville have zoning, and what does it mean for lot size and setbacks?

Yes. Gloversville has its own zoning ordinance, which the city amended in its entirety in 20232. It sets residence, commercial, manufacturing, cemetery and public districts: R-1 Residence, R-1A Residence, R-C Residence-Commercial, C Commercial, M Manufacturing, CEM Cemetery and PCR Public, Cultural, and Recreational10. A Downtown Urban Core Form-Based Overlay District also exists, and lot and area requirements within it are decided by the Planning Board10.

Lot size, setbacks and minimum dwelling size depend on the district, and we could not confirm a minimum floor area for single-family homes in the residence districts. Read the zoning chapter and map for your parcel's district, or ask the Building Inspector, before you buy. Fulton County does not administer Gloversville's zoning11.

How do septic permits work inside Gloversville?

We could not confirm who issues septic permits for land inside Gloversville city limits. The city's sewer and plumbing chapter regulates city sewers and plumbing, but it did not show who approves an on-site septic system, and we found no official city septic permit or inspection rule. We also found no rule requiring a new home to connect to public water or sewer, so ask the Building Inspector whether your parcel is on city sewer.

Statewide, a septic system that discharges to groundwater under 1,000 gallons per day needs no state SPDES permit, but approval may still be required from the city or county health department or the district office of the New York State Department of Health before construction12. For an alternative system, plans must be reviewed and approved by the State or county health department official having jurisdiction before construction13.

Can you live in an RV or tiny home in Gloversville?

We could not confirm a rule for long-term RV living, temporary camping, tiny homes, manufactured homes or accessory dwellings inside Gloversville. Zoning decides these questions district by district, so do not assume any of them is allowed or banned. Ask the Building Inspector in writing, with your parcel's address and district, before you buy or park anything.

New York's statewide camping rules cover state campgrounds, not private lots in a city, so they do not answer the question. Any dwelling you build or place still needs a building permit and a certificate of occupancy under the city's adopted code14.

Building a home in Gloversville: the steps, in order

  1. Find your parcel's zoning district on the city zoning map and confirm the use is allowed10.
  2. Meet with the City of Gloversville Building Inspector to discuss the project in general terms3.
  3. Have plans and specifications drawn up; the city may also require site plan review3.
  4. Ask the Building Inspector who approves septic or confirms sewer connection for your lot, since we could not confirm this.
  5. Apply for the building permit on the code enforcement official's form and allow up to 60 days for a decision5.
  6. If any part of the lot lies in a special flood hazard area, obtain a floodplain development permit before starting work7.
  7. Pass the required inspections, then obtain the certificate of occupancy before moving in14.

Owners of one- or two-family dwellings who have lived there at least 90 days may qualify to do their own plumbing work, subject to approval and inspection6.

What stays with Fulton County, and what should you check before you buy?

Fulton County's planning department assists the county's towns and villages with zoning and subdivision programs but does not itself issue building or zoning permits15. For land outside city limits, see the Fulton County page, because town and village rules differ.

Before you buy, check four things. Flood: development in a special flood hazard area needs a permit7. Driveways: a residence on a state highway needs a New York State Department of Transportation permit to build or modify a driveway16, and we could not confirm a city driveway rule. Splitting land: the city regulates subdivisions, with a carve-out for agricultural divisions of 5 acres or more that involve no new street17. Taxes: Fulton County's effective property tax rate is 2.1%18, with a median bill of $3,325 a year19.

Watch-outs

  • We could not confirm who permits septic systems inside Gloversville; ask the Building Inspector and the New York State Department of Health before you commit to a lot3.
  • The city's zoning ordinance was amended in its entirety in 2023, so older summaries of Gloversville zoning may be out of date2.
  • The 2025 New York State Uniform Code took effect December 31, 2025, and applies to building permit applications from that date20.
  • Searches for Gloversville rules often surface Johnstown or Fulton County town pages; Gloversville is a separate city with its own building and zoning offices11.

Sources

  1. Chapter 102, Article II: Building Construction Code - City of Gloversville, NY (Gloversville), quoted and re-checked
  2. Chapter 300: Zoning - City of Gloversville, NY (Gloversville), quoted and re-checked
  3. City of Gloversville Building Inspector (cityofgloversvilleny.gov)
  4. Chapter 300, Article XII: Administration and Enforcement - City of Gloversville, NY (Gloversville), quoted and re-checked
  5. Chapter 102, Article II: Building Construction Code - City of Gloversville, NY (Gloversville), quoted and re-checked
  6. Chapter 232: Sewer and Plumbing Rules - City of Gloversville, NY (Gloversville), quoted and re-checked
  7. Chapter 150: Flood Damage Prevention - City of Gloversville, NY (Gloversville), quoted and re-checked
  8. Part 1203 Uniform Code and the Energy Code: Minimum Standards for Administration and Enforcement (New York statewide rule), quoted and re-checked
  9. Chapter A304: Fees - City of Gloversville, NY (Gloversville), quoted and re-checked
  10. Chapter 300: Zoning - City of Gloversville, NY (Gloversville), quoted and re-checked
  11. Planning Department | FULTON COUNTY, quoted and re-checked
  12. State Pollutant Discharge Elimination System (SPDES) Permit Program (New York statewide rule), quoted and re-checked
  13. NYS Register March 18, 2015 Rule Making Activities — Standards for Individual Onsite Water Supply and Individual Onsite Wastewater Treatment Systems (New York statewide rule), quoted and re-checked
  14. Chapter 300, Article XII: Administration and Enforcement - City of Gloversville, NY (Gloversville), quoted and re-checked
  15. Planning Department | Fulton County, quoted and re-checked
  16. Residential Driveway Permits (New York statewide rule), quoted and re-checked
  17. Chapter 254: Subdivision of Land - City of Gloversville, NY (Gloversville), quoted and re-checked
  18. Effective property tax rate: Bolthole Index county data
  19. Median property tax bill: Bolthole Index county data
  20. Uniform Fire Prevention and Building Code, quoted and re-checked

Written October 24, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Gloversville

Gloversville’s own rules

  • Owner-builder exemptionConditional

    Plumbing work by an owner of a one- or two-family dwelling in Gloversville city.

    • Owner must be listed by the Fulton County Clerk as owner and have lived in the dwelling at least 90 days.
    • Owner must appear satisfactorily qualified to the Plumbing Inspector.
    • Work remains subject to rules, permits, and inspections.
    • A denial may be appealed in writing to the Examining Board of Plumbers.

    owner occupancy duration: >= 90 days (Owner of a one-family or two-family dwelling)

    “having lived in the dwelling for at least 90 days may perform plumbing work therein”
  • Building code adoptedAdopted (with conditions)

    Building construction in Gloversville city.

    • The adoption includes the New York State Uniform Fire Prevention and Building Code's existing and future amendments.
    “are hereby adopted for the regulation of building construction”
  • InspectionsRequired

    Buildings or lots for which a zoning certificate of occupancy is applied for inside Gloversville city.

    • The inspection precedes issuance of the certificate of occupancy.
    • The proposed use must conform to Chapter 300.
    “The Building Inspector shall make or cause to have made an inspection”
  • Certificate of occupancyRequired

    Occupancy or use of new, altered, moved, extended, or repurposed buildings and specified land uses within Gloversville city.

    • Excludes occupancy and use of vacant land consisting primarily of tilling the soil or similar agricultural use.
    • Excludes changes in use of land consisting primarily of tilling the soil or similar agricultural use.
    • Certificate is issued only if proposed use conforms to Chapter 300.
    “A certificate of occupancy is required for any of the following:”
  • Local zoningPresent (with conditions)

    Land inside Gloversville city limits.

    • Chapter 300 was amended in its entirety on 2023-10-24 by L.L. No. 13-2023.
    “[HISTORY: Adopted by the Common Council of the City of Gloversville 7-12-2015 by L.L. No. 1-2016”
  • Zoning districtsPublished (with conditions)

    Zoning districts inside Gloversville city limits.

    • Chapter 300 includes Schedule A and a Downtown Urban Core Form-Based Overlay District.
    • Schedule A states that lot and area requirements within that overlay district are determined by the Planning Board.

    published base districts: R-1 Residence; R-1A Residence; R-C Residence-Commercial; C Commercial; M Manufacturing; CEM Cemetery; PCR Public, Cultural, and Recreational

    “§ 300-7 R-1 Residence District. § 300-8 R-1A Residence District. § 300-9 R-C Residence-Commercial District. § 300-10 C Commercial District. § 300-11 M Manufacturing District. § 300-12 CEM Cemetery District. § 300-13 PCR Public, Cultural, and Recreational District.”
  • Agricultural exemptionConditional

    Agricultural divisions of land and agricultural uses of vacant land inside Gloversville city.

    • For subdivision definition, agricultural divisions must be into lots or parcels of five acres or more and not involve a new street.
    • For zoning certificates of occupancy, the cited exemptions are uses consisting primarily of tilling the soil or similar agricultural use.

    agricultural division lot size: >= 5 acres (No new street involved)

    “five (5) acres or more and not involving a new street shall not be deemed a "subdivision."”
  • Subdividing landRegulated (with conditions)

    Subdivisions within Gloversville city.

    • A division for agricultural purposes into lots or parcels of five acres or more that does not involve a new street is excluded from the code definition of subdivision.

    agricultural division exclusion lot size: >= 5 acres (No new street involved)

    “approve plats for subdivisions within the City of Gloversville”
  • Building in a floodplainRequired

    Development in areas of special flood hazard within Gloversville city jurisdiction.

    • Applies only to areas of special flood hazard.
    • When development adversely affects the special-flood-hazard area, flood-damage-mitigation measures are a condition of the permit.
    • Floodplain development without an approved permit is subject to a stop-work order.
    “A development permit shall be obtained before the start of construction or any other development within the area of special flood hazard”
  • Permit feesPublished (with conditions)

    City permit applications and permits, including building permits, inside Gloversville city.

    • Fee code directs readers to applicable Code sections for more detailed provisions.
    • Building-permit fee tiers use construction cost.

    construction cost, first tier: 15 USD (Cost of construction $1,000 or less) · additional construction cost, tier two: per 5 USD per $1,000 or fraction (Up to and including $15,000) · additional construction cost, tier three: per 2 USD per $1,000 or fraction (Exceeding $15,000)

    “$1,000 or less | $15.00 [...] Each additional $1,000 or fraction thereof, up to and including $15,000 | $5.00”
  • Permit processPublished (with conditions)

    Building-permit applications inside Gloversville city.

    • Application must be on the code enforcement official's form.
    • Application must contain the enumerated site, occupancy, cost, owner/applicant, work-description, signature, entry-consent, and plan information.
    • Plans may be waived for minor alterations or when otherwise unnecessary.
    • Permit is issued following official approval and receipt of legal fees.

    application decision deadline: <= 60 days (From submission date)

    “He shall approve or disapprove the application within 60 days”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Gloversville or Fulton County directly.

  • Minimum dwelling size — Single-family detached dwellings in the R-1 Residence District inside Gloversville city.
  • Living in an RV — Long-term RV occupancy on private land inside Gloversville city limits.
  • Camping on your land — Temporary camping on private land inside Gloversville city limits.
  • Tiny homes — Tiny-home occupancy inside Gloversville city limits.
  • Manufactured homes — Manufactured-home occupancy inside Gloversville city limits.
9 more unanswered
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Off-grid sanitation
  • Well permit
  • Mandatory utility hookup
  • Driveway access
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Gloversville publishes no rule on the point, not that none exists. Fulton County’s page lists the county offices to call.

← All of Fulton County: county rules, score and offices