Town of Upland, Indiana requires a building permit from the Building Official before construction begins.1 Upland adopts Grant County zoning regulations by reference.2 Upland’s sewer-connection rules can limit private septic use; septic permits inside town limits come from Grant County Health Department.345
At a glance
- Building permits
- Required before construction; apply to the Building Official1
- Zoning
- Town adopts Grant County zoning regulations and amendments2
- Septic permits
- Grant County Health Department; new-system permit fee $15056
- Town sewer
- Connection required after official notice for qualifying properties with public sewer within 300 feet of the property line3
- Inspections
- All construction is subject to periodic Building Official inspections7
- Move-in approval
- Full, partial or temporary certificate of occupancy required8
Who to call
Building permits
Town contact for routing building-permit questions to the Building Official
87 N. Main Street Upland, IN 46989
Planning & zoning
Town of Upland Plan Commission
Town planning contact; published variance and plat application resources
87 N. Main Street Upland, IN 46989
Septic permits
Grant County Health Department
Environmental Division contact for septic permits, records and inspections inside Upland
401 S Adams St. | Marion, IN 46953
Contact details are copied from each office’s official page and were checked against it on October 12, 2026.
Off-grid gear
Going off-grid in Town of Upland means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Town of Upland, IN?
Town of Upland requires a valid building permit from the Building Official before construction starts.1 The Upland application calls for scaled plans and specifications, a plot plan unless all work is inside an existing structure, any required state design release, requested supporting information and the adopted fee.9 Upland construction is subject to periodic inspections even when a building permit is not required.7 Occupancy also requires a full, partial or temporary certificate of occupancy from the Building Official.8
Who handles building-permit and zoning questions in Town of Upland?
Start Upland building-permit questions with Town Hall and request the Building Official’s application form and current fee schedule.109 Town Hall’s published phone is (765) 998-7439, with the town address at 87 N. Main Street, Upland, IN 46989.10 Upland’s municipal Plan Commission page provides development-standard variance, use-variance and plat application resources.11 Septic-system work inside Upland remains a separate matter for Grant County Health Department, rather than being covered by a town building permit.56
Does Town of Upland have zoning, and can you live in an RV or tiny home?
Town of Upland adopts Grant County zoning regulations and all amendments by reference; the town’s adoption provision does not reproduce the district standards.2 We could not confirm Upland’s applicable minimum lot size, dwelling size or setback schedule; ask the town Plan Commission to identify the parcel’s district and the standards for your proposed home.11 We also could not confirm residential RV, tiny-home or accessory-dwelling occupancy inside Upland; describe the intended use to town planning before buying.11 A building used for occupancy in Upland requires a full, partial or temporary certificate of occupancy.8
How do sewer connections and septic permits work in Town of Upland?
For Upland properties used for human occupancy or other covered purposes that abut a street, alley or right-of-way containing a town public sewer, connection is required at the owner’s expense within 60 days after official notice when the sewer is within 300 feet of the property line.3 Upland prohibits private sewage-disposal facilities except as provided in its sewer chapter, so establish sewer service and private-system eligibility before planning an off-grid home.4
Where a septic system is used in Upland, Grant County Health Department issues septic permits before construction, replacement, repair or alteration; fees are $150 for new construction, $125 for replacement and $50 for repair.6 Grant County’s septic process requires an application, soil analysis and contractor installation plans, with permit issuance after plan approval.12 Countywide, 0% of surveyed soils receive the strict USDA “not limited” rating for conventional drain fields; that does not make septic impossible, but makes a site evaluation especially important.13
What are the steps for building a home in Town of Upland?
- Ask Upland planning to identify the parcel’s zoning district and confirm the proposed use under the zoning regulations the town adopts.211
- Establish whether Upland’s sewer-connection requirement applies before designing private sewage disposal.34
- For an existing septic system, contact Grant County’s Environmental Division about records; where no record exists, obtain an inspection and submit the results for building-permit review.14
- Submit the Building Official’s application with required plans, supporting information and fee, and obtain the Upland building permit before construction.91
- Arrange Building Official inspections and obtain a full, partial or temporary certificate of occupancy before moving into the building.78
What should you check before buying land in Town of Upland?
For a proposed land division inside Upland’s applicable planning jurisdiction, a subdivision plat or replat needs Commission approval before recording; an excluded-division application also requires written county Health Department approval of sewage adequacy.15 We could not confirm a Upland-specific residential well-permit requirement; ask Grant County Health Department’s Environmental Division before arranging a well.16 Indiana requires licensed water-well drillers.17 For a driveway connecting to an Indiana state highway, permission comes through INDOT’s Electronic Permit System.18 If the parcel is outside town limits, use the Grant County guide for the county’s unincorporated-area building-permit requirements.19
Watch-outs
- We could not confirm an owner-builder exemption or Upland building-permit fee amount; ask the Building Official through Town Hall before budgeting or starting work.10
- Upland’s agricultural exemption concerns state structure classification and design release; it does not establish a blanket exemption from local zoning or inspections.20
- We could not confirm Upland’s local floodplain-development approval process; ask town planning about the parcel, and remember that most Indiana floodway development is under DNR Division of Water jurisdiction, subject to exemptions.1121
Sources
- § 150.08 Building permits; application; certificate of occupancy (Town of Upland), quoted and re-checked
- § 153.01 County regulations adopted by reference (Town of Upland), quoted and re-checked
- § 50.16 Prohibited acts; connection with public sewer required (Town of Upland), quoted and re-checked
- § 50.16 Prohibited acts; connection with public sewer required (Town of Upland), quoted and re-checked
- Grant County Environmental Division (Town of Upland), quoted and re-checked
- Grant County Health Department FAQs (Town of Upland), quoted and re-checked
- § 150.09 Investigations and inspections of construction activities (Town of Upland), quoted and re-checked
- § 150.08 Building permits; application; certificate of occupancy (Town of Upland), quoted and re-checked
- § 150.08 Building permits; application; certificate of occupancy (Town of Upland), quoted and re-checked
- Town of Upland Town Hall (uplandindiana.com)
- Town of Upland Plan Commission (uplandindiana.com)
- Grant County Health Department Environmental Division FAQs, quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Grant County Residential Onsite Septic System (Town of Upland), quoted and re-checked
- codelibrary.amlegal.com (Town of Upland), quoted and re-checked
- Grant County Health Department (in.gov)
- Recommended Standards For Private Water Wells (Indiana statewide rule), quoted and re-checked
- INDOT Driveway Permit Guide 2024 (Indiana statewide rule), quoted and re-checked
- Grant County Code of Ordinances, quoted and re-checked
- Plan Review FAQs (Indiana statewide rule), quoted and re-checked
- Water: Community Assistance & Information (Indiana statewide rule), quoted and re-checked
Written October 12, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.