Zoning, building permits and septic rules in Ravenna Township, Minnesota

Ravenna Township is a township in Dakota County, Minnesota. Ravenna Township adopts its own zoning, so inside its limits Ravenna Township’s rules apply, not the county’s. Septic permits inside Ravenna Township come from the county and state together. 3 rules below are quoted from official sources and independently re-checked, most recently on November 7, 2026. Rules for unincorporated land are on the Dakota County page.

Answers from the rulebook for Ravenna Township

Ravenna Township’s own rules

  • Building permitRequired

    Any building or structure built or rebuilt inside Ravenna Township; the Township's Building Inspector is the building official administering and enforcing the Building Code in the Township.

    • A permit is required before any building or structure is built or rebuilt in the Township.
    • If a project does not require a building permit under the Minnesota State Building Code, the person must obtain a Township zoning permit before building or rebuilding.
    • All applicable permits required by the ordinance must be obtained before construction of a building, structure, or driveway.
    • Any permit approval is subject to applicant verification that the subject septic system is operational under Dakota County Ordinance 113, including proof of a Water Tight Tank Certification less than three years old signed by a licensed maintainer.
    • Permit fees are assessed for work governed by the Building Code according to the Town Board's fee schedule, plus the Minnesota Statutes section 326B.148 surcharge.
    • A construction, alteration, or expansion permit becomes invalid if work does not begin within 180 days of issuance or is suspended or abandoned for 180 days after beginning; the Building Inspector may grant written extensions of no more than 180 days each.

    water tight tank certification age: < 3 years (Must be signed by a licensed maintainer when permit approval is subject to septic-system operational verification.) · permit commencement deadline: <= 180 days (Work must commence within 180 days after issuance; written extensions may each be no more than 180 days.)

    “A permit is required before any building or structure is built or rebuilt in the Township.”
  • Local zoningPresent (with conditions)

    Land within the boundaries of Ravenna Township, Dakota County, Minnesota.

    • The ordinance divides the Township into districts and makes different regulations for different districts.
    • Where another law, statute, rule, ordinance, resolution, or regulation imposes a more restrictive condition or higher standard, that more restrictive requirement prevails.
    • Land within the Township may require permits or permissions from the Township, County, and State depending on the proposed use; approval by one does not approve another unless expressly stated.
    “Zoning Ordinance 01-2021 Amended thru February 2025”
  • Who permits septicMixed (with conditions)

    Subsurface sewage treatment systems inside Ravenna Township, Dakota County, Minnesota.

    • Dakota County administers and enforces state SSTS regulations within Ravenna Township's shoreland and floodplain areas.
    • Ravenna Township administers and enforces SSTS regulations outside shoreland and floodplain areas, consistently with Minnesota Rules chapters 7080-7083.
    • For the Township-administered area, Ravenna Township incorporates Dakota County Ordinance 113, as amended, but does not administer or enforce those regulations within designated shoreland or floodplain areas.
    • Dakota County Ordinance 113 applies to all county land except municipalities that administer an SSTS ordinance at least as strict as the county ordinance.
    • A single SSTS or group of SSTS under single ownership within one-half mile with design flow greater than 10,000 gallons per day requires an MPCA state disposal-system permit; a permit is also required if measured daily flows exceed 10,000 gallons per day for a consecutive seven-day period.

    state permit design-flow threshold: > 10000 gallons per day (Single SSTS or group under single ownership within one-half mile of each other.) · state permit measured-flow threshold: > 10000 gallons per day (When exceeded for a consecutive seven-day period.)

    “The county also regulates septic systems in the shoreland/floodplain areas [...] Each township (except Randolph and Waterford) [...] has their own municipal septic inspector.”

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.