Town of Fairlee is a town in Orange County, Vermont. Town of Fairlee adopts its own zoning, so inside its limits Town of Fairlee’s rules apply, not the county’s. 13 rules below are quoted from official sources and independently re-checked, most recently on October 29, 2026. Rules for unincorporated land are on the Orange County page.

Answers from the rulebook for Town of Fairlee

Town of Fairlee’s own rules

  • InspectionsLimited

    Permitted residential work in Fairlee town

    • The form contains a 'date of inspection' field for office use. It does not set out a required inspection schedule, so this is a limited finding.
    “i shall allow the zoning administrator access at reasonable times to ensure compliance with this permit and its conditions.”
  • Local zoningPresent (with conditions)

    All land inside Fairlee town limits. The Town of Fairlee Unified Development Bylaw combines zoning, subdivision and flood hazard regulations and is administered by the Fairlee zoning administrator.

    • The copy read is the ACCD file titled Proposed Amendments, May 2023. Its cover says the bylaw was adopted August 14, 2018 and 'as amended by the voters july 11, 2023'. The adopted text was not independently confirmed on a town page, so confirm before relying on it.
    • Form Z-1 cites sections of the town of Fairlee zoning regulations for each permit.
    “fairlee unified development udb adopted: august 14, 2018 interim amendments september 27, 2021 interim amendment lake morey moratorium september 27, 2021 interim amendments january 24, 2022 interim amendments april 10, 2023 as amended by the voters july 11, 2023”
  • Zoning districtsPublished

    Zoning districts and overlay areas of Fairlee town

    • The table of contents lists the districts (village area, interchange area, lakeshore resort, Lake Morey area, mixed use, residential area, rural resource area) and overlay areas. The zoning map is referenced but was not opened.
    “§3.1.6 residential area a. description per the zoning map, the residential area is a broad classification of all lands lying outside of all other zoning districts.”
  • Minimum lot sizeDistrict specific (with conditions)

    Residential area (§3.1.6), the main single-family residential district of Fairlee town

    • Class A lots on village water: 20,000 sq ft per principal use.
    • Class B lots not on village water: 2 acres per principal use.
    • Subject to the 2023 amendment copy noted in local_zoning.

    lot area minimum, class A (on village water): 20000 square feet (per principal use) · lot area minimum, class B (not on village water): 2 acres (per principal use)

    “class b lots (not on village water): 1. lot area minimum: 2 acres per principal use. 2. lot frontage minimum: 200 feet.”
    One more reviewed finding on this topic
  • SetbacksDistrict specific (with conditions)

    Residential area (§3.1.6)

    • Front setback is measured from the center of the highway right-of-way.
    • Class A lots on village water: 50 ft front, 15 ft side and rear.
    • Class B lots not on village water: 60 ft front, 25 ft side and rear.

    front building setback, class A: 50 feet (from center of highway right-of-way) · side and rear setback, class A: 15 feet · front building setback, class B: 60 feet (from center of highway right-of-way) · side and rear setback, class B: 25 feet

    “building setback minimum: 60 feet from center of highway right-of-way. 4. side and rear setback minimum: 25 feet.”
    One more reviewed finding on this topic
    • District specific (with conditions) — Rural resource area (§3.1.7)
      “building setback minimum: 65 feet from center of highway right-of-way. 4. side and rear setback minimum: 40 feet.”
  • Building heightDistrict specific (with conditions)

    Residential area (§3.1.6)

    • Class A lots: measured from lowest adjacent grade.
    • Class B lots: measured from street grade.

    maximum height, all structures: <= 35 feet (class A from lowest adjacent grade; class B from street grade)

    “5. maximum height all structures: 35 feet from lowest adjacent grade.”
    One more reviewed finding on this topic
  • Subdividing landRegulated (with conditions)

    Land subdivision inside Fairlee town

    • Minor subdivisions are delegated to the zoning administrator; major subdivisions go to the DRB under §6.2.3.
    • Cluster development, density bonuses and lot-creation transfers to the receiving area are provided for.
    “article vi subdivision amendments delegate minor subdivision functions to the zoning administrator, brings plat submissions into compliance with state regulations, enables cluster development, density bonuses, and the transfer of lot creation rights to the receiving area.”
  • Building in a floodplainLimited

    Flood hazard area overlay in Fairlee town

    • Applies in the flood hazard overlay area and other listed overlay areas; the flood hazard standards (§7.1.4) were not read.
    • Consult the zoning administrator for work in these areas.
    “note: even maintenance, repair or replacement, or ground disturbance may require a permit in some areas, particularly the flood 3 hazard overlay area, lake fairlee area, lake morey area, the lake morey watershed overlay area, and lake shore resort area. for any work in these areas, consult the zoning administrator.”
  • Permit feesPublished (with conditions)

    Residential zoning/building permit (Form Z-1) for a new structure in Fairlee town

    • The form also requires a site plan (ask the zoning administrator for details) and a $15.00 recording fee.
    • Fee shown on form revision rev.1 /1/2026.

    new structure permit fee: 100 USD (plus 15 cents per square foot and a $15.00 recording fee)

    “fee: new structure $100.00 & 15¢ square foot+ $15.00 recording fee.”
  • Permit processPublished (with conditions)

    Zoning/building permits issued by the Fairlee zoning administrator

    • Some applications are referred to the Development Review Board, per the form's office-use section.
    • A permit does not take effect until the appeal period has passed.
    • Activities under the permit must be completed within two years.
    • The permit is void if information is misrepresented.

    appeal period: 15 days

    “this permit shall not take effect until time for such appeal has passed.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Town of Fairlee or Orange County directly.

  • Owner-builder exemption — Owner-builder exemption in Fairlee town
  • Building code adopted — Building code adoption in Fairlee town
  • Certificate of occupancy — Certificate of occupancy or compliance for new homes in Fairlee town
  • Minimum dwelling size — Minimum dwelling size in Fairlee town
  • Lot coverage — Lot coverage in Fairlee town
11 more unanswered
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Well permit
  • Agricultural exemption
  • Driveway access
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Town of Fairlee publishes no rule on the point, not that none exists. Orange County’s page lists the county offices to call.

Off-grid gear

Going off-grid in Town of Fairlee means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

← All of Orange County: county rules, score and offices