Val Verde County, Texas

Building permits, zoning and land rules in Del Rio, Texas

Del Rio, Texas requires a city building permit for new residential construction inside city limits, with zoning and technical-code review before issuance.1 Del Rio Development Services issues building permits; the city Planning & Zoning Department handles development and rezoning review.23 Septic applicants are directed to Val Verde County, whose Health Department administers the county OSSF program.45

At a glance

Building permits
Required for new residential construction inside city limits1
Zoning review
City review before residential building permit issuance1
Septic permits
City directs septic applicants to Val Verde County45
Residential building fee
$7 per $1,000 of value; $56 minimum, plus $15 processing per permit4
Inspections
Permitted work must remain exposed until approved; final inspection required6
Occupancy
Certificate of Occupancy required before occupying a building7

Who to call

Building permits

Del Rio Development Services

City building permits, code review, inspections and certificates of occupancy

830-774-8526

114 W. Martin St. Del Rio, TX 78840

Zoning

Del Rio Planning & Zoning

City development applications, rezoning review and zoning information

830-703-5384

114 W. Martin St. Del Rio, TX 78840

Septic permits

Val Verde County Health Department / Risk Management

County contact for OSSF applications and septic requirements

830-774-7569

207 E. Losoya Street Del Rio, Texas 78840

Contact details are copied from each office’s official page and were checked against it on October 11, 2026.

Off-grid gear

Going off-grid in Del Rio means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Del Rio, Texas?

New residential construction inside Del Rio city limits requires a city building permit, and the city reviews the application for zoning and technical codes before issuance.1 Del Rio’s residential fee schedule lists $7 per $1,000 of project value with a $56 minimum, plus a $15 processing fee per permit.4 The schedule separately lists a $45 inspection fee.4 Building permit approval does not finish the process: permitted construction must remain accessible and exposed until the chief building official approves the work, and all permits require final inspection.6

Who issues building permits in Del Rio, and how do you reach them?

Del Rio Development Services issues building, electrical, plumbing, mechanical and sign permits, reviews plans for code compliance, and issues certificates of occupancy.2 Contact Development Services at 830-774-8526 or at 114 W. Martin St. Del Rio, TX 78840 for the city building application and inspection arrangements.2 Del Rio Planning & Zoning is the separate city contact for development applications and rezoning review, at 830-703-5384.3 Septic applicants should contact Val Verde County Health Department / Risk Management at 830-774-7569; the city fee schedule directs septic tanks to the county.84

Does Del Rio have zoning, and what about RVs, tiny homes and setbacks?

Del Rio reviews residential building applications for zoning compliance before issuing a building permit.1 Del Rio Planning & Zoning publishes a Residential Use Matrix, Lot and Building Dimension Table and Planning and Zoning Map.3 Residential plot plans must show lot size, existing and proposed structures, uses, setbacks and property pins.9 Ask Planning & Zoning to identify the parcel’s district and the applicable use and dimensional standards before choosing a house plan.3 We could not confirm Del Rio’s residential RV, temporary-camping, tiny-home or accessory-dwelling rules, or district-specific minimum lot size and setback numbers; ask Planning & Zoning about the proposed use before buying.3

How do septic permits work inside Del Rio?

Del Rio’s published fee schedule directs septic-tank questions to Val Verde County, and the county administers an OSSF program subject to exceptions for areas already regulated under another order, ordinance or resolution.45 Val Verde County’s septic application requires a plot design, septic-system and potable-water locations, and a complete site evaluation and system design before a permit is issued.10 The county form lists a $250 residential septic permit fee, paid by check or money order.10 Texas generally requires an approved plan and permit to construct, alter, repair, extend or operate an OSSF.11 Ask the county Health Department which inspection steps and local requirements apply to the Del Rio address before installation.8 Texas’s septic permitting exemption for a single-family dwelling on at least 10 acres requires every stated condition, including a site evaluation, all OSSF parts at least 100 feet from property lines, on-site disposal, no nuisance or groundwater pollution, and no other dwelling on the tract.11

Building a home in Del Rio: what are the steps, in order?

  1. Ask Del Rio Planning & Zoning about the parcel’s zoning and proposed development before preparing the residential application.3
  2. Prepare the plot plan showing structures, uses, setbacks and property pins, plus floor plans with room uses, dimensions and building-system details.9
  3. Submit the complete city application, two full plan sets, PDF construction documents and plan-review fee; complete applications generally take 3–5 working days to review, depending on project size.9
  4. For a septic installation, submit the county OSSF application, site evaluation and system design before seeking septic permit approval.10
  5. Keep permitted work exposed for inspection and arrange final inspection; obtain the required Certificate of Occupancy before occupying the building.67

What should you check before buying land in Del Rio?

For land outside Del Rio city limits, use the Val Verde County guide: the county’s published building permit requirements apply to property within the Amistad Land Use and Zoning Order area.12 Inside Del Rio, ask Development Services about the proposed water source; the city lists a $75 water-well permit fee, but we could not confirm the circumstances requiring that permit.42 Ask Planning & Zoning about access, floodplain review and any proposed manufactured home before committing to a parcel.3 We could not confirm a general owner-builder or agricultural exemption from Del Rio’s city requirements; obtain a project-specific answer from Development Services before relying on either.2

Watch-outs

  • Del Rio residential building permits become invalid if work does not commence within 180 days of issuance or remains incomplete after suspension or abandonment for 180 days after work commenced.9
  • We could not confirm permission for residential RV living or tiny-home occupancy in Del Rio; ask city Planning & Zoning before using either as housing.3
  • Del Rio’s city building permit does not replace the county septic application and site evaluation for an OSSF installation.110

Sources

  1. Buildings Permit Requirements and Procedures — Residential One & Two Family Dwellings (Del Rio), quoted and re-checked
  2. Del Rio Development Services (cityofdelrio.com)
  3. Del Rio Planning & Zoning (cityofdelrio.com)
  4. City of Del Rio Consolidated Fee Schedule (Del Rio), quoted and re-checked
  5. November 14, 2016 Commissioners Court Regular Meeting, quoted and re-checked
  6. Del Rio Code of Ordinances, Chapter 8, Required Inspections (Del Rio), quoted and re-checked
  7. Development Services — City of Del Rio (Del Rio), quoted and re-checked
  8. Val Verde County Health Department / Risk Management (valverdecounty.texas.gov)
  9. Buildings Permit Requirements and Procedures — Residential One & Two Family Dwellings (Del Rio), quoted and re-checked
  10. OSSF Form For Installers Only, quoted and re-checked
  11. Getting a Permit for an OSSF - Such as a Septic System (Texas statewide rule), quoted and re-checked
  12. List of Documents needed for Building Permit, quoted and re-checked

Written October 11, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Del Rio

Del Rio’s own rules

  • Building permitRequired

    New one- and two-family residential construction inside Del Rio city limits.

    • Complete application, two full sets, PDF construction documents, and plan-review fee are required.
    • The permit is reviewed for zoning and technical codes before issuance.
    • Review generally takes 3–5 working days depending on project size and completeness.
    “What will be required for building permit: Complete Application and two (2) full sets and a pdf file of Construction documents.( Including plan review fee)CASH,CHECK,CREDIT CARDS OR MONEY ORDER are accepted”
  • InspectionsRequired

    Construction or work inside Del Rio city limits for which a city permit is required.

    • Work must remain accessible and exposed until approved.
    • The permit holder or agent must notify the chief building official when work is ready for inspection.
    • All permits require final inspection under the residential permit handout.
    “All construction or work for which a permit is required shall be subject to inspection by the chief building official and all such work shall remain accessible and exposed for inspection purposes until approved by the chief building official.”
  • Certificate of occupancyRequired

    Occupancy of buildings, leased space, business premises, business ownership/name changes, and relocations inside Del Rio city limits.

    • The city’s published FAQ states the requirement before occupancy or the listed business changes.
    • The residential and commercial submittal procedures identify the chief building official as approving the certificate; commercial procedures also identify the fire marshal and community health department when applicable.

    commercial certificate of occupancy fee: 70 USD (Per certificate)

    “Yes, a Certificate of Occupancy permit is required before you occupy a building, lease space, change in ownership of a business, change in business name, or before relocating business from one location to another.”
  • Permit feesPublished

    City development, building, inspection, occupancy, plumbing, well, and related permits inside Del Rio city limits.

    • The published schedule is marked last updated July 18, 2025.
    • Residential building fees are $7 per $1,000 of value with a $56 minimum; processing fee is $15 per permit.
    • Inspection fees are $45; reinspection fees vary from $45 to $180.
    • A commercial certificate of occupancy is $70 per certificate.
    • A water-well permit fee is listed at $75 per well.
    • The schedule states septic tanks should be handled through the Val Verde County Health Risk Assessment website.

    residential building permit fee: 7 USD per $1,000 value ($56 minimum) · processing fee: 15 USD per permit · inspection fee: 45 USD per inspection · commercial certificate of occupancy: 70 USD per certificate · water well permit fee: 75 USD per well

    “Residential projects (one- and two-family dwelling units) Per occurrence Per $1,000 value $7.00 $56 minimum”
  • Permit processPublished

    Residential building-permit applications inside Del Rio city limits.

    • Submit a complete application, two full plan sets, a PDF construction document, and the plan-review fee.
    • Plot plans must show lot size, existing and proposed structures, uses, setbacks, and property pins.
    • Floor plans must identify room uses and dimensions and specified building-system details.
    • Plans are reviewed for zoning and technical codes before issuance; complete submissions generally take 3–5 working days depending on project size.
    • All work remains subject to field approval; unused permits receive no refunds.
    • Issued permits become invalid if work does not commence within 180 days or is incomplete after abandonment or suspension for 180 days.

    review time: 3-5 working days (Depending on project size and complete documentation) · permit commencement deadline: 180 days (Permit becomes invalid if work does not commence) · permit abandonment deadline: 180 days (After work commenced)

    “An issued permit becomes invalid if the work on the site authorized by the permit does not commence within 180 days of issuance, or if the work on the site is incomplete due to suspension or abandonment 180 days after the work commenced. All permits require final inspection.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Del Rio or Val Verde County directly.

  • Owner-builder exemption — Owner-builder exemptions for construction inside Del Rio city limits.
  • Minimum dwelling size — Minimum dwelling size inside Del Rio city limits; district-specific numeric standards were not established from the reviewed official sources.
  • Minimum lot size — Minimum lot size inside Del Rio city limits; district-specific numeric standards were not established from the reviewed official sources.
  • Setbacks — Building setbacks inside Del Rio city limits; district-specific numeric standards were not established from the reviewed official sources.
  • Lot coverage — Lot coverage inside Del Rio city limits; district-specific numeric standards were not established from the reviewed official sources.
12 more unanswered
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Septic inspection
  • Off-grid sanitation
  • Well permit
  • Agricultural exemption
  • Driveway access
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Del Rio publishes no rule on the point, not that none exists. Val Verde County’s page lists the county offices to call.