Pleasant Grove, Alabama, a city in Jefferson County, lists its own Building Department and building permit page, so building permits inside city limits come from the city1. The city's own zoning code bars manufactured homes used as single-family dwellings outside a mobile home park2. Septic permits come from the Jefferson County Department of Health, and the building permit follows only after that permit is issued3.
At a glance
- Building permits
- Issued by the City of Pleasant Grove Building Department1
- Zoning
- City zoning code with districts such as E-1, R-1, R-2 and RG456
- Septic
- Jefferson County Department of Health permit, then the building permit3
- Manufactured homes
- Not allowed as single-family dwellings outside a mobile home park2
- Minimum home size
- 1,400 sq ft in R-1; 1,200 sq ft in R-278
- Driveways
- Permit required from the city's planning, engineering and permits department9
- Floodplain
- Lowest floor at least two feet above base flood elevation where data exist10
- Tiny homes
- Not confirmed; ask the Building Department1
Who to call
Building permits
City of Pleasant Grove Building Department
Building permits and inspections inside Pleasant Grove city limits; the page also links builders license, mechanical, plumbing and electrical permits, and stormwater land disturbance
501 Park Road, Pleasant Grove, Alabama 35127
Septic permits
Jefferson County Department of Health - Community Environmental Protection Division
Onsite sewage disposal (septic) permits and site evaluations in Jefferson County, including inside city limits
Contact details are copied from each office’s official page and were checked against it on October 16, 2026.
Off-grid gear
Going off-grid in Pleasant Grove means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Pleasant Grove, AL, and who issues it?
Pleasant Grove has its own Building Department, and its city page links a building permit application, a builders license page, mechanical, plumbing and electrical permits, and stormwater land disturbance information1. Inside Pleasant Grove city limits, start there, not at Jefferson County Development Services, which serves unincorporated land.
We could not confirm which residential building code the city has adopted, whether it has an owner-builder exemption, or its fee schedule, so ask the Building Department before you budget. Alabama's Home Builders Licensure Law has a statewide exemption for an owner who acts as their own contractor on a one- or two-family home for their own use11. A driveway inside the city also needs a permit from the city's department of planning, engineering and permits before it is installed9.
Who do you call at the Pleasant Grove Building Department?
The City of Pleasant Grove Building Department is at 501 Park Road, Pleasant Grove, Alabama 351271. For immediate assistance, the city's inspector page gives (205)744-1726 and the email [email protected]1.
That page names a City Inspector and Chief Building Official, but it does not state an inspection schedule, so confirm by phone what inspections your project needs1.
Does Pleasant Grove have zoning, and what does it mean for homes, lots and setbacks?
Pleasant Grove adopts its own zoning by district, and the rules differ by district. In the R-1 single-family district, the minimum lot is 14,000 square feet with a 100-foot width4. In R-2, the minimum lot is 10,000 square feet with an 85-foot width5. In the E-1 estate district, lots need 1 acre and a 150-foot width12. Where sanitary sewers are unavailable in either single-family district, the 15,000-square-foot lot area required by the county health department must be met instead5.
Minimum livable floor area is 1,400 square feet in R-17 and 1,200 square feet in R-28. In the RG garden home district, the front setback is 20 feet (10 feet with an enclosed garage), the rear setback is 25 feet and the side setback is 0 feet6.
We could not confirm a general lot-coverage limit, so ask the Building Department.
Can you live in an RV, tiny home or manufactured home in Pleasant Grove?
Pleasant Grove's code bars a mobile or manufactured home intended as a single-family dwelling anywhere in the city except in a development classified as a mobile home park2. The code also bars using an accessory building as a separate dwelling, other than for domestic servants employed on the premises13. Overnight camping in city parks needs prior written approval from the parks and recreation department14.
We could not confirm any Pleasant Grove provision on tiny homes, and none on living in an RV on a private lot, so ask the Building Department before you rely on either. Jefferson County's one-year allowance for a camper, RV or tiny home during construction is a county zoning rule for unincorporated land, not a city rule15.
How do septic permits work inside Pleasant Grove city limits?
The Jefferson County Department of Health issues septic permits inside Pleasant Grove city limits, wherever a new onsite sewage disposal system is used. A county site evaluation comes first, and the building permit is issued after the health department issues the permit to construct3. The process begins when the homeowner hires an engineer, land surveyor or soil scientist for soil investigations and submits a permit application and plot plan16. Questions go to the Community Environmental Protection Division at (205) 930-123016.
In the RG garden home district, lots may be served by water and sewer or by septic tanks17. Jefferson County soils matter here: about 24% of county soils rate as not limited for a conventional drain field, so expect a site evaluation and possibly an engineered system18. We could not confirm any city or county rule on private wells in Pleasant Grove.
Building a home in Pleasant Grove: the steps, in order
- Confirm your lot's zoning district and its lot size, width, floor-area and setback rules with the Building Department1.
- If the lot has no public sewer, hire an engineer, land surveyor or soil scientist and apply to the Jefferson County Department of Health for a septic permit16.
- After the health department issues the septic permit, apply for the building permit3.
- Get a driveway permit from the city's department of planning, engineering and permits before installing the driveway9.
- If the lot is in a mapped flood hazard area, plan the lowest floor at least two feet above base flood elevation where that data exists10.
- Schedule inspections with the Building Department at (205)744-17261.
What stays with Jefferson County, and what to check before you buy
Septic and the health department's lot-size requirements stay with the Jefferson County Department of Health even inside city limits3. A new driveway connection to a street maintained by Jefferson County, including county-maintained roads inside municipalities, also needs an access application to the county Department of Roads and Transportation19.
If the parcel is outside city limits, the county's rules apply instead: see the Jefferson County page. Jefferson County's effective property tax rate is 0.6%20, and the median county property tax bill is $1,340 a year21.
Watch-outs
- Confirm the lot is inside Pleasant Grove city limits before using these rules; Jefferson County rules apply only to unincorporated land22.
- A manufactured home cannot be placed as a single-family dwelling in the city outside a mobile home park2.
- We could not confirm the city's adopted residential building code, fee schedule or owner-builder rules, so call the Building Department at (205)744-17261.
- A septic permit must come before the building permit, so start the Jefferson County Department of Health site evaluation early3.
Sources
- City of Pleasant Grove Building Department (cityofpg.com)
- Sec. 98-599. Mobile/manufactured home parks (Pleasant Grove), quoted and re-checked
- Onsite Sewage Disposal (Pleasant Grove), quoted and re-checked
- Sec. 98-213. Area and dimensional regulations (Pleasant Grove), quoted and re-checked
- Sec. 98-253. Area and dimensional regulations (Pleasant Grove), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- Sec. 58-45. Prohibited parking in front yard (Pleasant Grove), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- Exemptions (Alabama statewide rule), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- Sec. 98-151. Accessory buildings (Pleasant Grove), quoted and re-checked
- library.municode.com (Pleasant Grove), quoted and re-checked
- ZONING RESOLUTION, quoted and re-checked
- Jefferson County Department of Health - Community Environmental Protection Division (jcdh.org)
- library.municode.com (Pleasant Grove), quoted and re-checked
- Share of soils USDA rates "not limited" for a conventional septic drain field (SSURGO). A strict rating: the median county is about 6% and a tenth of counties are 0%, so a low figure means most lots need a site evaluation or an engineered system, not that septic is impossible. Cite it only with that caveat: Bolthole Index county data
- Jefferson County Subdivision & Construction Regulations, quoted and re-checked
- Effective property tax rate: Bolthole Index county data
- Median property tax bill: Bolthole Index county data
- Jefferson County Zoning Regulations — Adopted October 9, 2025, quoted and re-checked
Written October 16, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.