Zoning, building permits and septic rules in Town of Phil Campbell, Alabama
Town of Phil Campbell is a town in Franklin County, Alabama. Town of Phil Campbell adopts its own zoning, so inside its limits Town of Phil Campbell’s rules apply, not the county’s. 6 rules below are quoted from official sources and independently re-checked, most recently on November 7, 2026. Rules for unincorporated land are on the Franklin County page.
Answers from the rulebook for Town of Phil Campbell
Town of Phil Campbell’s own rules
Building permitRequired
Construction for which a building permit is required inside Phil Campbell town limits.
The town's published contractor notice says permits must be obtained from the Building Inspector.
conditions associated with contractor licensing are stated in the town notice: contractors must be licensed by the proper Alabama licensing board, and required licenses/certificates are verified before permit issuance.
“Building Permits must be obtained from the Building Inspector, all contractors must be licensed by the proper State of Alabama Licensing Board.”
InspectionsRequired
Commercial buildings for new businesses physically located inside Phil Campbell town limits.
Inspection by both the Building and Fire Department is required before the business opens.
The published instruction directs applicants to contact the Building and Zoning Department to schedule inspection.
“All commercial buildings must be inspected by both the Building and Fire Department prior to business opening.”
Local zoningPresent (with conditions)
Businesses physically located inside Phil Campbell town limits.
The published town application requires Building and Zoning Department approval and verification that the proposed business meets the town's zoning regulations and permitted uses before entering a lease agreement.
“All businesses, including home operated businesses, must verify that the proposed business meets the Zoning Regulations and Uses Permited BEFORE you enter into a lease agreement.”
Permit processPartial
Building permits inside Phil Campbell town limits.
The published contractor notice requires building permits to be obtained from the Building Inspector.
The notice also states that required licenses and certificates are verified before building-permit issuance.
No official building-permit application, plan-submittal list, fee schedule, or review timeline was located.
“Building Permits must be obtained from the Building Inspector [...] All required licenses/certificates will be verified prior to issuance of building permits and business licenses.”
Rules another office applies inside Town of Phil Campbell
Town of Phil Campbell does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.
Septic permitRequired
Construction of an onsite sewage disposal system inside Phil Campbell town limits when an onsite system is used.
Application must be submitted to the local county health department before construction.
A Permit to Install issues only if the application and plans are complete and meet all rule requirements.
Construction may begin only after issuance of the Permit to Install.
The system installer must be licensed by the Alabama Onsite Wastewater Board.
“No person shall begin the installation or repair of an OSS/EDS, or component thereof, until the responsible person has been issued a valid Permit to Install (Repair) an Onsite Sewage System (OSS) by the LHD.”
Off-grid sanitationLimited
Onsite sewage disposal systems used at homes inside Phil Campbell town limits.
The requirement applies before constructing an onsite sewage disposal system.
An application for a Permit to Install must be submitted to the local county health department.
Construction may begin only after a Permit to Install issues.
“Before the construction of an onsite sewage disposal system, you must submit an Application for a Permit to Install an Onsite Sewage Disposal System to your local county health department. If the application and plans are complete and meet all the requirements of the rules, a 'Permit to Install' will be issued. Then and only then can you begin the construction of your system.”
Still unanswered
We looked and could not find an official answer yet. Silence is not permission; ask Town of Phil Campbell or Franklin County directly.
Owner-builder exemption — Owner-built dwellings inside Phil Campbell town limits.
Building code adopted — Construction inside Phil Campbell town limits.
Certificate of occupancy — Buildings inside Phil Campbell town limits.
Zoning districts — Zoning districts inside Phil Campbell town limits.
Minimum dwelling size — Residential dwellings inside Phil Campbell town limits.
19 more unanswered
Minimum lot size
Setbacks
Lot coverage
Building height
Living in an RV
Camping on your land
Tiny homes
Manufactured homes
Accessory dwellings
Septic inspection
Well permit
Mandatory utility hookup
Agricultural exemption
Shed and accessory-building permit exemption
Subdividing land
Driveway access
Building in a floodplain
Short-term rentals
Permit fees
Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.
Unanswered questions are usually a sign that Town of Phil Campbell publishes no rule on the point, not that none exists. Franklin County’s page lists the county offices to call.
Off-grid gear
Going off-grid in Town of Phil Campbell means bringing your own water and power. The kit we’d start with: