Tyrone Township, Michigan, in Kent County, administers building permits and its own zoning ordinance.12 Township zoning approval must come before a building permit, and new structures requiring a Certificate of Occupancy carry a refundable $500 occupancy fee.34 Kent County Health Department handles septic permits and well permits inside Tyrone Township.56
At a glance
- Building permits
- Township building office; zoning approval comes first13
- Zoning
- Township zoning ordinance applies2
- Septic permits
- Kent County Health Department; obtain approval before a new building served by septic57
- Well permits
- Required for installation of on-site water-supply wells6
- Occupancy fee
- $500 refundable fee for new structures requiring a Certificate of Occupancy8
- Owner-builder
- State licensing exemption for qualifying own-use construction; applicable building permits and inspections still apply9
Who to call
Planning & zoning
Tyrone Township Zoning Application
Tyrone Township Zoning Application
28 E Muskegon St PO Box 275, Kent City, MI 49330
Septic permits
Kent County Health Department -- Environmental Health Division
On-site septic and well permits, site evaluations, and well/septic evaluations
700 Fuller Ave NE, Grand Rapids, MI 49503
Roads & driveways
Kent County Road Commission (KCRC)
Permits for work in county road rights-of-way, including driveways
1900 4 Mile Road NW, Walker, MI 49544
Contact details are copied from each office’s official page and were checked against it on October 11, 2026.
Off-grid gear
Going off-grid in Tyrone Township means bringing your own water and power. The kit we’d start with:
- Water Crystal Quest Filter any source — well, rain, or creek — to drinking-clean.
- Power Bluetti Solar generators and home battery backup for living off the grid.
- Septic Soil percolation test kit Run your own perc test before paying an engineer — the first thing a septic office asks about.
- Water Well water test kit Bacteria, nitrates, hardness — know what the well on a parcel is really pumping.
These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.
Do you need a building permit in Tyrone Township, Michigan?
Start a Tyrone Township home project with the township Building Inspector, and obtain township zoning approval before a building permit is issued.13 For a new structure requiring a Certificate of Occupancy, Tyrone Township requires a $500 refundable occupancy fee before issuing the building permit.4 The fee is refunded when the certificate is issued, but moving into the building before receiving the certificate forfeits the fee.8 Michigan’s owner-builder licensing exemption applies to qualifying construction for the owner’s own use and occupancy on the owner’s property; the exemption does not remove applicable building permits, inspections or zoning requirements.9
Who handles building permits and zoning in Tyrone Township?
Tyrone Township’s Building Inspector is listed at (616) 437-7201 and [email protected]; the Zoning Administrator is listed at (616) 349-0223 and [email protected].110 Use the zoning contact for parcel-use questions and the building contact for construction questions.110 The township zoning application requires a completed application and approval before issuance of a building permit.3 Building and zoning approval do not replace Kent County Health Department septic and well permits inside Tyrone Township.76
Does Tyrone Township have zoning, and can you live in an RV or tiny home?
Tyrone Township has its own zoning ordinance, and subdivision lots must conform to the requirements of the zone where the plat is located.211 Before buying land for an RV, tiny home or accessory dwelling, ask the Tyrone Township Zoning Administrator to confirm the proposed residential use and the parcel’s district requirements.10 We could not confirm Tyrone Township’s private-land RV occupancy, temporary camping, tiny-home occupancy or accessory-dwelling rules; ask the Zoning Administrator for the applicable ordinance provisions.10 We also could not confirm district-specific minimum lot size, minimum dwelling size or setbacks; request those requirements for the actual parcel.10
How do septic and well permits work inside Tyrone Township?
Kent County Health Department administers septic rules throughout Tyrone Township, and a Health Officer permit is generally required before constructing, repairing, enlarging or relocating a sewage disposal facility.57 A new building served by septic must obtain the sewage-disposal permit before the township construction permit can issue.7 New-construction septic applications need a detailed site plan and floorplans, and on-site water-supply well installation requires a separate well permit.126 Permitted septic components generally must remain uncovered and accessible until final inspection and Health Officer approval.13 Kent County requires MISS Dig utility marking before the site visit.14
What are the steps to build a home in Tyrone Township?
Follow the approval sequence for a Tyrone Township parcel:
- Ask the township Zoning Administrator about the intended use and obtain zoning approval before the building permit.103
- For a septic-served new home, obtain the Kent County Health Department sewage-disposal permit before the township construction permit; obtain the well permit for an on-site water supply.76
- Coordinate the building application with the township Building Inspector and budget the refundable $500 occupancy fee when a new structure requires a Certificate of Occupancy.14
- Arrange construction inspections with the enforcing agency and septic final inspection with the Health Officer.1513
- Obtain the required Certificate of Occupancy before moving in to preserve the occupancy-fee refund.8
What should you check before buying land in Tyrone Township?
For an agriculturally zoned Tyrone Township parcel, an agricultural zoning permit is required before constructing any building, structure or storage facility; the site-plan examination fee is $30.4 Do not assume agricultural zoning removes approval requirements.4 For a lot split within a recorded plat, the township process includes a Clerk application, Kent County Health Department information, Planning Commission recommendation and Township Board approval.16 County-road right-of-way work, including driveways, requires a Kent County Road Commission permit.17 Michigan EGLE floodplain review can also apply to river, stream or drain floodplains meeting the state’s drainage-area threshold.18 For land outside Tyrone Township, consult the Kent County guide.2
Watch-outs
- Tyrone Township’s $500 occupancy fee is forfeited if a building is occupied before its required Certificate of Occupancy is issued.8
- Off-grid premises in Tyrone Township still need sewage disposal acceptable to the Health Officer; public sewer availability can also trigger a connection requirement.1920
- We could not confirm an agricultural exemption from Tyrone Township building or zoning requirements; ask the Building Inspector and Zoning Administrator before treating a barn as exempt.110
Sources
- Tyrone Township Building Inspector (tyronetownship.org)
- Planning Commission Ordinance — Zoning powers (Tyrone Township), quoted and re-checked
- Tyrone Township Zoning Application (tyronetownship.org)
- State Construction Code; Fee Schedule — Occupancy permit fee (Tyrone Township), quoted and re-checked
- Sewage Disposal Regulations for Kent County, MI (Tyrone Township), quoted and re-checked
- Septic & Well (Tyrone Township), quoted and re-checked
- Sewage Disposal Regulations for Kent County, MI (Tyrone Township), quoted and re-checked
- State Construction Code; Fee Schedule — Occupancy permit fee (Tyrone Township), quoted and re-checked
- Frequently Asked Questions – Residential Builder (Michigan statewide rule), quoted and re-checked
- Tyrone Township Zoning Administrator (tyronetownship.org)
- Planning Commission Ordinance — Zoning powers (Tyrone Township), quoted and re-checked
- Septic & Well | Kent County, MI, quoted and re-checked
- Sewage Disposal Regulations for Kent County, MI (Tyrone Township), quoted and re-checked
- Septic & Well | Kent County, MI, quoted and re-checked
- MCL 125.1512, Inspection of construction (Michigan statewide rule), quoted and re-checked
- Subdivision Ordinance — Lots (Tyrone Township), quoted and re-checked
- Kent County Road Commission (KCRC) (kentcountyroads.net)
- Floodplains (Michigan statewide rule), quoted and re-checked
- Sewage Disposal Regulations for Kent County, MI (Tyrone Township), quoted and re-checked
- Sewage Disposal Regulations for Kent County, MI (Tyrone Township), quoted and re-checked
Written October 11, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.