The Town of Bar Harbor, Maine requires building permits for new buildings and structures through town Code Enforcement.1 Bar Harbor applies the Maine Uniform Building and Energy Code and town land-use requirements.23 For septic, submit a site evaluator’s design to Code Enforcement for approval; Maine’s Local Plumbing Inspector issues the disposal-system permit under statewide rules.45
At a glance
- Building permits
- Required for new buildings and structures; town Code Enforcement issues them13
- Zoning
- Town land-use requirements; lot standards depend on district and sewer service36
- Septic
- Submit site evaluator’s HHE-200 to Code Enforcement; local plumbing inspection required4
- Tiny homes
- State law allows qualifying tiny-home placement subject to applicable land-use requirements7
- Manufactured homes
- State law allows qualifying homes where single-family dwellings are allowed, with applicable requirements8
- Floodplain
- Town written approval required for construction, earthmoving and improvements in mapped flood hazard areas9
Who to call
Building permits
Town of Bar Harbor Code Enforcement
Building, land-use, shoreland zoning, plumbing and subsurface wastewater questions; ask here about floodplain review.
93 Cottage Street
Building permits
Town of Bar Harbor Building Permit Guidance
Identifies work requiring building permits and listed exceptions.
Building permits
Town of Bar Harbor Building Permit Administration
Building permit issuance conditions and fee-schedule link.
Septic permits
Town of Bar Harbor Code Enforcement — Septic Applications
Receives septic designs for approval and explains local plumbing inspection requirements.
Septic permits
Maine CDC Subsurface Wastewater Program
State wastewater rules, permit forms and guidance; the Local Plumbing Inspector issues the disposal-system permit.
Contact details are copied from each office’s official page and were checked against it on October 12, 2026.
Off-grid gear
Going off-grid in Town of Bar Harbor means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in the Town of Bar Harbor, ME?
Bar Harbor requires a building permit for new buildings and structures, and the town’s guidance also lists moving or demolishing structures and changes of use as permit-triggering activities.1 Bar Harbor’s Code Enforcement Officer issues building permits, and applications must be submitted in writing.3 The town enforces the Maine Uniform Building and Energy Code and inspects permitted construction for compliance.210 Do not start an activity requiring town approval until the property owner has received the required building or land-use permit.11
Who is the Town of Bar Harbor building department?
Town of Bar Harbor Code Enforcement is the starting office for residential construction, land-use, shoreland zoning, plumbing and subsurface wastewater questions.12 Call 207-288-3329 or visit the office at 93 Cottage Street to discuss the parcel and proposed work.12 Bar Harbor issues a building permit only to the owner of record or an authorized agent, and written authorization may be required.11 Existing violations of the land-use chapter or a previously approved subdivision or site plan can prevent building-permit approval for the property.11
Does the Town of Bar Harbor have zoning and minimum lot sizes?
Bar Harbor regulates land use through its town ordinance, with additional site-plan, subdivision, Design Review Board or conditional-use review possible depending on the activity and district.3 In Bar Harbor’s Village Residential District, minimum lot size is 10,000 square feet with sewers and 40,000 square feet without sewers.6 Maximum lot coverage in that district is 50% with sewers and 25% without sewers.13 Sewer service therefore changes both the lot-size and coverage standards in Village Residential; do not apply those district standards to another Bar Harbor district.613 Ask Code Enforcement to identify the parcel’s district and applicable setbacks before choosing a house layout.12
How do septic permits work inside the Town of Bar Harbor?
Bar Harbor requires an approved and inspected septic system for buildings when public sewer is unavailable, and a registered site evaluator must submit an HHE-200 form to Code Enforcement for approval.4 Maine requires a disposal-system permit for new, expanded or replacement systems or components, except normal maintenance and repair; the Local Plumbing Inspector examines the application and issues the permit.5 Septic work cannot begin before that permit is issued.14 Bar Harbor requires inspection before underground portions are covered.4 Hancock County’s soils data rates only 6.4% of soils not limited for conventional drain fields; that countywide screening does not establish a Bar Harbor lot’s suitability or make septic impossible, so obtain a site evaluation.155
Can you live in an RV or tiny home in the Town of Bar Harbor?
We could not confirm whether Bar Harbor allows residential RV occupancy or temporary camping on a private parcel; ask town Code Enforcement about the proposed use before buying an RV for the site.12 Maine requires municipalities to allow a qualifying tiny home on an individual house lot where single-family dwellings are allowed, or as an accessory structure, subject to applicable land-use requirements.7 That placement rule does not waive building, safety, utility, septic or shoreland requirements in Bar Harbor.7 Maine also requires qualifying manufactured housing where single-family dwellings are allowed, with applicable standards and permitted municipal design criteria.8
What are the steps to build a home in the Town of Bar Harbor?
Start with Bar Harbor Code Enforcement to discuss the parcel’s land-use requirements and the proposed project.12 Then establish sewer availability or arrange a site evaluator’s HHE-200 septic design for submission to Code Enforcement.4 Submit written building-permit applications and resolve any additional district-specific review before starting permitted work.311 For construction, earthmoving or other improvements in Bar Harbor’s mapped flood hazard areas, obtain the Code Enforcement Officer’s written floodplain approval.9 Arrange required construction inspections and obtain the required certificate of occupancy before regulated occupancy.1016 For land outside town limits, use the Hancock County guide to identify the relevant authority; Bar Harbor’s building and land-use process applies inside the town.3
Watch-outs
- We could not confirm a Bar Harbor owner-builder exemption from building permits; ask town Code Enforcement before treating self-built work as exempt.12
- We could not confirm Bar Harbor’s private-well permit requirements or minimum dwelling floor area; bring the proposed water supply and house plan to Code Enforcement.12
- Bar Harbor vacation-rental uses require registration and remain subject to district-specific land-use permissions.17
Sources
- Town of Bar Harbor Building Permit Guidance (barharbormaine.gov)
- Chapter 36 Building Construction (Town of Bar Harbor), quoted and re-checked
- Chapter 36 Building Construction (Town of Bar Harbor), quoted and re-checked
- Town of Bar Harbor Code Enforcement — Septic Applications (barharbormaine.gov)
- Subsurface Wastewater System Permitting (Maine statewide rule), quoted and re-checked
- ecode360.com (Town of Bar Harbor), quoted and re-checked
- Title 30-A, §4363: Regulation of tiny homes (Maine statewide rule), quoted and re-checked
- Title 30-A, §4358: Regulation of manufactured housing (Maine statewide rule), quoted and re-checked
- Article VII Permits (Town of Bar Harbor), quoted and re-checked
- Chapter 36 Building Construction (Town of Bar Harbor), quoted and re-checked
- Town of Bar Harbor Building Permit Administration (barharbormaine.gov)
- Town of Bar Harbor Code Enforcement (barharbormaine.gov)
- ecode360.com (Town of Bar Harbor), quoted and re-checked
- Maine CDC Subsurface Wastewater Program (maine.gov)
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Chapter 36 Building Construction (Town of Bar Harbor), quoted and re-checked
- Article III Land Use Activities and Standards (Town of Bar Harbor), quoted and re-checked
Written October 12, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.