Zoning, building permits and septic rules in Lone Pine Township, Minnesota

Lone Pine Township is a township in Itasca County, Minnesota. Lone Pine Township adopts its own zoning, so inside its limits Lone Pine Township’s rules apply, not the county’s. Septic permits inside Lone Pine Township come from Itasca County (Itasca County Environmental Services - Zoning · 218-327-2857). 3 rules below are quoted from official sources and independently re-checked, most recently on November 10, 2026. Rules for unincorporated land are on the Itasca County page.

Answers from the rulebook for Lone Pine Township

Lone Pine Township’s own rules

  • Building permitLimited

    New structures and listed development activity inside Lone Pine Township subject to Itasca County zoning jurisdiction.

    • The required county authorization is a zoning permit; the official county page does not characterize it as a general State Building Code permit.
    • Permit is required for new structures, change in use, additions, covered alterations, replacements, signs, sanitation systems, shoreland alterations, and home occupations II.
    • Covered maintenance, alteration, or remodeling is limited to work costing more than 50 percent of the structure’s market value.
    • The permit must be procured at Environmental Services before commencing the project or operation.
    • Shoreland alterations are excepted where Section 5.9 exempts them.
    • Applicants must also comply with township, state, and federal rules and obtain state and federal permits where required; mitigation conditions apply to variances, conditional uses, and nonconforming structures.

    covered maintenance, alteration, or remodeling cost threshold: > 50 percent of structure market value (Normal maintenance below this threshold is described in the county zoning-permit checklist as not requiring a zoning permit.)

    “A zoning permit is required for new structures; change in use; new additions;”
  • Local zoningPresent (with conditions)

    Land inside Lone Pine Township, Itasca County, Minnesota; county zoning controls apply because the township is not an incorporated municipality.

    • The current county ordinance index identifies a "Zoning Ordinance (3/1/2025)."
    • The cited county jurisdiction statement excludes incorporated municipalities; it does not establish that Lone Pine Township separately adopted or administers a township zoning ordinance.
    • Zoning permits are conditioned on the applicable county ordinance, and township, state, and federal rules may separately require permits.
    “Itasca County’s zoning jurisdiction does not include incorporated municipalities.”
  • Who permits septicCounty (with conditions)

    Subsurface sewage treatment systems serving land inside Lone Pine Township, including unsewered township land.

    • Itasca County Environmental Services Department administers the SSTS program and the ordinance’s provisions.
    • The county ordinance applies to all county lands except an incorporated area that administers an approved qualifying SSTS ordinance; that exception does not describe Lone Pine Township.
    • State agencies administer specified systems, including systems requiring state approval; state disposal-system permits apply at an average design flow greater than 10,000 gallons per day or a measured daily flow of at least 10,000 gallons per day for seven consecutive days.
    • For non-state-administered systems, a construction permit from Environmental Services is required before installation, construction, replacement, extension, or alteration.

    state disposal-system permit average design-flow threshold: > 10000 gallons per day (MPCA permit for onsite SSTS or group of SSTS on adjacent properties under single ownership.) · state disposal-system permit measured-flow threshold: >= 10000 gallons per day for a consecutive seven-day period (MPCA permit.)

    “The jurisdiction of this Ordinance shall include all lands of the County except for any incorporated area [...]”

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

← All of Itasca County: county rules, score and offices