Oakwood, Georgia, in Hall County, sets its own zoning under Chapter 54 of the city code1, and building permits are required for new construction inside city limits2. Septic permits for Oakwood addresses come from the county board of health, not the city3. RVs at a private residence in Oakwood are limited to 21 days4.

At a glance

Building permit
Required inside Oakwood city limits2
Zoning
City zoning (Chapter 54), districts include R-1, R-2, MHP and A-11
Septic
County board of health permit; city rules add limits on small lots56
RV living
Temporary only: 21 days, one RV, no city sewer connection4
Manufactured homes
Only in mobile home parks or A-1 lots of 3 acres7
Owner-builder
No Georgia license needed to build your own home; city codes still apply8

Who to call

Building permits

City of Oakwood Code Enforcement and Inspections (Planning and Development Department)

Building permits, plan review and inspections inside Oakwood city limits

Septic permits

Hall County Environmental Health (Georgia Department of Public Health, District 2)

Septic (on-site sewage) permits and well permits

770-531-3973

[email protected]

2875 Browns Bridge Road, Gainesville, GA 30504

Contact details are copied from each office’s official page and were checked against it on October 16, 2026.

Off-grid gear

Going off-grid in Oakwood means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Does Oakwood, GA have zoning, and what does it mean for lot size and homes?

Yes. Oakwood zones land inside city limits under Chapter 54 of its city code, with districts such as R-1, R-2, MHP and A-11. Single-family homes in the A-1 Agricultural District need a lot of at least three acres and 200 feet of width9. The R-1 district permits single-family detached dwellings but not mobile or manufactured homes7. Manufactured homes are allowed only inside mobile home parks (MHP) or on A-1 lots of three acres and 200 feet of width7. In the MHP district, each mobile home must sit 10 feet from the front line, 3 feet from the side line and 5 feet from the rear line10. Accessory apartments are limited to one per lot and need 6,000 square feet of lot for each dwelling11. We could not confirm lot sizes in the single-family district, building height, lot coverage or tiny-home rules; ask Oakwood's Planning and Development Department before you buy.

Do you need a building permit in Oakwood, and who issues it?

Yes. No building or structure may be erected, moved, enlarged or structurally altered in Oakwood until the zoning administrator issues a building permit2. A building permit becomes invalid if work does not start within 90 days of issue or stops for six months or more2. Oakwood has adopted the state minimum codes, including the building, residential, fire, plumbing, mechanical, electrical and energy codes with Georgia amendments12. The city's Code Enforcement and Inspections office processes building permits and checks plans for all construction in the city13. Georgia does not require a license to build your own home, but the city's codes still apply8. We could not confirm Oakwood's permit fees; ask the city office. Hall County's building permit process covers unincorporated land only14.

How do septic permits work inside Oakwood?

Georgia requires a construction permit from the County Board of Health before a septic system is built, and the site must be found suitable first5. In Hall County that office is Hall County Environmental Health15. Oakwood adds its own limits: the city issues no permit for a subsurface septic system on a lot with less than 75 feet of frontage and less than 12,000 square feet of area6. In the city's watershed protection district, septic tanks must be pumped every five years or at the county health frequency, whichever is less often16. When public sewer becomes available, a property on septic must connect within 90 days of notice17. Georgia law separately requires sewer connection when a public system is within 200 feet of the property line18. We could not confirm Oakwood's rules for private wells; ask Hall County Environmental Health.

Can you live in an RV or tiny home in Oakwood?

Only briefly in an RV. At a private residence in a residential district, Oakwood permits temporary use of one recreational vehicle for a maximum of 21 days, and connecting it to the city sewer is prohibited4. RVs may not be parked or stored on vacant residential lots4. Camping on city streets, sidewalks and public rights of way is unlawful, and camping in city recreation facilities is allowed only in designated camping areas19. That rules out living in an RV on a vacant Oakwood lot while you build. We could not confirm any Oakwood rule specific to tiny homes. Georgia treats a site-built or modular tiny home as a dwelling subject to the same building codes, and the local government must approve its siting20. Ask Oakwood's Planning and Development Department before buying for a tiny home.

Building a home in Oakwood: the steps, in order

  1. Confirm the lot's zoning district (R-1, R-2, MHP or A-1) with the City of Oakwood, since lot size and home type depend on it1.
  2. Find out whether public sewer serves the lot; if not, apply to Hall County Environmental Health for a septic permit, plus a well permit if no public water is available15.
  3. Apply to the city for a building permit, issued through the zoning administrator2.
  4. Build to the adopted state codes, and expect the city's inspections office to inspect new homes in all trades13.
  5. Ask the city about a certificate of occupancy; we could not confirm an Oakwood rule, and under Georgia law only the local government can issue one21.

What stays with Hall County, and what to check before you buy near Oakwood

Septic and well permits stay with Hall County Environmental Health, part of the Georgia Department of Public Health, for addresses inside Oakwood too3. Land outside city limits falls under Hall County's rules instead; see the Hall County page for unincorporated land. A driveway onto a state highway needs a permit from the Georgia Department of Transportation district office22. We could not confirm Oakwood's flood hazard permit rules or driveway rules on city streets; ask the city. For budgeting, Hall County's effective property tax rate is 0.8%23, and the median property tax bill is $2,382 a year24.

Watch-outs

  • We could not confirm Oakwood's building permit fees, flood hazard rules, single-family district lot sizes or tiny-home rules, so ask the City of Oakwood Planning and Development Department before you buy1.
  • City rules differ from county rules: outside Oakwood city limits, Hall County's own building permit and zoning rules apply14.
  • Oakwood bars RV hookups to city sewer and caps temporary RV use at 21 days4.

Sources

  1. Oakwood Code Sec. 54-308 R-1 Permitted uses (Oakwood), quoted and re-checked
  2. Oakwood Code Sec. 54-110 Building permit required (Oakwood), quoted and re-checked
  3. Onsite Sewage (Georgia statewide rule), quoted and re-checked
  4. Oakwood Code Sec. 54-83 Vehicle parking in residential zoning districts (Oakwood), quoted and re-checked
  5. Manual for On-Site Sewage Management Systems (Georgia statewide rule), quoted and re-checked
  6. Oakwood Code Sec. 52-160 Compliance with all regulations (Oakwood), quoted and re-checked
  7. Oakwood Code Sec. 54-603 A-1 Permitted uses (Oakwood), quoted and re-checked
  8. Residential and Commercial General Contractors Frequently Asked Questions (Georgia statewide rule), quoted and re-checked
  9. Oakwood Code Sec. 54-603 A-1 Permitted uses (Oakwood), quoted and re-checked
  10. Oakwood Code Sec. 54-432 Mobile home space requirements (Oakwood), quoted and re-checked
  11. Oakwood Code Sec. 54-87 Accessory apartments (Oakwood), quoted and re-checked
  12. Oakwood Code Sec. 12-19 Adopting codes (Oakwood), quoted and re-checked
  13. City of Oakwood Code Enforcement and Inspections (Planning and Development Department) (cityofoakwood.net)
  14. Building Permit Information, quoted and re-checked
  15. Hall County Environmental Health (Georgia Department of Public Health, District 2) (hallcounty.org)
  16. Oakwood Code Sec. 20-26 Septic systems (Oakwood), quoted and re-checked
  17. Oakwood Code Sec. 52-161 Connected to public sewer when available (Oakwood), quoted and re-checked
  18. GA DPH Onsite Sewage Manual (Georgia statewide rule), quoted and re-checked
  19. Oakwood Code Sec. 32-22 Park prohibited acts (Oakwood), quoted and re-checked
  20. Georgia Tiny House Fact Sheet (Georgia statewide rule), quoted and re-checked
  21. dca.georgia.gov (Georgia statewide rule), quoted and re-checked
  22. Regulations for Driveway & Encroachment Control Manual (Georgia statewide rule), quoted and re-checked
  23. Effective property tax rate: Bolthole Index county data
  24. Median property tax bill: Bolthole Index county data

Written October 16, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Oakwood

Oakwood’s own rules

  • Building permitRequired

    Erecting, moving, extending, enlarging or structurally altering buildings inside Oakwood city

    • Except as specifically exempted by the zoning regulations
    • Permit invalid if work not commenced within 90 days of issue or suspended or abandoned for six months or more
    • Development permits are not required for individual structures in approved single-family subdivisions or single-family units on individual lots (Sec. 54-109)
    “No building, structure or sign, except as specifically exempted by these regulations, shall be erected, moved, extended, enlarged or structurally altered, nor shall any excavation or filling of any lot for the construction of any building be commenced, until the zoning administrator has issued a building permit for such work in conformity with the provisions of these regulations.”
  • Building code adoptedAdopted

    Construction inside Oakwood city

    • Latest edition as adopted and amended by the state department of community affairs
    • Includes IBC, IRC, fire, plumbing, mechanical, gas, electrical and energy codes with Georgia amendments
    “The following codes, the latest edition as adopted and amended by the state department of community affairs, shall be enforced in the city”
  • Local zoningPresent

    Land inside Oakwood city limits

    • Zoning is in Chapter 54 of the city code with districts such as R-1, R-2, MHP and A-1.
    “The following uses are permitted in the R-1 Single-Family Residential District:”
  • Minimum lot sizeSpecified

    Single-family dwellings in the A-1 Agricultural District inside Oakwood city

    • Minimum lot width 200 feet
    • R-1 district minimum lot size not found in provided sections

    minimum lot size: >= 3 acres

    “Dwellings, single-family, provided each dwelling is located on a lot that is a minimum of three acres and a minimum lot width of 200 feet.”
  • SetbacksSpecified

    Mobile home spaces in the MHP Mobile Home Park District inside Oakwood city

    • R-1 and A-1 setbacks (Sec. 54-88) not in provided sections

    front setback: >= 10 ft · side setback: >= 3 ft · rear setback: >= 5 ft

    “Each mobile home shall be set back a minimum of ten feet from the front space line or street right-of-way, three feet from the side space line, and five feet from the rear space line.”
  • Living in an RVTemporary only (with conditions)

    RV use at private residences in residential zoning districts in Oakwood city

    • Limited to one recreational vehicle
    • Connection to city sewer system is prohibited
    • No parking or storage on vacant residential lots
    • Store only in side or rear yards, carports or enclosed buildings
    • In mobile home parks RV use limited to 120 days with no extensions

    maximum duration: <= 21 days

    “the temporary use of recreational vehicles such as motor homes, travel trailers and tent trailers at private residences shall be permitted but limited to a maximum duration in time of 21 days. such parking or use shall be limited to one recreational vehicle. connection to city sewer system is prohibited.”
  • Camping on your landLimited

    Camping in Oakwood city parks; private-land temporary stays are via the 21-day RV rule

    • Camping in city recreation facilities only in designated camping areas
    • Camping on streets, sidewalks and public rights of way is unlawful (Sec. 30-6)
    • Private residential temporary RV use limited to 21 days
    “It shall be unlawful for any person to camp in any recreation facility unless in a designated camping area.”
  • Manufactured homesLimited

    Mobile and manufactured homes inside Oakwood city: MHP and A-1 districts; R-1 excludes them

    • MHP district: only within mobile home parks, not on individual lots under separate ownership
    • A-1 district: lot minimum three acres and 200 feet width
    • R-1 permits single-family detached dwellings, not including mobile or manufactured homes

    A-1 minimum lot for manufactured home: >= 3 acres (lot width of at least 200 feet)

    “Mobile homes and manufactured homes within mobile home parks, but not including mobile homes on individual lots under separate ownership.”
  • Accessory dwellingsLimited

    Accessory apartments on lots inside Oakwood city

    • Lot must meet district minimum lot size and have at least 6,000 sq ft for each dwelling
    • One extra off-street parking space in side or rear yard
    • Not permitted with a home occupation
    • County health department must certify water, sewer and/or septic adequacy
    • Detached units need permanent foundation and conditional use approval conditions may apply

    accessory apartment heated floor area: >= 400 sq ft (not to exceed size of principal dwelling)

    “only one accessory apartment for a total of two dwelling units per lot shall be permitted.”
  • Septic permitLimited

    Private wastewater disposal systems inside Oakwood city

    • No subsurface absorption permit where front footage is less than 75 feet and lot area is less than 12,000 square feet
    • Septic tanks not allowed on lots under one acre in the watershed district (Sec. 20-26)
    • Must comply with state and federal agencies and the local board of health

    minimum lot area for subsurface absorption: >= 12000 sq ft (or front footage of at least 75 feet)

    “No permit shall be issued for any private wastewater disposal system employing subsurface soil absorption facilities where the front footage of the lot is less than 75 feet and the area of the lot is less than 12,000 square feet.”
  • Septic inspectionLimited

    Septic tanks in Oakwood's watershed protection district

    • Applies to homes built on or after April 1, 2000; older homes must show pumping within five years before requesting new water service
    • Pumping proof available to county health department on request

    pumping frequency: <= 5 years (or county public health table LT-1 frequency, whichever is less often)

    “septic tanks shall be properly pumped once every five years or according to the frequencies cited in the county public health regulations (table lt-1) whichever is less often.”
  • Mandatory utility hookupConditional

    Properties with private wastewater systems inside Oakwood city when public sewer becomes available

    • Connection within 90 days after notification by the city building inspector or health department that the private facility is no longer acceptable
    • Septic tanks must be cleaned and filled

    connection deadline: <= 90 days

    “a direct connection shall be made to the public sewer within 90 days after notification by the city building inspector or by the health department”
  • Permit processPartial

    Development and building permits inside Oakwood city

    • Development permits valid two years; expire if work not begun within 120 days
    • Building permits invalid if not commenced within 90 days
    • Single-family dwellings on individual lots need no development permit
    “all development permits shall be issued by the zoning administrator, who shall in no case approve a development permit for the use, construction, or alteration of any land or building if the land or building as proposed to be used, constructed or altered would be in violation of any of the provisions of these regulations or any other codes and laws. development permits shall be valid for two years from its issuance.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Oakwood or Hall County directly.

  • Owner-builder exemption — Owner-builders inside Oakwood city
  • Inspections — Inspections of construction inside Oakwood city
  • Certificate of occupancy — Occupancy of new buildings inside Oakwood city
  • Minimum dwelling size — Main dwellings in R-1 and A-1 in Oakwood city
  • Lot coverage — R-1 and A-1 in Oakwood city
9 more unanswered
  • Building height
  • Tiny homes
  • Well permit
  • Agricultural exemption
  • Subdividing land
  • Driveway access
  • Building in a floodplain
  • Short-term rentals
  • Permit fees

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Oakwood publishes no rule on the point, not that none exists. Hall County’s page lists the county offices to call.

← All of Hall County: county rules, score and offices