Town of Gilbert is a town in Mingo County, West Virginia. Septic permits inside Town of Gilbert come from Town of Gilbert. 12 rules below are quoted from official sources and independently re-checked, most recently on October 24, 2026. Rules for unincorporated land are on the Mingo County page.

Answers from the rulebook for Town of Gilbert

Town of Gilbert’s own rules

  • Building permitRequired

    Development, new construction, substantial improvement, substantial-damage repair, and structure placement or relocation within Gilbert town

    • A completed permit application and standard site plan are required; the permit must be obtained from the Floodplain Administrator.
    “It shall be unlawful for any contractor, person, partnership, business, or corporation to undertake, or cause to be undertaken, any development or the new construction, substantial improvement, repair of substantial damage, or the placement or relocation of any structure (including manufactured homes) within the town, unless a permit application and standard site plan has been completed, and a permit has been obtained from the Floodplain Administrator.”
  • Building code adoptedAdopted (with conditions)

    Structures erected or removed throughout Gilbert town

    • Gilbert incorporates the State Building Code promulgated by the Fire Marshal under W. Va. Code § 29-3-5b.
    “There is hereby adopted and incorporated by reference as if set out at length herein for the purpose of safeguarding life and property and to ensure the quality of construction of all structures erected or removed throughout the municipality that certain code know as the State Building Code as promulgated by the Fire Marshal under W. Va. Code § 29-3-5b.”
  • InspectionsLimited

    Construction and development covered by Gilbert's floodplain chapter

    • During construction, the Floodplain Administrator or another authorized official may inspect for compliance with the permit application, laws, and ordinances.
    “During the construction period, the Floodplain Administrator or other authorized official may inspect the premises to determine that the work is progressing in compliance with the information provided on the permit application and with all applicable laws and ordinances.”
  • Subdividing landLimited

    Land inside Gilbert town that is partially or fully in a special flood hazard area

    • Before subdivision, utilization for a manufactured-home park or subdivision, or other development, a detailed site plan must be submitted to and approved by the Floodplain Administrator.
    “In addition, where land that is either partially or fully in the special flood hazard area is to be subdivided, utilized for a manufactured home park or subdivision, or otherwise developed, a detailed site plan shall be submitted to, and approved by, the Floodplain Administrator prior to any development.”
  • Building in a floodplainRequired

    Development, new construction, substantial improvement, substantial-damage repair, or structure placement or relocation within Gilbert town

    • A completed permit application and standard site plan are required, and a permit must be obtained from the Floodplain Administrator. Additional detailed-site-plan approval applies to land partially or fully in a special flood hazard area before subdivision, manufactured-home park/subdivision, or other development.
    “In addition, where land that is either partially or fully in the special flood hazard area is to be subdivided, utilized for a manufactured home park or subdivision, or otherwise developed, a detailed site plan shall be submitted to, and approved by, the Floodplain Administrator prior to any development.”
  • Permit feesVariable (with conditions)

    Floodplain determinations and development regulated by Gilbert's floodplain chapter

    • All proposed development is assessed a town-approved flat floodplain-determination fee. Development in a special flood hazard area is assessed an additional fee based on a town-approved schedule and estimated construction value; review and inspection costs may be reimbursed. Fees double for work started before a permit and triple for each subsequent occurrence by the same person.
    “A floodplain determination fee shall be assessed on all proposed development. This shall be a flat fee approved by the town.”
  • Permit processPartial

    Development and construction inside Gilbert town regulated by the floodplain chapter

    • Applicant completes a permit application and standard site plan and obtains the Floodplain Administrator's permit before covered work. For special-flood-hazard-area subdivision, manufactured-home park/subdivision, or other development, a detailed site plan must be submitted and approved first.
    “It shall be unlawful for any contractor, person, partnership, business, or corporation to undertake, or cause to be undertaken, any development or the new construction, substantial improvement, repair of substantial damage, or the placement or relocation of any structure (including manufactured homes) within the town, unless a permit application and standard site plan has been completed, and a permit has been obtained from the Floodplain Administrator.”

Rules another office applies inside Town of Gilbert

Town of Gilbert does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Who permits septicLocal (with conditions)

    Private on-site sewage systems serving land inside Gilbert town, Mingo County

    • A certified installer initiates the process and submits the on-site sewage application to the Health Department; the sanitarian evaluates the site.
    “The homeowner/property owner and/or certified installer will fill out an on-site sewage system application and submit it to the Health Department.”
  • Septic permitRequired

    New, modified, or repaired private on-site sewage systems inside Gilbert town, Mingo County

    • The sanitarian must approve the site before the Health Department issues a construction permit; construction may begin after issuance.
    “Once the Sanitarian has approved the site a Construction Permit for the new system, modification, or repair will be issued by the Health Department.”
  • Septic inspectionRequired

    New, modified, or repaired private on-site sewage systems inside Gilbert town, Mingo County

    • The certified installer must contact the Health Department before the system is covered; the sanitarian evaluates installation against the approved construction plan.
    “When construction/repair of the system is finished, but before the system is covered up, the certified installer must contact the Health Department for a final inspection.”
  • Off-grid sanitationLimited

    On-site sewage options for homes inside Gilbert town, Mingo County

    • On-site systems require Health Department site approval, construction permitting, and final inspection. Alternative systems for new construction may be considered only if the lot is two acres or larger.

    minimum lot area for consideration of alternative on-site sewage system for new construction: >= 2 acres

    “Alternative systems may be considered for new construction only if the lot is two acres or larger in size.”
  • Well permitRequired

    Water-well installation inside Gilbert town, Mingo County

    • A certified water-well driller is required; after application, the sanitarian conducts site visits, and a permit issues only if the site complies with Water Well Regulation requirements.
    “The Mingo County Health Department conducts water well permitting and sampling activities. A permit is required for the installation of a water well.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Town of Gilbert or Mingo County directly.

  • Owner-builder exemption — Owner-built homes inside Gilbert town
  • Certificate of occupancy — Residential occupancy inside Gilbert town
  • Local zoning — Land inside Gilbert town limits
  • Zoning districts — Land inside Gilbert town limits
  • Minimum dwelling size — Dwellings inside Gilbert town
12 more unanswered
  • Minimum lot size
  • Setbacks
  • Lot coverage
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Accessory dwellings
  • Mandatory utility hookup
  • Agricultural exemption
  • Driveway access
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Town of Gilbert publishes no rule on the point, not that none exists. Mingo County’s page lists the county offices to call.

Off-grid gear

Going off-grid in Town of Gilbert means bringing your own water and power. The kit we’d start with: