Whalan is a city in Fillmore County, Minnesota. 5 rules below are quoted from official sources and independently re-checked, most recently on November 5, 2026. Rules for unincorporated land are on the Fillmore County page.

Answers from the rulebook for Whalan

Whalan’s own rules

  • Building permitRequired

    Projects covered by Whalan's City Land Use Permit Application, including a new home, addition, move-in structure, or other listed project inside Whalan city limits.

    • No work may begin before the permit is obtained.
    • If work begins before issuance, a $400 late fee is due in addition to the permit fee.

    late fee for beginning work before permit issuance: 400 USD (In addition to the permit fee.)

    “NO WORK MAY BEGIN UNTIL A PERMIT IS OBTAINED. IF WORK HAS BEGUN ON THE PROJECT BEFORE A PERMIT IS ISSUED, A $400.00 LATE FEE MUST BE PAID IN ADDITION TO THE PERMIT FEE.”
  • InspectionsRequired

    All new dwellings inside Whalan city limits.

    • Footings must be dug and inspected before actual construction of the dwelling begins.
    “SITE INSPECTIONS ARE REQUIRED FOR ALL NEW DWELLINGS: The footings must be dug and inspected before the actual construction of the dwelling may begin.”
  • Permit feesPublished (with conditions)

    Land-use permit projects inside Whalan city limits.

    • New homes, additions, porches, decks, attached garages, moved-in homes, and mobile or manufactured homes are assessed by living area.
    • All other structures are assessed separately.
    • The stated minimum charge is $8.
    • Beginning work before permit issuance triggers a $400 late fee in addition to the permit fee.

    listed residential-project permit fee: per 7.5 USD per 100 square feet of living space (New homes, home additions, porches, decks, attached garages, homes moved in, and mobile or manufactured homes.) · other-structure permit fee: per 5 USD per 100 square feet (All other structures.) · minimum permit charge: 8 USD · late fee: 400 USD (Work began before permit issuance; added to permit fee.)

    “NO WORK MAY BEGIN UNTIL A PERMIT IS OBTAINED. IF WORK HAS BEGUN ON THE PROJECT BEFORE A PERMIT IS ISSUED, A $400.00 LATE FEE MUST BE PAID IN ADDITION TO THE PERMIT FEE. The following projects are assessed $7.50 per 100 square feet of living space; New Homes, Home Additions, Porches, Decks, an attached garage, homes being moved in, and mobile or manufactured homes. All other structures are assessed at $5.00 per 100 square feet. A minimum is $8.00.”
  • Permit processPartial

    Land-use permit projects inside Whalan city limits.

    • The application requires an aerial photograph showing the proposed-construction location.
    • The application calls for measuring specified setbacks.
    • No work may begin until a permit is obtained.
    “An aerial photo of the site must be provided with the application”

Rules another office applies inside Whalan

Whalan does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Well permitLimited

    Specified well and boring types statewide, including inside Whalan city limits.

    • Construction permits apply to some other well or boring types, including monitoring wells and bored geothermal heat exchangers.
    • Applications must be submitted to MDH for review and written approval before work begins.
    “For some other types of wells or borings [...] construction permits are required.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Whalan or Fillmore County directly.

  • Owner-builder exemption — Owner-built residential construction inside Whalan city limits.
  • Building code adopted — Building construction inside Whalan city limits.
  • Certificate of occupancy — Occupancy of structures inside Whalan city limits.
  • Zoning districts — Zoning districts inside Whalan city limits.
  • Minimum dwelling size — Dwellings inside Whalan city limits.
19 more unanswered
  • Minimum lot size
  • Setbacks
  • Lot coverage
  • Building height
  • Living in an RV
  • Camping on your land
  • Tiny homes
  • Manufactured homes
  • Accessory dwellings
  • Who permits septic
  • Septic permit
  • Septic inspection
  • Off-grid sanitation
  • Mandatory utility hookup
  • Agricultural exemption
  • Subdividing land
  • Driveway access
  • Building in a floodplain
  • Short-term rentals

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Whalan publishes no rule on the point, not that none exists. Fillmore County’s page lists the county offices to call.

← All of Fillmore County: county rules, score and offices