The Town of Center, Colorado requires a building permit, issued by the Town Administrator, for construction, moving, alteration or repair inside town limits1. Center also has its own zoning code, Chapter 44 of the town's Code of Ordinances2. Septic rules inside town limits are unconfirmed, so call the town and Saguache County Land Use before you buy3.
At a glance
- Building permit
- Required inside town limits; issued by the Town Administrator or a representative1
- Zoning
- Yes. Center has its own zoning code (Chapter 44)2
- Building code
- 2006 International Residential Code adopted4
- Septic
- Not confirmed inside town; ask the town and Saguache County Land Use3
- RV living
- Camping units limited to 5 days per year outside a campground or mobile home park5
- Tiny homes
- Allowed in the Residential (R) district on lots over 3,500 sq ft and 25 ft wide6
- Accessory dwellings
- Allowed in R and PUDR districts with administrative approval7
- Short-term rentals
- Licensed by the town; capped at 5 licenses in town8
Who to call
Planning & zoning
Town hall: building permit and zoning questions inside Center town limits, plus the town's documents and forms page
294 S. Worth Street
Building permits
Town of Center Building Department (under Public Works)
Building department inside the Public Works Department; the town's utilities, streets and code enforcement also sit under Public Works
Contact details are copied from each office’s official page and were checked against it on October 16, 2026.
Off-grid gear
Going off-grid in Town of Center means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Center, Colorado?
Yes. Inside the Town of Center, the town code makes it unlawful to begin excavation for construction, moving, alteration or repair, other than ordinary repair, until the Town Administrator or an authorized representative has issued a building permit1. Applications are made in duplicate with a plot plan and structure details, and a denial must be stated in writing9. Center has adopted the 2006 edition of the International Residential Code for one- and two-family dwellings4.
That is the town's rule. Land outside town limits falls under Saguache County, where structures also need a county building permit10. A fee schedule for permits inside Center is something we could not confirm, so ask Town Hall for it.
Who issues building permits in Center, and how do you reach them?
The Town of Center issues its own building permits through the Town Administrator or an authorized representative1. The town's website lists a Building Department inside its Public Works Department11. Town Hall is at 294 S. Worth Street and answers at (719) 754-349712.
Saguache County's Land Use Department does not issue building permits for lots inside Center; its permit authority covers unincorporated Saguache County10. Center also reaches into neighboring Rio Grande County, so confirm with Town Hall which county applies to a specific parcel.
Does Center have zoning, and what does it mean for RVs, tiny homes and lot size?
Yes. Center adopts its own zoning, Chapter 44 of the town's Code of Ordinances2. The districts are Residential Estate (RE), Residential (R), Residential Mobile Home (R-MH), Commercial Highway (C-H), Commercial Business (C-B) and Industrial (I)13. Saguache County's own lack of countywide zoning does not apply inside the town14.
In the Residential (R) district, the minimum lot is 7,000 square feet and 50 feet wide, with at least 3,500 square feet of lot per dwelling unit15. Setbacks are 20 feet in front, 5 feet on a side facing a street, 3 feet on an interior side, and 10 feet in the rear16. The maximum building height in the R district is 35 feet17.
Tiny homes are allowed in the R district on lots over 3,500 square feet with a width of at least 25 feet6.
A manufactured home must be on an engineered perimeter foundation, be inspected by a registered state inspector, and be no more than 10 years old at placement18; Chapter 26 of the town code sets separate setbacks for manufactured homes. A single-wide needs at least 980 square feet of living space19.
A detached accessory dwelling unit is limited to 750 square feet and needs administrative approval before a building permit7.
Can you live in an RV in Center, Colorado?
Not for long on an ordinary lot. Center limits camping units on lots inside town to 5 days per year, except in an authorized mobile home park or campground, and bars storing them in a required front setback or on streets and alleys5.
The 60-day construction-period RV rule and the temporary RV permit that Saguache County describes apply to unincorporated Saguache County, not to lots inside Center20. The state's camping rules cover Colorado Parks and Wildlife land, not private lots21.
How do septic permits work inside Center?
We could not confirm who issues septic permits for lots inside Center, or whether a given lot is on the town's sewer. Colorado law requires a permit from the local public health agency for an on-site wastewater system wherever a building is not served by a sewage treatment works22. Saguache County Land Use issues septic permits for unincorporated Saguache County, and the county notes that only some incorporated areas have central water and sewer323.
Where public sewer is or becomes available, the town code requires mobile home parks to connect to it; we found no matching connection rule for single-family lots24. Before you buy, ask Town Hall whether the lot has a sewer tap, and ask Saguache County Land Use if it does not. Private wells are another open question inside town; Colorado requires a state well permit for every new well that diverts groundwater25.
Building a home in Center: the steps, in order
- Call Town Hall at (719) 754-3497 to confirm the lot's zoning district and whether it is on town water and sewer12.
- Check the district's lot size, setbacks and height against your plans1516.
- If you plan an accessory dwelling, get administrative approval first7.
- Submit the building permit application in duplicate with a plot plan to the Town Administrator or representative9.
- For a lot without sewer, get the septic permit from the local public health agency before building approval26.
- Build to the adopted 2006 International Residential Code and pass the required inspections before the certificate of occupancy427.
What stays with Saguache County, and what to check before you buy in Center
Land outside town limits is governed by Saguache County, where septic permits come from the Land Use Department and building permits are required countywide in unincorporated areas310. Do not apply the county's setbacks, RV or permit-fee figures to a lot inside Center.
Before you buy, confirm the zoning district, the sewer and water connection, and any floodplain status; we could not confirm town floodplain or driveway rules. A driveway directly onto a state highway needs a state access permit28. County context: Saguache County's effective property tax rate is 0.3%29, and the county has about 2.1 people per square mile30.
Watch-outs
- Center's zoning table of allowed uses was not fully readable for every district, so confirm a lot's district and permitted uses with Town Hall before you rely on the R-district numbers6.
- Center straddles Saguache and Rio Grande counties, so ask Town Hall which county's health office handles septic and wells for a given lot3.
- Short-term rentals in Center need a council-approved license and cannot be mobile homes, RVs, tents or yurts8.
Sources
- Center Code Sec 44-211 Building permits (Town of Center), quoted and re-checked
- Center Code Sec 44-6 Interpretation and application (Town of Center), quoted and re-checked
- Land Use | Saguache County, quoted and re-checked
- Center Code Sec 10-95 IRC adopted (Town of Center), quoted and re-checked
- Center Code Sec 44-72 Storage and parking of camping units (Town of Center), quoted and re-checked
- Center Code Sec 44-32 Residential (R) (Town of Center), quoted and re-checked
- Center Code Sec 44-73 Accessory dwelling units (Town of Center), quoted and re-checked
- Center Code Sec 44-74 Short term rentals (Town of Center), quoted and re-checked
- Center Code Sec 44-211 Building permits (Town of Center), quoted and re-checked
- saguachecounty.colorado.gov, quoted and re-checked
- Town of Center Building Department (under Public Works) (centerco.gov)
- Town of Center (Town Hall) (centerco.gov)
- Center Code Sec 44-37 Table of allowed uses (Town of Center), quoted and re-checked
- Land Use, quoted and re-checked
- Center Code Sec 44-32 Residential (R) (Town of Center), quoted and re-checked
- Center Code Sec 44-32 Residential (R) (Town of Center), quoted and re-checked
- Center Code Sec 44-32 Residential (R) (Town of Center), quoted and re-checked
- Center Code Sec 26-2 Regulations (manufactured homes) (Town of Center), quoted and re-checked
- Center Code Sec 26-1 Definitions (Town of Center), quoted and re-checked
- Saguache County Land Development Code, Article XIII, quoted and re-checked
- Title 33 - Parks and Wildlife - Colorado Revised Statutes 2024 (Colorado statewide rule), quoted and re-checked
- Title 25 - Public Health and Environment - Colorado Revised Statutes 2024 (Colorado statewide rule), quoted and re-checked
- saguachecounty.colorado.gov, quoted and re-checked
- Center Code Sec 44-106 Mobile home park utilities (Town of Center), quoted and re-checked
- Water Administration (Colorado statewide rule), quoted and re-checked
- Title 25 - Public Health and Environment - Colorado Revised Statutes 2024 (Colorado statewide rule), quoted and re-checked
- Center Code Sec 44-73.1 Administrative review for ADUs (Town of Center), quoted and re-checked
- Access Permits | Frequently Asked Questions (Colorado statewide rule), quoted and re-checked
- Effective property tax rate: Bolthole Index county data
- Population density: Bolthole Index county data
Written October 16, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.