Memphis, Missouri requires a city building permit before construction and compliance with city zoning and subdivision ordinances.1 Memphis has its own zoning districts; the single-family districts require public water and sewer.23 Where private sewage disposal is allowed, Memphis requires a written permit from the Superintendent, and state or county health requirements still apply.4
At a glance
- Building permit
- Required before construction inside Memphis city limits1
- Residential building code
- 2012 IRC, with city modifications and supplements5
- Zoning
- City districts govern land use; confirm the parcel district before designing2
- Water and sewer
- Public water and sewer required in R-1a, R-1b and R-1c districts3
- Private sewage disposal
- City Superintendent’s written permit required where public sewer is unavailable; health requirements also apply64
- Lot coverage
- In R-1b, main and accessory buildings may cover no more than 30% of lot area7
- Floodplain development
- Floodplain development permit required in applicable areas8
Who to call
Building permits
Starting contact for city building-permit applications, zoning questions, and referral to the Building Inspector or floodplain administrator
125 W Jefferson, Memphis, MO 63555
Septic permits
Public sewer availability and referral to the Superintendent for city private sewage disposal approval
Septic permits
Missouri DHSS Onsite Wastewater Treatment Program
State onsite wastewater permitting questions for Scotland County; coordinate with Memphis for private sewage disposal inside city limits
930 Wildwood Dr, Jefferson City, MO 65102
Contact details are copied from each office’s official page and were checked against it on October 12, 2026.
Off-grid gear
Going off-grid in Memphis means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Memphis, MO?
Memphis requires an application filed with the city and a building permit obtained before construction begins.1 The Memphis application needs the city form, a sketch or drawing, and an estimated construction cost; proposed work must meet the city zoning and subdivision ordinances and be likely to comply with city building codes.1 Residential construction follows the 2012 IRC as modified and supplemented by Memphis.5 We could not confirm an owner-builder exemption: ask City Hall to have the Building Inspector identify the requirements for your proposed work before you commit to building it yourself.9
Who handles building permits and inspections in Memphis?
Start with Memphis City Hall at 660-465-7285 or [email protected] for the city application and a referral to the Building Inspector.9 The Memphis permit holder must notify the Building Inspector before construction, and construction requires at least 2 inspections; additional inspections may be required, or an inspection may be waived with written reasons.10 Defects can lead to a stop-construction order.10 At completion, the Memphis building permit serves as the certificate of occupancy only with the Building Inspector’s verification that the required inspections were completed satisfactorily.11
Does Memphis have zoning, and can you live in an RV or tiny home?
Memphis zoning includes agricultural, single-family, multifamily, commercial, industrial and mobile-home districts.2 In the Memphis R-1b district, main and accessory buildings together may cover no more than 30% of the lot.7 Memphis R-1a, R-1b and R-1c lots must have public water and public sewer, so a plan for independent sanitation cannot simply bypass the district’s utility requirements.3 We could not confirm general permission for RV living, temporary camping, tiny-home occupancy or an accessory dwelling in Memphis; ask City Hall for a zoning determination describing the exact proposed use.9 Ask for the parcel’s residential setbacks, minimum lot area, minimum dwelling size and height limits before drawing a site plan.9
How do septic permits and sewer connections work in Memphis?
Where Memphis public sewer is unavailable, private sewage disposal must comply with the city sewer chapter, and the owner must obtain a written permit signed by the Superintendent before system construction.126 A Memphis subsurface soil absorption system requires at least 15,000 square feet of lot area; that sanitation threshold is not a general residential minimum lot size.6 State or county health requirements remain applicable alongside the city approval.4 Missouri DHSS lists Scotland County for state onsite wastewater permitting; contact DHSS and the city Superintendent to establish the approvals for a Memphis address.1314 Call Memphis Water and Sewer at 660-465-2013 to ask about public sewer availability.15
Building a home in Memphis: what are the steps in order?
- Ask City Hall to confirm the Memphis parcel’s zoning district and the standards for the proposed home.92
- Establish public water and sewer service requirements; Memphis single-family districts require both, while private disposal needs city approval where sewer is unavailable.36
- Check whether the Memphis site needs a floodplain development permit before arranging site work.8
- Submit the city building-permit form, sketch or drawing and construction-cost estimate, and obtain the building permit before starting construction.1
- Notify the Memphis Building Inspector before construction, arrange the required inspections and obtain satisfactory inspection verification on the permit for occupancy.1011
What should you check before buying land in Memphis?
For a Memphis lot, check sewer availability before pricing a private wastewater system: public sewer within 100 feet of the property line triggers connection within 90 days after official notice, and private facilities must be abandoned when public sewer becomes available.3 If private disposal is allowed, Missouri requires a construction permit for most onsite system installations or repairs, with some residential exemptions; confirm any exemption rather than starting work on that assumption.16 Memphis also requires its own written private sewage disposal permit.6 Ask City Hall about private-well approval and driveway access, which we could not confirm.9 For land outside Memphis city limits, use the Scotland County guide for the county building-permit answer rather than applying Memphis requirements.17
Watch-outs
- Memphis building approval does not replace the city’s private sewage disposal approval or applicable state and county health requirements.14
- Memphis floodplain development requires a floodplain development permit in applicable areas; ask City Hall for the floodplain administrator before planning site work.89
- Missouri DHSS temporarily suspended onsite sewage application fees effective August 28, 2026; ask Memphis separately about city building and sewage approval fees.189
Sources
- Article II: Building Permits And Code Enforcement (Memphis), quoted and re-checked
- Chapter 405: Zoning Regulations (Memphis), quoted and re-checked
- Article III: Zoning Districts — Use And Regulations (Memphis), quoted and re-checked
- Chapter 710: Sewers and Sewage Disposal (Memphis), quoted and re-checked
- Article I: Adoption Of Building Codes (Memphis), quoted and re-checked
- Chapter 710: Sewers and Sewage Disposal (Memphis), quoted and re-checked
- Article III: Zoning Districts — Use And Regulations (Memphis), quoted and re-checked
- Chapter 415 Floodplain Management (Memphis), quoted and re-checked
- Memphis City Hall (cityofmemphismo.com)
- Article II: Building Permits And Code Enforcement (Memphis), quoted and re-checked
- Article II: Building Permits And Code Enforcement (Memphis), quoted and re-checked
- Chapter 710: Sewers and Sewage Disposal (Memphis), quoted and re-checked
- OWTS Construction Permit Process, quoted and re-checked
- Missouri DHSS Onsite Wastewater Treatment Program (health.mo.gov)
- Memphis Water and Sewer (cityofmemphismo.com)
- OWTS Construction Permit Process (Missouri statewide rule), quoted and re-checked
- Missouri Division of Fire Safety / data.mo.gov – County Building Codes for Missouri (dated 07/01/2026) (2026 county census)
- OWTS Construction Permit Process (Missouri statewide rule), quoted and re-checked
Written October 12, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.