Gonzales County, Texas

Zoning, building permits and septic rules in Nixon, Texas

Nixon is a city in Gonzales County, Texas. 4 rules below are quoted from official sources and independently re-checked, most recently on November 7, 2026. Rules for unincorporated land are on the Gonzales County page.

Answers from the rulebook for Nixon

Nixon’s own rules

  • Building permitRequired

    Residential and commercial construction inside Nixon city limits.

    • Residential building-permit applications must be submitted 10 business days before the requested start date.
    • Commercial building-permit applications must be submitted 15 business days before the requested start date.
    • Construction may not commence until completed approval through Code Compliance Department and Bureau Veritas (BV), if required.
    • Electrical, plumbing, and HVAC permits cannot be issued to an unlicensed person; the licensed contractor must pull the permit.
    • A permit is good for 180 days after issuance; work before approval doubles the permit fee and may result in an ordinance-violation citation.

    residential application lead time: >= 10 business days (Before requested start date.) · commercial application lead time: >= 15 business days (Before requested start date.) · permit validity: 180 days (After issuance.)

    “Construction may not commence until completed approval”
  • Manufactured homesLimited

    HUD manufactured homes inside Nixon city limits.

    • An approved variance by city council is required before the HUD manufactured-home permit can be approved.

    HUD manufactured-home permit fee: 150 USD (Permit approval requires an approved city-council variance.)

    “must have approved variance by city council”
  • Permit processPublished (with conditions)

    Residential and commercial construction permit applications inside Nixon city limits.

    • Residential applications must be submitted 10 business days before the requested start date.
    • Commercial applications must be submitted 15 business days before the requested start date.
    • Construction may not commence until completed approval through Code Compliance Department and Bureau Veritas, if required.

    residential application lead time: >= 10 business days (Before requested start date.) · commercial application lead time: >= 15 business days (Before requested start date.)

    “Residential building permits must be submitted 10 business days prior to requested start date, commercial building permits must be submitted 15 business day prior to requested start date. Construction may not commence until completed approval through Code Compliance Department and Bureau Veritas (BV) (if required).”

Rules another office applies inside Nixon

Nixon does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Septic permitRequired

    On-site sewage facilities, including septic systems and holding tanks, inside Nixon city limits where an OSSF is used.

    • The permitting authority may apply more stringent local requirements.
    • An OSSF can be exempt under the 10-acre rule only if it meets all listed state conditions, including site evaluation, a single-family dwelling on a tract of at least 10 acres, no nuisance or groundwater pollution, all OSSF parts at least 100 feet from the property line, on-property effluent disposal, and no other dwelling on the tract.
    • Emergency repairs listed by TCEQ do not require a permit but must be reported in writing to the permitting authority within 72 hours after repairs begin.
    • Grandfathered OSSFs may not need a permit if installed before a local authorized program or before September 1, 1989, whichever is earlier, and if additional listed conditions are met.

    10-acre-rule tract size: >= 10 acres (Only if all other stated exemption conditions are met.) · minimum OSSF distance from property line: >= 100 feet (Only for the stated 10-acre-rule exemption.) · emergency-repair report deadline: <= 72 hours (After repairs have begun.)

    “A permit and approved plan are required to construct, alter, repair, extend, and operate an OSSF.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Nixon or Gonzales County directly.

  • Owner-builder exemption — Owner-built structures inside Nixon city limits.
  • Building code adopted — Buildings inside Nixon city limits.
  • Inspections — Construction inside Nixon city limits.
  • Certificate of occupancy — Occupancy of buildings inside Nixon city limits.
  • Local zoning — Land inside Nixon city limits.
20 more unanswered
  • Zoning districts
  • Minimum dwelling size
  • Minimum lot size
  • Setbacks
  • Lot coverage
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Accessory dwellings
  • Who permits septic
  • Septic inspection
  • Well permit
  • Mandatory utility hookup
  • Agricultural exemption
  • Shed and accessory-building permit exemption
  • Subdividing land
  • Driveway access
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Nixon publishes no rule on the point, not that none exists. Gonzales County’s page lists the county offices to call.