Bolthole Index

Saginaw County, Michigan

Zoning, building permits and septic rules in Marion Township, Michigan

Marion Township is a township in Saginaw County, Michigan. Marion Township adopts its own zoning, so inside its limits Marion Township’s rules apply, not the county’s. Septic permits inside Marion Township come from Saginaw County (Saginaw County Health Department – Environmental Health Division · 989-758-3800). 23 rules below are quoted from official sources and independently re-checked, most recently on October 30, 2026. Rules for unincorporated land are on the Saginaw County page.

Answers from the rulebook for Marion Township

Marion Township’s own rules

Rules another office applies inside Marion Township

Marion Township does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

  • Who permits septicCounty (with conditions)

    Onsite septic systems on land inside Marion Township that is not served by a public sewage disposal system; the county health department issues the permits there

    • Saginaw County Environmental Health Code governs onsite wastewater systems and wells.
    • The township's building permit guidance names the Saginaw County Health Department as the issuer of the septic permit for a new house.
    “onsite wastewater treatment and disposal (septic) systems and onsite water wells are covered under the saginaw county environmental health code.”
  • Septic permitRequired

    Building or replacing a septic system on a site inside Marion Township not served by a public water supply and sewage disposal system

    • The permit is valid for two years and states minimum construction standards; changes must be approved before installation.
    • Septic installers must be registered with the Saginaw County Health Department.
    • A preliminary soil evaluation is available before purchase.
    • If the property is in a regulated floodplain or wetland, an EGLE permit must be obtained before the county health permit is issued.
    “if you own property and are planning to build or need to replace a well or septic system at a site which is not served by a public water supply and sewage disposal system, you are required to obtain a well permit and/or a wastewater disposal permit from this office.”
  • Septic inspectionRequired

    Completed onsite septic systems in Marion Township

    • The county health department collects the inspection; the system must be inspected before backfilling or covering.
    “make a complete inspection of the completed onsite wastewater treatment and disposal system prior to covering”
  • Well permitRequired

    Building or replacing a private water well on a site inside Marion Township not served by a public water supply

    • Well must be installed by a well driller licensed by the Michigan EGLE, per the county health department page.
    • Township guidance says the owner must connect to city water if available.
    “if you own property and are planning to build or need to replace a well or septic system at a site which is not served by a public water supply and sewage disposal system, you are required to obtain a well permit and/or a wastewater disposal permit from this office.”
  • Driveway accessRequired

    New driveway access to a house site in Marion Township; the Saginaw County Road Commission issues the driveway permit

    • The driveway approach must be approved by the Saginaw County Road Commission (or MDOT on a state highway) and the work completed before house construction starts.
    • A passable driveway to the building site must be approved by the township building inspector before construction starts.
    “driveway permit: must be issued by the saginaw county road commission (989-752-6140).”
  • Building in a floodplainRequired

    Development on property in a regulated floodplain or wetland in Marion Township

    • An EGLE fill permit is required in the floodplain (township guidance), and a county health permit cannot issue until EGLE approval for floodplain or wetland sites (county health page).
    • Soil erosion permit may also apply under the county drain office for earth changes of one acre or more or within 500 feet of a lake, stream, or county drain.
    “mdeq fill permit: is required by the michigan dept. of environmental quality (989) 686-8025 ext. 8364 if the property is in the floodplain.”

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Marion Township or Saginaw County directly.

  • Owner-builder exemption — Owner-builder construction of a home in Marion Township
  • Certificate of occupancy — Occupancy of a newly built house in Marion Township
  • Living in an RV — Long-term or full-time RV occupancy on private land in Marion Township
  • Camping on your land — Temporary camping on private land in Marion Township
  • Tiny homes — Tiny homes used as dwellings in Marion Township
4 more unanswered
  • Off-grid sanitation
  • Agricultural exemption
  • Short-term rentals
  • Permit fees

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Marion Township publishes no rule on the point, not that none exists. Saginaw County’s page lists the county offices to call.

← All of Saginaw County: county rules, score and offices