Phillips County, Montana
Town of Saco is a town in Phillips County, Montana. 6 rules below are quoted from official sources and independently re-checked, most recently on November 6, 2026. Rules for unincorporated land are on the Phillips County page.
Town of Saco does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.
State building-permit process for construction inside Saco town limits.
“Yes, projects which are exempt from the building permit process (at the state level) include: 1. Farm or ranch buildings. 2. Private homes and apartments with four or fewer units that do not serve transient guests.”
Construction inside Saco town limits subject to Montana's statewide building-code program.
International Building Code edition: 2024 · International Residential Code edition: 2024
“All of the codes listed below are amended and adopted by: Administrative Rules of Montana (ARM) Title 24, Chapter 301 [...] International Building Code, 2024 Edition - Effective: September 26, 2026 International Residential Code, 2024 Edition - Effective: September 26, 2026”
Projects inside Saco town limits that require permitting under the Montana Building Codes Program.
“Field inspection staff for the programs are positioned around the state to ensure adequate coverage for inspection and regulation of projects requiring a permit.”
Drainfield installation inside Saco town limits when the parcel has a Certificate of Subdivision Approval (COSA).
“Yes, even thought you have a COSA, a drainfield permit is still required by the local health department.”
State building permits for projects inside Saco town limits that are processed by the Montana Building Codes Program.
plan review fee: 35 percent of building permit fee
“A plan review fee must be paid in addition to the building permit fee. The plan review fee is 35 percent of the building permit fee as established in Table 109.2. Both the building permit fee and the plan review fee must be paid before a building permit will be issued.”
State building-permit applications for projects inside Saco town limits processed by the Montana Building Codes Program.
“The plan review process begins when the plans and application are received in the office. The plan reviewer then calculates the valuation of the building and the necessary permit fees and screens the plans to determine if the plans, as submitted, are sufficient to do a plan review.”
We looked and could not find an official answer yet. Silence is not permission; ask Town of Saco or Phillips County directly.
Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.
Unanswered questions are usually a sign that Town of Saco publishes no rule on the point, not that none exists. Phillips County’s page lists the county offices to call.
Off-grid gear
Going off-grid in Town of Saco means bringing your own water and power. The kit we’d start with:
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.