Greene County, New York
Town of Coxsackie is a town in Greene County, New York. Town of Coxsackie adopts its own zoning, so inside its limits Town of Coxsackie’s rules apply, not the county’s. Septic permits inside Town of Coxsackie come from Town of Coxsackie. 12 rules below are quoted from official sources and independently re-checked, most recently on October 29, 2026. Rules for unincorporated land are on the Greene County page.
Excavation, erection, construction, enlargement, alteration, improvement, solid-fuel heating installation, or demolition of a building or structure in the Town of Coxsackie.
“No person, firm or corporation shall commence the excavation, erection, construction, enlargement, alteration, or improvement of any building or structure, install solid fuel-heating equipment or cause the same to be done, or commence the demolition of any building or structure or any portion thereof without first obtaining a separate building permit from the Building Inspector for each such building or structure; except that no building permit shall be required for:”
Construction for which a Town building permit has been issued.
final inspection deadline: <= 10 days (after applicant notification)
“Upon the completion of the construction for which a permit has been issued, the applicant shall notify the Code Officer, who shall make a final inspection within 10 days of the applicant's notification to the Code Officer to determine if said construction is in compliance with the application and with this chapter and the other applicable laws.”
Construction completed under a Town building permit.
“If said construction complies, the Code Officer shall issue or direct the issuance of a certificate of occupancy.”
Land inside the Town of Coxsackie.
“This chapter shall be known and may be cited as the "Zoning Law of the Town of Coxsackie, New York."”
Installation of an individual sewage-disposal device, and construction, location, or alteration of a structure intended for human occupancy using such a device, inside the Town of Coxsackie.
“No installation of a septic tank, tile field, seepage pit, chemical toilet, privy, pipe or other means of disposal or discharge of sewage or sink wastes shall be begun, nor shall the construction, location or alteration of any structure intended for human occupancy be commenced until an application duly filled out on forms supplied by the Town Clerk and a plot plan showing the intended location of the proposed disposal system to be used in connection with such structure shall have been filed in the Town Clerk's office and approved in the manner hereinafter prescribed.”
Private sewage and sink-waste disposal systems inside the Town of Coxsackie.
“No septic tank, tile field, seepage pit, chemical toilet, privy, pipe or other means for the disposal or discharge of sewage or sink wastes shall be installed anywhere in the Town of Coxsackie except as herein provided.”
Development receiving a density increase under Town Zoning Schedule C inside the Town of Coxsackie.
“Where density increases are permitted in accordance with Schedule C, public water and sewer are required.”
Subdivision plats inside the Town of Coxsackie.
“§ 174-1 Planning Board empowered to approve plats; declaration of policy; title.”
Driveways intersecting Town roads inside the Town of Coxsackie.
culvert-pipe minimum diameter: >= 12 inches (unless waived in writing by the Town Superintendent of Highways)
“All driveways intersecting with Town roads must have a minimum of a twelve-inch culvert pipe in the ditch line at the point where the driveway intersects the Town road, unless this requirement is waived in writing by the Town Superintendent of Highways.”
Building-permit applications in the Town of Coxsackie.
“No building or structure shall be constructed, altered or placed within the Town of Coxsackie until an application for a permit, filled out in triplicate and including the following information, is submitted, reviewed, filed with and a fee paid to the Town Clerk and approved by the Code Officer.”
Town of Coxsackie does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.
Construction in the Town of Coxsackie.
“The Town Board of the Town of Coxsackie, having duly adopted a resolution accepting the applicability of the New York State Building Construction Code, hereby enacts the following chapter pursuant to the provisions of § 381 of the Executive Law of the State of New York and all other applicable laws.”
We looked and could not find an official answer yet. Silence is not permission; ask Town of Coxsackie or Greene County directly.
Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.
Unanswered questions are usually a sign that Town of Coxsackie publishes no rule on the point, not that none exists. Greene County’s page lists the county offices to call.
Off-grid gear
Going off-grid in Town of Coxsackie means bringing your own water and power. The kit we’d start with:
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.