Charlotte, Michigan requires a building permit before covered construction, alteration, movement or repair of a building inside city limits.1 Charlotte administers its own zoning; Eaton County’s repeal of county zoning does not repeal municipal zoning authority.23 For a Charlotte parcel without available municipal wastewater service, Barry-Eaton District Health Department handles septic site evaluation, permits and final review.4

At a glance

Building permits
Required before covered work; limited minor-repair exception1
Zoning
City zoning applies inside Charlotte2
Septic permits
Barry-Eaton District Health Department, where municipal wastewater is unavailable5
Minimum lot size
R-1: 8,400 square feet; R-2: 12,000 square feet, subject to schedule notes67
Owner-builder
State licensing exemption for own use and occupancy on own property; building permits still apply8
Wells
BEDHD site evaluation, well permit and final review9

Who to call

Building permits

Charlotte Building & Planning

Charlotte Building & Planning

517-543-8833

111 E. Lawrence Avenue Charlotte, MI 48813

Zoning

Charlotte Zoning Ordinance Information

Charlotte Zoning Ordinance Information

517-543-2750

Septic permits

Barry-Eaton District Health Department — Eaton County Office

Barry-Eaton District Health Department — Eaton County Office

517-543-2430

[email protected]

1033 Health Care Dr. Charlotte, Michigan 48813

Contact details are copied from each office’s official page and were checked against it on October 12, 2026.

Off-grid gear

Going off-grid in Charlotte means bringing your own water and power. The kit we’d start with:

These are affiliate links — we may earn a commission, at no cost to you. As an Amazon Associate, Bolthole Index earns from qualifying purchases.

Do you need a building permit in Charlotte, MI?

Charlotte requires a building permit before a building or structure is erected, altered, moved or repaired.1 Charlotte’s minor-repair exception excludes changes involving structural parts, stairways, occupancy, light or ventilation, ingress or egress, and other regulated features.1 A Charlotte building permit cannot authorize work or land use inconsistent with city zoning, so resolve the proposed use before committing to a building design.1 Michigan’s owner-builder licensing exemption covers a home erected for the owner’s own use and occupancy on the owner’s property; the exemption does not remove building-permit, inspection or zoning requirements.8

Who handles building inspections and zoning in Charlotte?

Charlotte Building & Planning administers and enforces the city zoning ordinance.10 Request a Charlotte building inspection at 517-543-8833 and provide your name, phone number, permit number or job-site address, and inspection type.10 The city department lists the 2015 Michigan Residential Code for residential construction and the 2021 Michigan Building Code for commercial and industrial construction.10 Charlotte’s permit holder must notify the Building Official immediately when authorized work is complete for a final inspection.11 Ask Charlotte Building & Planning for the current application package and building-permit fee before submitting a project.

Does Charlotte have zoning, lot-size rules and setbacks?

Charlotte has city zoning districts, including residential, industrial, conservancy and mobile-home districts.12 Charlotte’s R-1 schedule specifies a minimum lot area of 8,400 square feet and width of 70 feet; R-2 specifies 12,000 square feet and 85 feet, with both subject to the schedule’s cross-referenced notes.67 Charlotte’s R-2 schedule lists a 30-foot front setback, side setbacks of 10 and 12 feet, and a 35-foot rear setback, subject to the schedule notes.13 The city website announces a zoning update; ask Building & Planning which adopted ordinance and map govern the parcel before relying on these dimensions.14

How do septic and well permits work inside Charlotte?

For Charlotte land without available municipal wastewater service, Barry-Eaton District Health Department evaluates the site and issues the septic permit before installation.4 A favorable site evaluation comes before the septic permit application, fee and construction authorization.15 After installation, the owner or contractor must notify BEDHD; the system can be covered only after final approval and an approved tag.16 A residential or business drinking-water well also requires BEDHD site evaluation, a well permit and final review, including required water sampling.9 Call the Eaton County health office at 517-543-2430 about the proposed site.17

Can you live in an RV or tiny home in Charlotte?

We could not confirm Charlotte’s private-land RV occupancy, temporary camping, tiny-home occupancy or accessory-dwelling rules; ask Charlotte Building & Planning about the exact proposed use and parcel. Charlotte’s zoning code does require a building permit for covered building work and prohibits permits for uses inconsistent with city zoning.1 Charlotte also requires a certificate of occupancy before occupying a new or altered building or beginning a new land use.18 Do not treat an RV, small cabin or backyard dwelling as approved accommodation while construction proceeds; request a city determination before including that arrangement in your purchase or construction plan.

Building a home in Charlotte: what are the steps?

  1. Ask Charlotte Building & Planning to identify the parcel’s zoning district and confirm that the proposed home meets city zoning before seeking a building permit.1
  2. Where municipal wastewater is unavailable, arrange BEDHD’s site evaluation and septic permit before installing the sewage system.5
  3. Obtain the Charlotte building permit before starting covered construction.1
  4. Request city building inspections through the published inspection line, and notify the Building Official upon completion for final inspection.1011
  5. Obtain the required Charlotte certificate of occupancy before occupying the new or altered home.18

For land outside Charlotte city limits, consult the Eaton County guide: the county zoning repeal leaves municipal and township zoning authority intact.3

Watch-outs

  • Charlotte’s city website announces a zoning update; confirm the ordinance currently in force with Building & Planning before using the residential dimensional schedule.14
  • We could not confirm Charlotte’s minimum dwelling floor area, agricultural building-permit exemption or current city building-permit fees; ask Charlotte Building & Planning before pricing a project.10
  • Eaton County’s zoning repeal does not repeal Charlotte’s municipal zoning authority.3

Sources

  1. § 82-30 Permits (Charlotte), quoted and re-checked
  2. Charlotte, MI Laws (Charlotte), quoted and re-checked
  3. Resolution to Repeal the Eaton County Land Development Code, quoted and re-checked
  4. On-Site Sewage Systems, quoted and re-checked
  5. On-Site Sewage Systems, quoted and re-checked
  6. § 82-426 Schedule Limiting Height, Bulk, Density and Area by Zoning District (Charlotte), quoted and re-checked
  7. § 82-426 Schedule Limiting Height, Bulk, Density and Area by Zoning District (Charlotte), quoted and re-checked
  8. Frequently Asked Questions – Residential Builder (Michigan statewide rule), quoted and re-checked
  9. On-Site Drinking Water Wells, quoted and re-checked
  10. Charlotte Building & Planning (charlottemi.gov)
  11. § 82-32 Final Inspection (Charlotte), quoted and re-checked
  12. § 82-85 Districts (Charlotte), quoted and re-checked
  13. § 82-426 Schedule Limiting Height, Bulk, Density and Area by Zoning District (Charlotte), quoted and re-checked
  14. Charlotte Zoning Ordinance Information (charlottemi.gov)
  15. On-Site Sewage Systems, quoted and re-checked
  16. On-Site Sewage Systems, quoted and re-checked
  17. Barry-Eaton District Health Department — Eaton County Office (barryeatonhealth.org)
  18. § 82-30 Permits (Charlotte), quoted and re-checked

Written October 12, 2026 from the rules quoted below, each taken from an official source and re-checked by an independent reviewer. This is research, not legal advice: rules change, so confirm with the office before you buy or build.

Answers from the rulebook for Charlotte

Charlotte’s own rules

  • Building permitRequired

    Erection, alteration, movement, or repair of buildings and structures inside Charlotte city limits.

    • Minor repairs or changes not involving structural parts, stairways, construction type, occupancy, light or ventilation, ingress or egress, or other features regulated by the City Building Code, Housing Law of Michigan, or Chapter 82 are excepted.
    • A permit cannot be issued for work or land use inconsistent with Chapter 82.
    “No building, structure, or part thereof shall be hereafter erected, altered, moved or repaired unless a building permit shall have been first issued for such work.”
  • InspectionsRequired

    Work covered by a Charlotte building permit.

    • The permit holder must notify the Building Official immediately upon completion for final inspection.
    “The holder of every building permit [...] shall notify the Building Official immediately upon the completion of the work authorized by such permit, for a final inspection.”
  • Local zoningPresent

    Land inside Charlotte city limits; Charlotte administers Chapter 82 zoning.

    • The code supplement states legislation is current through Ordinance No. 2025-07, passed 7-28-2025.
    “For the purpose of this chapter, the city is hereby divided into the following zoning districts.”
  • Zoning districtsPublished

    Charlotte city zoning districts.

    • The code lists residential, nonresidential, conservancy, industrial, parking, and mobile-home districts.
    “R-1 One-Family Residential District [...] P-1 Vehicular Parking District”
  • Permit processPartial

    Building-permit and certificate-of-occupancy process inside Charlotte city limits.

    • A building permit must precede covered work.
    • A certificate of occupancy must precede occupation of a new or altered building or a new land use.
    • A final inspection is required after permitted work is complete.
    • The city zoning code provides the core process, but the complete application package and current fee procedure were not established.

    certificate processing period: 10 days (if conformity is found)

    “No building, structure, or part thereof shall be hereafter erected, altered, moved or repaired unless a building permit shall have been first issued for such work.”

Rules another office applies inside Charlotte

Charlotte does not set these itself; the county, a health district or the state does, and they apply to every address inside its limits.

Still unanswered

We looked and could not find an official answer yet. Silence is not permission; ask Charlotte or Eaton County directly.

  • Owner-builder exemption — Owner-builder exemption for building construction inside Charlotte city limits.
  • Building code adopted — Building-code adoption applicable inside Charlotte city limits.
  • Minimum dwelling size — Dwelling size in Charlotte residential districts.
  • Living in an RV — RV occupancy on private land inside Charlotte city limits.
  • Camping on your land — Temporary camping on private land inside Charlotte city limits.
6 more unanswered
  • Tiny homes
  • Accessory dwellings
  • Agricultural exemption
  • Building in a floodplain
  • Short-term rentals
  • Permit fees

Each answer was extracted from an official source and independently re-checked against that source by a second reviewer. That is an evidence check, not legal advice. Rules change; confirm with the authority before you buy or build.

Unanswered questions are usually a sign that Charlotte publishes no rule on the point, not that none exists. Eaton County’s page lists the county offices to call.

← All of Eaton County: county rules, score and offices