Brown County, Minnesota
Comfrey is a city in Brown County, Minnesota. Comfrey adopts its own zoning, so inside its limits Comfrey’s rules apply, not the county’s. 7 rules below are quoted from official sources and independently re-checked, most recently on November 4, 2026. Rules for unincorporated land are on the Brown County page.
Structures erected, added to, structurally altered, or moved inside Comfrey city limits.
permit expiration: 1 year (unless construction is actually commenced; extensions are governed by §9.05)
“No structure shall be erected, added to, structurally altered, or moved until a permit therefore has been issued by the Zoning Committee, which permit must be conspicuously displayed on the premises prior to commencing any work.”
Plumbing work inside Comfrey city limits.
“Plumbing Code. The Minnesota Plumbing Code as in effect on July 1, 2002, is adopted, together with all changes and amendments, and the provisions thereof, including the terms defined therein, shall be enforced and in effect in the City of Comfrey, except as otherwise modified pursuant to the terms of the Comfrey City Code.”
Land inside Comfrey city limits in Brown and Cottonwood Counties, Minnesota.
“Residential District: All areas of the City of Comfrey not classified as commercial districts above shall be classified as residential districts until amended or changed in the manner prescribed in this Section.”
Zoning districts inside Comfrey city limits.
“The boundaries of the use districts as specified above shall be delineated on the official zoning map, which shall be on permanent file and available for public inspection in the City Clerk’s office.”
Travel trailers, motorized dwellings, tent trailers, and similar recreational equipment on residential lots inside Comfrey city limits.
maximum living, sleeping, or housekeeping use: <= 7 consecutive days (when parked or stored on a residential lot or in a location not approved for that use)
“No such equipment shall be used for living, sleeping, or housekeeping purposes for more than seven consecutive days when parked or stored on a residential lot, or in any location not approved for such use.”
Comfrey zoning building permits.
“The fee for a building permit shall be established by resolution of the City Council. The Zoning Committee shall issue the building permit only if it determines that the building plans and the application comply with the terms of this Section.”
Comfrey does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.
Residential District lots inside Comfrey city limits.
minimum lot area: >= 7000 square feet (area platted prior to October 1, 1979) · minimum lot area: >= 8400 square feet (area platted after October 1, 1979)
“Lot area shall be a minimum of 7,000 square feet in any area platted prior to October 1, 1979, and a minimum of 8,400 square feet in any area platted after October 1, 1979.”
We looked and could not find an official answer yet. Silence is not permission; ask Comfrey or Brown County directly.
Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.
Unanswered questions are usually a sign that Comfrey publishes no rule on the point, not that none exists. Brown County’s page lists the county offices to call.
Off-grid gear
Going off-grid in Comfrey means bringing your own water and power. The kit we’d start with:
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.